Student Computer Replacement 2011-2015. 3/29/2012. Main Objectives. Student computer fleet that is consistent and reliable Student computer fleet that can be maintained with the resources we can provide Maximize the number and use of computers available to students for academic purposes
E N D
Student Computer Replacement 2011-2015 3/29/2012
Main Objectives • Student computer fleet that is consistent and reliable • Student computer fleet that can be maintained with the resources we can provide • Maximize the number and use of computers available to students for academic purposes • Maintain a reliable presentation station in every classroom
History • Seattle’s voter-approved BEX III and BTA III levies provide funds for student technology upgrades and replacements • Originally presented replacement plan to ETs last March based on plans for VDI deployment • VDI outcome – VDI won’t work in all situations (no longer relying on upgrading GX620s to VDI thick clients) • Now ready to restart with more options for schools andVDI is still an option but deployments have been delayed
Overview of Rollout • Establish a 3.5:1 student to computer ratio in every school • Set minimum for standard of Dell 740 or Intel-based Mac for presentation stations. • Upgrade RAM in GX740s to 4GB • Allow schools a menu of computer hardware choices to meet their identified needs • Final school choices will be governed by a dollar formula based on the 3.5:1 ratio and a standard replacement cost of $1019 for a desktop PC. • Provide for replacement of all projectors and one half of document camera fleet
Allotment • Each school will receive an allotment relative to their student enrollment. Over 9,000 new devices will be deployed over the next two years • Allotment adjustments were made for enrollment variations between March 2011 and October 2011 • Schools that had enrollment reductions were not penalized • Additional computers acquired by schools since last March did not impact their allotment
Schedule • The current schedule is based on the one distributed last March • Schools with large Mac deployments were completed in the summer of 2011 to leverage volume discounts • As in the past, large deployments will be scheduled during school breaks in order to accommodate processing and distribution logistics • Note that the schedule may have slight variations due to vendor production schedules and warehouse volume
Process • A kick-off meeting will be scheduled with each school roughly 6-8 weeks before deployment • An IT and Network Analyst will work with each school on their student technology replacement plan • The Principal submits a plan to Robert Shore with a cc to Fran Clifton and Eric Caldwell • The equipment is ordered • The computers are imaged and deployed • The necessary professional developments are scheduled & held
School Options • Schools receive a cost value based on a 3.5:1 ratio of computers that no longer meet standard (GX620 or older and pre-Intel-based Macs). The school gets $1019 credit for each computer slated to be replaced. • Schools can choose from options list to meet the following needs: • Presentation Stations at least GX740 or better • Aligns with building CSIP and supports school identified interventions • MAP/online testing • Student technology use (standards, access, etc.) • Schools can not repurpose surplus computers for library OPAC use
Option List • PC or Mac desktop • PC or Mac laptop carts • VDI thin OR thick clients • iPad cart (or individual iPads to fill out existing carts) • iPod cart • Note each option has different costs that will impact final numbers of devices for each school
Surplus • Opportunity to remove old equipment without cost • Schools are not encouraged to keep surplused computers, but may do so if they have a plan approved by their Network Analyst and Principal • If a school elects to keep GX620s they will not be replaced or repaired and school will have to pay to surplus them in the future • No equipment older than a GX620 will be allowed on the network once a school’s replacement has been completed