ZACUCE Update. October 24, 2010. ZACUCE . Our mission: To build a Zarathushti cultural center that will bring the community together in a common place, give us a sense of belonging, and help us leave a legacy for the future. Seriously evaluated 20+ properties

melaney
Download Presentation

ZACUCE Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ZACUCE Update October 24, 2010

  2. ZACUCE • Our mission: To build a Zarathushti cultural center that will bring the community together in a common place, give us a sense of belonging, and help us leave a legacy for the future. • Seriously evaluated 20+ properties • Currently have $245K in cash and additional $165K in outstanding pledges

  3. Recent Progress • Purchased land in Mt. Laurel in March 2010 for $225,000 • Building committee: Noshir Karanjia, Erach Patel, Tehmtan Tehsildar &Kersey Vakharia

  4. 808 South Church St., Mt. Laurel

  5. Architect Selection • Cyrus Rivetna Architects, Chicago, Ill. • Completed study of religious buildings of all faiths. • Spent 6 months in India and Iran studying architecture and layouts of all major Atash Behrams and Agiaries • Currently designing Darbe Mehrs in Dallas and Washington DC. • Cyrus has agreed to provide his consultation and designs at no costto ZACUCE.

  6. Conceptual Site Plan

  7. Conceptual Floor Plan Main components: Atrium Dedicated prayer hall Classrooms Kitchen Assembly hall Bathrooms Storage Patio/Garden Backyard open space

  8. Timeline • Initial meeting with architect Aug 2010 • Select engineering contractor Sept 2010 • Finalize schematic design Jan 2011 • Complete civil design and site plan Feb 2011 • Present plan to ZAPANJ members March 2011 • Submit plans for township approval April 2011 • Township review and approval Sept 2011 • Complete architectural and engineering design Dec 2011 • Building permits received Jan 2012 • Construction complete Nov 2012

  9. Building Options • Build it all at once (7,600 sq. ft.) • Includes assembly hall, classrooms, dedicated prayer hall, atrium, kitchen, etc. • Phased approach: Assembly hall in Phase 1 • Dedicated prayer hall and classrooms added in Phase 2 • Phased approach: Classrooms and dedicated prayer hall in Phase 1 • Assembly hall added in Phase 2

  10. Estimated Option Costs • Build All At Once 7,600 sq. ft. $1.2M • Assembly Hall First Phase 1: 6,000 sq. ft $1.02M Phase 2: 1,600 sq. ft$320K $1.3M • Classrooms & Dedicated Prayer Hall First Phase 1: 4,600 sq. ft. $828K Phase 2: 3,000 sq. ft$600K $1.4M

  11. Next Steps • Fundraising begins! • We need to raise at least $800,000 • Dedicated fundraising committee • More to come • ZACUCE to finalize floor plan and determine build approach • Get involved • Lead large or small projects • Outside community contacts • Feedback and comments are welcome

  12. PercisBansal Khursheed Bapasola Diana Dadachanji* Katayun Kapadia Noshir Karanjia* VeeraKaranjia Adi Kasad* *ZACUCE trustee Come Share Your Thoughts • Jehan Kasad* • Ava Lala* • Meher Mistry • Erach Patel • Freny Ranji* • Anoo Sukhia* • Tehmtan Tehsildar • Kersey Vakharia