1 / 76

Tubas City Electrical Network Study

Detailed analysis of Tubas city's electrical network, including network elements, consumption patterns, load flow analysis, and improvement strategies to enhance efficiency and reliability.

mbarba
Download Presentation

Tubas City Electrical Network Study

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Tubas ELECTRICAL NETWORK STUDY Prepared by : Omar Abu-Omar Ahmad Nerat Sameed banifadel PRESENTATION TO: Dr.MAHER KHAMASH

  2. Contents : • Chapter 1 : Introduction • 1.1 Improvement the distribution of electrical network • 1.2 Methods of improvement of distribution electrical networks • Chapter 2 : Tubas City Electricity Network • 2.1 Electrical Supply • 2.2 Elements Of The Network • 2.3 Electrical Consumption • 2.4 Problems in The Network • Chapter 3 : Load Flow Analysis • Chapter 4 : Maximum Case • Chapter 5 : Minimum Case • Chapter 6 : Connection point • Chapter 7 : Economical study

  3. Introduction • Improvement the distribution of electrical network • Benefits and advantages to improvement of distribution electrical networks • 1.Reduction of power losses. • 2. increasing of voltage levels . • 3. correction of power factor. • 4.increasing the capability of the distribution transformer. • Methods of improvement of distribution electrical networks 1. swing buses 2.transformer taps 3. capacitor banks (compensation) 4.changing of configuration of distribution network

  4. 2.1 Electrical Supply : • TUBAS ELECTRICAL NETWORK is provided by Israel Electrical Company (IEC) • The main supply for electrical distribution network in Tyaseer • Through an over head transmission line of 33 kv. • The main circuit breaker is rated at (200 A). • The max demand is reached (10MVA).

  5. 2.2 Elements Of The Network : • number of Transformers : 73 Δ/Υ (33/0.4) KV distribution transformers. • And the table shows the number of each of them and the rated KVA : 630 KVA and 400 KVA has tap changer without load= ±5%

  6. The conducters used in the network are ACSR (120mm2 & 95mm2 & 50mm2) • The under ground cable used in the network are XLPE Cu (95mm2 & 50mm2)

  7. 2.3 Electrical Consumption : • The table below shows the total consumption of energy for 5 years .

  8. The daily load curve :We take readings to the load changes during the day, the result gives the graph below : The daily load curve : We take readings to the load changes during the day, the result gives the graph below : The daily load curve we have very important information like: Max demand Load factor The suitable distribution of the load Total energy consumption How to avoid penalties and other important things

  9. 2.4Problems in The Network: • The P.F is less than 0.92% , this cause penalties and power losses. • There is a voltage drop. • There is power losses.

  10. 3 Load Flow Analysis : *Apparent Power Measuring *Power factor and load factor calculations

  11. By using etap power station we starting the study with the original case after the applying the data needed • like power factor and load consumption of power and other data : • The resultant basic information for TUBAS network with out connected the well came as shown in the following table:

  12. The maximum case • 3.1 the mediumvoltages & The low tensionvoltages • The actual medium voltages and low voltage on each transformer is shown in the table below :

  13. Note : the colored values refers to the least low voltages which has more drop of voltages.

  14. Value of maximum loads in table below:(before improvement)

  15. Note : the power factor less than 92% . This causes more penalties on the total bill

  16. SUMMARY • we have to summarize the results, total generation, demand , loading., percentage of losses, and the total power factor The swing current = 240 A The p.f in the network equal 88.3

  17. The maximum load improvement • we have # of methods in order to improve the network for a lot of positive effects such as reducing the cost / kwh . these methods are: • 1- increasing the swing bus voltage • 2- tab changing in the transformer. • 3- adding capacitors to produce reactive power • 4- change the connection of the network

  18. increasing the swing bus voltage • In the network the connection point have the flexibility to increase the voltage on the swing bus up to 5% from the original voltage (33 kv) the new value of the swing bus voltage equal (34.65KV) the run of etab after applying this improvement the data shown in the following table:

  19. This table shows the bus voltage after increasing the swing bus voltage. • But we can't apply this method because the control of swing bus only by IEC

  20. improvement the max. case using tap changing • In this method of tab changing involves changing in the tab ratio on the transformer but in limiting rang which not accede (5% ). • And after we applying this method we have the following result as shown In the table below :

  21. This table show that the volteges of buses after improvement by changing the taps of transformer. The swing current = 258 A

  22. Power factor improvement • Qc = P(tan cos (p.f old)- tan cos (p.f new)) = 957 KVAR • PF new at least = 92% , PF old = 89.5 • The table below shows the voltage level before and after adding the capacitance:

  23. The result of basic information of the network after adding capacitance: The swing current = 251A Origin Cace 258A We note: and the total current decrease . Losses before p.f improvement = 0.485 Mw . Losses after p.f improvement = 0.460Mw .

  24. the voltage level improvement using capacitors

  25. The result of basic information of the network after adding capacitance:

  26. 5 Comparison between three case • 1. the origin case . • 2. power factor improvement case . • 3. improvement using tap.

  27. Minimum case : • Value of minimum loads in table below:(before improvement)

  28. The medium & low tension voltages

  29. The power factor on some transformers is low and we aim to rise both the power factor more than 0.92 and voltages to reach 100% nearly.

  30. summary • we have to summarize the results, total generation, demand , loading., percentage of losses, and the total power factor. The swing current = 95A

More Related