1 / 5

MTA beam line installation Weekly Report September 28, 2007 Period covered: September 24 th September 28 th (Week 8

MTA beam line installation Weekly Report September 28, 2007 Period covered: September 24 th September 28 th (Week 8). MTA – Week 6. MTA Weekly Report – Week 8. Electrical Work Tunnel Work Termination of load cables 100% complete Termination of the instrumentation 96% complete

mauli
Download Presentation

MTA beam line installation Weekly Report September 28, 2007 Period covered: September 24 th September 28 th (Week 8

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MTA beam line installation Weekly ReportSeptember 28, 2007Period covered:September 24th September 28th (Week 8) Shutdown’07 Week 8 F.G. Garcia MTA – Week 6

  2. MTA Weekly Report – Week 8 • Electrical Work • Tunnel Work • Termination of load cables 100% complete • Termination of the instrumentation 96% complete • Vacuum instrumentation is 44% complete thanks to B. Brooker and Rosie • T&M pulled a 480VAC 3-wire cable from the Linac panel to the new MTA disconnect box (PEI room) • Alignment • Awaiting on the surveyors to rechecked the beam line components based on the latest beam sheet • Mostly corrections will be elevation related • Due to lab priorities, task was delayed a couple of days… • AMG accommodated MTA job the best they could • Currently a crew is in the Linac enclosure Shutdown’07 Week 8 F.G. Garcia

  3. MTA Weekly Report – Week 8 • LCW work100% complete • All magnets connected to the water manifold and valved in. • Vacuum workLinac side has priority until Oct 2nd • Coming along very well… • 95% spool pieces are made and dry-fit • Start immediately connecting the spool pieces after alignment • Effort starts today • All ion pumps in the Linac side (2) are installed • Stand is delivered at the MTA side • Instrumentation group installed MW cans on the stands • Magnificent help from Instrumentation group Oct 1st and Oct 2nd : - Finalize the spool piece connections - Start roughing vacuum as soon as possible - Concentrate in MTA side after Oct 3rd Shutdown’07 Week 8 F.G. Garcia

  4. MTA Weekly Report – Week 8 • Mechanicalinstallation • Beam stop assembled, tested and delivered • Outstanding group effort to meet the deadline • Awaiting the final alignment of the beam pipe thru the shielding wall and installation of the beam valve in order to proceed with the beam stop installation • Expect to be complete 9/28 • Shielding installation • Cable penetration shielding is complete • Safety can lock the penetrations • To Do: shielding around the beam pipe • Awaiting for the beam pipe to be aligned • Material is available and procedure has been developed Oct 1st and Oct 2nd: Finalize the shielding requirements for beam operation in Linac Shutdown’07 Week 8 F.G. Garcia

  5. Linac side Beam Valve #2 Today’s activities Beam Stop BPM (total of 8 BPM system) MTA Q9 MTA Q8 MTA Q7 MW (total of 4 MW system) MTA Q6 Toroid MTA Q5 MTA Q4 Beam Valve #1 Ion pump #2 MTA Q3 MTA Q2 Ion pump #1 Shutdown’07 Week 8 F.G. Garcia MTA Q1