160 likes | 282 Views
FMP Update to the Congregation Sunday July 20 and 27, 2014. Meeting AGENDA. Summary of the phases Current status Schedule for Phase 1 construction Sanctuary schedule Lower narthex bathrooms schedule Expenditures and Funding . Architect and Contractors.
E N D
FMP Update to the Congregation Sunday July 20 and 27, 2014
Meeting AGENDA • Summary of the phases • Current status • Schedule for Phase 1 construction • Sanctuary schedule • Lower narthex bathrooms schedule • Expenditures and Funding
Architect and Contractors • Architect: John Faile (Bay Village, Ohio) • General Contractor: Lawler Construction • Lighting Contractor: Vincent Lighting • Technology Contractors: Jeff Frey, NPI
Facility Modernization Program Team Members • Grant Comnick • Doug Olson • Jan Saunders • John Cuciak • Pr. Bishop • Phil Sprague • Charlie Koch • Barb Raynoha • Ron Kear • Craig Jagels • Jeff Frey
What does Phase 1 include? • Sanctuary upgrades: • Expanded platform • Two large screen TV’s • Sound system • Lighting, white wall upgrades • Upper window blinds, window film • Chairs • Emergency exit platform (courtyard) • And more on next slide……
What does Phase 1 include?(cont’d) • Narthex improvements: • Lower bathroom upgrades • Narthex air conditioning • Narthex lighting upgrades • Fireplace upgrade • Fire system replacement • Parking lot lighting upgrade • Electrical upgrade
Current Phase 1 Status • Design decisions are completed for: • Sanctuary cross • Sanctuary platform • Sanctuary large screen TV’s • Sanctuary white wall upgrades • Sanctuary chairs • Sanctuary lighting upgrades • Lower narthex bathrooms • Narthex air conditioning • Narthex fireplace upgrade
Construction schedulePhase 1 • Sanctuary work will be a two-week period, with completion by August 31. • We will worship in the Fellowship Hall during that time period. • Upgrade of lower narthex bathrooms will be a two-week project, completion by August 31.
What’s next (beyond Phase 1) • Improvements in: • Education Wing • Administration Wing • Fellowship Hall & Kitchen • Deferred Items from Phase 1
66% of the funds are committed for this entire project. 87% of the funds are committed for Phase 1. Thank you. FMP Total Funding
Phase 1 Funding Summary • 87% ($349,000) of funds are committed for Phase 1. • $51,000 are still needed for Phase 1 this year. • We have two options: • Additional Pledges in 2014 • Borrow the funds in 2014 • Thank you for your prayerful consideration in 2014.
Total FMP Funding Summary • 66% ($467,000) committed for the total project. • $233,000 (including $51,000 Phase 1) are still needed for the entire project. • Thank you for your prayerful consideration for the remainder of the project as well.