Stay informed on the latest construction activities at Casey's Pump House and Swan Lake Pump Station. Updates include piping installation, strainer vault construction, pump maintenance, and upcoming projects. Follow along for detailed progress reports.
E N D
Casey’s Pump House Area Piping & Strainer Vault Const. K. Collins / ICW Backbone Piping
Casey’s Pond Conditions for West Strainer Vault Construction, Jan 2107 • All 400 HP Pumps OFF • West Strainer OFF • 3 of 4 100 HP Pumps ON • All 100 HP Pumps Rebuilt and Motors raised above Flood Plain • Each Pump rated at 1500 GPM • C-4 Pump House ON • 1 ea. 1500 GPM Pump out for repairs • ICW System will supply 4300 GPM, should maintain ~65 PSI at FCC. Presenter | Presentation Title
CMTF Pipe Loop work 10-28-16 to 11-11-16 Intake box installed 10/6, Portadam Removal Completed Oct. 14th Delivery of CMTF Pump Station Nov. 29. Comm line install Scheduled for early November Pump Station discharge connection to be completed in November while CMTF Cryo is down Pump Station power Connection to switch at NML by mid December K. Collins / ICW Backbone Piping
Swan Lake Construction Activities Oct. 28 to Nov. 4 Swan Lake Pump Station foundation excavation completed, starting concrete formwork Directionally bored discharge pipe to 16” ICW completed Pine St. Intake Pipe through Pine St Crossing completed Road A-2 Pine St Portadam removed Intake structure complete Road D Pine St Closing Inbound/ Outbound Oct 17 to Nov 7 Detour to Wilson St. Pine St will be open for Lederman Ctr. Road D K. Collins | ICW Backbone Piping
Future Directional Bores through Berm Areas K. Collins | ICW Backbone Piping