MTA beam line installation Weekly Report September 28, 2007 Period covered: September 24 th September 28 th (Week 8). MTA – Week 6. MTA Weekly Report – Week 8. Electrical Work Tunnel Work Termination of load cables 100% complete Termination of the instrumentation 96% complete
E N D
MTA beam line installation Weekly ReportSeptember 28, 2007Period covered:September 24th September 28th (Week 8) Shutdown’07 Week 8 F.G. Garcia MTA – Week 6
MTA Weekly Report – Week 8 • Electrical Work • Tunnel Work • Termination of load cables 100% complete • Termination of the instrumentation 96% complete • Vacuum instrumentation is 44% complete thanks to B. Brooker and Rosie • T&M pulled a 480VAC 3-wire cable from the Linac panel to the new MTA disconnect box (PEI room) • Alignment • Awaiting on the surveyors to rechecked the beam line components based on the latest beam sheet • Mostly corrections will be elevation related • Due to lab priorities, task was delayed a couple of days… • AMG accommodated MTA job the best they could • Currently a crew is in the Linac enclosure Shutdown’07 Week 8 F.G. Garcia
MTA Weekly Report – Week 8 • LCW work100% complete • All magnets connected to the water manifold and valved in. • Vacuum workLinac side has priority until Oct 2nd • Coming along very well… • 95% spool pieces are made and dry-fit • Start immediately connecting the spool pieces after alignment • Effort starts today • All ion pumps in the Linac side (2) are installed • Stand is delivered at the MTA side • Instrumentation group installed MW cans on the stands • Magnificent help from Instrumentation group Oct 1st and Oct 2nd : - Finalize the spool piece connections - Start roughing vacuum as soon as possible - Concentrate in MTA side after Oct 3rd Shutdown’07 Week 8 F.G. Garcia
MTA Weekly Report – Week 8 • Mechanicalinstallation • Beam stop assembled, tested and delivered • Outstanding group effort to meet the deadline • Awaiting the final alignment of the beam pipe thru the shielding wall and installation of the beam valve in order to proceed with the beam stop installation • Expect to be complete 9/28 • Shielding installation • Cable penetration shielding is complete • Safety can lock the penetrations • To Do: shielding around the beam pipe • Awaiting for the beam pipe to be aligned • Material is available and procedure has been developed Oct 1st and Oct 2nd: Finalize the shielding requirements for beam operation in Linac Shutdown’07 Week 8 F.G. Garcia
Linac side Beam Valve #2 Today’s activities Beam Stop BPM (total of 8 BPM system) MTA Q9 MTA Q8 MTA Q7 MW (total of 4 MW system) MTA Q6 Toroid MTA Q5 MTA Q4 Beam Valve #1 Ion pump #2 MTA Q3 MTA Q2 Ion pump #1 Shutdown’07 Week 8 F.G. Garcia MTA Q1