1 / 37

C E T A S

C E T A S. Preferred Alternative Presentation March 15, 2011 Fern Valley Interchange City of Phoenix, Jackson County Key number: 12723. 1. Project Development Team. Anna Henson, Environmental Project Manager, ODOT Dick Leever, Project Team Lead, ODOT

melia
Download Presentation

C E T A S

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. C E T A S Preferred Alternative Presentation March 15, 2011 Fern Valley Interchange City of Phoenix, Jackson County Key number: 12723 1

  2. Project Development Team • Anna Henson,Environmental Project Manager, ODOT • Dick Leever, Project Team Lead, ODOT • Peter Schuytema, Transportation Analysis, ODOT • Gary Leaming, Public Involvement, ODOT • Mike Baker, Area Planner, ODOT • Nancy Reynolds, Sr. Transportation Planner, URS • Pat Foley, Public Involvement, RVCOG • Brian Sheadel, Designer, ODOT • Joe Strahl, City of Phoenix Public Works consultant • Mike Kuntz, Jackson County • Vicki Guarino, RVCOG • Chris Bucher, FHWA (advisory member) 2

  3. Project Vicinity 3

  4. Area Context and Features • Natural Resources • Bear Creek, • Bear Creek Greenway • Coleman Creek • Payne Creek • Historic Resources • Medford Canal • Arrowhead Ranch 4

  5. Area Context and Features (cont.) Transportation Problem: Congestion on Fern Valley Road, OR 99, and the I-5 ramps. Poor visibility related to the vertical alignment of the I-5 structure. Bear Creek Bridge has structural problems and is narrow which limits traffic capacity. 5

  6. Purpose and Need • Purpose Statement The purpose of the proposed action is to reduce congestion and improve operational conditions at the I-5 interchange with Fern Valley Road, on Fern Valley Road within the City of Phoenix UGB, and on OR 99 near its intersection with Fern Valley Road. In addition, the Bear Creek Bridge is structurally deficient and functionally obsolete. 6

  7. Need for the Proposed Action Congestion at Fern Valley Interchange: Vehicles queue back onto I-5 during peak hours. By 2030, traffic predicted to back up from OR 99 to N. Phoenix Road. Poor sight distance on Fern Valley Road caused by the I-5 overpass. Lack of continuous sidewalks and bike lanes in the project area. Improve safety and operations at Fern Valley Interchange, on Fern Valley Road and OR 99. Correct structural and traffic capacity problems at the Bear Creek Bridge. Purpose and Need 7

  8. Goals and Objectives Goal #1: Ensure project compatibility with land use plans. • Provide for economic & residential growth. • Protect existing businesses and residences. Goal #2: Provide safe and efficient movement of emergency vehicles, school buses & freight. Goal #3: Provide facilities that encourage alternate modes of transportation. • Reduce vehicle/bike/pedestrian conflicts. • Ensure design that’s compatible with future park-and-ride facilities. Goal #4: Provide for easy and/or safe access to existing & planned businesses and residences. • Reduce turn lanes to minimize congestion. • Reduce the number of driveways where appropriate. • Reduce sharp turns and road curvature for truck movements. 8

  9. Goal #5: Ensure design is not cost-prohibitive. Support short-latitudinal crossings of Bear Creek. Minimize right of way acquisitions. Goal #6: Enhance community livability and quality of life. Improve connection between west and east Phoenix. Avoid bisecting neighborhoods. Avoid new, major arterials next to neighborhoods and natural areas. Goal #7: Protect and enhance the natural environment. Minimize disruptions to traffic flow to maintain air quality. Avoid and minimize impacts to wetlands, riparian areas, and native vegetation. Avoid impacts to parks, including the Bear Creek Greenway. Goal #8: Protect the integrity of the Bear Creek Greenway Trail. Minimize construction and long-term impacts to the Greenway, including the creek, trail and adjacent riparian vegetation. Goals and Objectives 9

  10. Agencies Participating in the CETAS Review Process for this Project • Federal Highway Administration • Oregon Department of Environmental Quality • Oregon Department of Fish & Wildlife • Oregon Department of Land Conservation & Development • Oregon Department of State Lands • Oregon State Historic Preservation Office • U.S. Fish & Wildlife Service • U.S. Army Corps of Engineers • National Marine Fisheries Service • U.S. Environmental Protection Agency 10

  11. History of Concurrence Points • CETAS Project Triage: February 17, 2004 • Purpose & Need Concurrence: July, 2004 • Evaluation Criteria: April, 2005 • Range of Alternatives: July, 2007 11

  12. Alternatives Analyzed No-Build Alternative • Traffic congestion would continue to increase at major intersections. • 7 of 16 intersections would be over capacity (vc>1.0) by 2030: • I-5 north off ramp/Fern Valley Road (v/c 1.38) • I-5 south off ramp/Fern Valley Road (v/c 1.37) • OR 99/Fern Valley Road (v/c 0.98) • Impacts to I-5: long traffic queues on Fern Valley Road and OR 99. • Traffic on interchange ramps would continue to spill back onto I-5, creating serious safety conflicts between high-speed and stopped vehicles. • Fern Valley Road: Queues from OR 99 to east of N. Phoenix Road. Travel to connecting roads and properties would be blocked. • OR 99: Queues along most of the route from S. Stage Road to south end of downtown couplet. 12

  13. Alternatives Analyzed (cont.) No-Build Alternative (cont.) • Continued intermittent and substandard bike and pedestrian facilities along Fern Valley Road and OR 99, not meeting ADA requirements. • Emergency services and bus service would be slowed due to congestion. • Continued deterioration of the Bear Creek Bridge; continued poor alignment and poor sight distance on the Greenway multi-use path.

  14. Build Alternative (N. Phoenix Thru): Interchange replaced slightly north of existing. West of I-5, alignment generally follows existing Fern Valley Road to OR 99. East of I-5, alignment shifts northeast and connects with realigned N. Phoenix Road north of Arrowhead Ranch. Anna: You need to provide handout maps and a large map on the wall. Alternatives Analyzed (cont.) 14

  15. Build Alternative Features: Interchange Design Newer interchange type: Crossing Diamond Interchange (aka Diverging Diamond Interchange). Is very efficient. Has narrower footprint than conventional diamond interchange minimizing impacts to businesses in interchange area. Anticipated 50% reduction in crashes since there are no left turns. Alternatives Analyzed (cont.) 15

  16. Build Alternative Features: Fern Valley Road: 2 lanes in each direction except 1-way road just west of Bear Creek (westbound on Fern Valley Road; eastbound on E. Bolz Road) Bear Creek Bridge: Widened from 2 to 4 lanes (from 36 feet to 100 feet wide) Bike and pedestrian facilities: 6-foot shoulders throughout (except 5-foot shoulders on OR 99) Shoulders designated by pavement markings for bike travel 6-foot sidewalks throughout Alternatives Analyzed (cont.) Existing Bear Creek Bridge 16

  17. Build Alternative Features: Includes IAMP measures to preserve interchange capacity. IAMP tools intended to protect function of interchange by helping manage traffic and traffic-generating land uses in developing areas. IAMP Measures include (summary): Capacity expansion and retention Trip Budget Motor Vehicle Trip Reduction Designs and Programs OR 99 Setback on new construction Amendments to City’s comp plan Alternative Mobility Standards at I-5 ramp terminal with Fern Valley Rd Bus Stop and transfer site location/Shared Park and Ride Lot help Alternatives Analyzed (cont.) 17

  18. Alternatives Analyzed — Summary of Impacts • Cultural, Historic and Archaeological Resources • Historic resources on National Register: • Medford Canal—No impact • Arrowhead Ranch—No impact • SHPO concurred that Build Alternative would not adversely affect historic properties (April 2008) • Archaeological resources: • Researched previously recorded sites. • Site visit—Included pedestrian survey along areas not previously inventoried; exploratory subsurface probing where no subsurface visibility existed. • No resources were identified during database and field inventories • Bear Creek Greenway is considered archaeologically sensitive landform. • SHPO concurred on Finding of No Historic Properties Affected--Archaeology (January 2009) 18

  19. Alternatives Analyzed — Summary of Impacts • Socioeconomics: • Business relocations: 4 (coffee stand, restaurant, 2 mobile food vendors) • Residential displacements: 2 (along E. Bolz Road) • Environmental Justice: Analysis indicates no disproportionally high and adverse effects on EJ populations. • Access to area businesses and travel time: • Reduced traffic congestion improves access to area businesses in most cases. By 2030 Build Alternative would reduce travel time from OR 99 to S. Phoenix Road approximately 7 mins. • Build Alternative would require more circuitous route from I-5 to reach the mostly highway- and trucking-related businesses in the southeast interchange quadrant. • Safety improvements: • Bicyclist and Pedestrian safety would improve throughout project • Travel flow to businesses/residences is improved due to less delays and stops. This increases safety by reducing the more severe rear end collisions. 19

  20. Land Use: Lands converted to highway use: 22.1 acres on 42 parcels (mostly land zoned for commercial use; 7.4 acres of land zoned EFU). No Goal exceptions required. Development of land is likely to occur in the interchange area, but this is consistent with local comprehensive plans. 2 CUP’s required (Jackson County and city of Phoenix) IAMP: adopted by the City of Phoenix (February 2011) restricts development that would generate high traffic volumes protecting the interchange and connecting roadway network. Alternatives Analyzed — Summary of Impacts 20

  21. Section 4(f) Resource — Bear Creek Greenway: Build Alternative will realign existing path to remove sharp curve that is under bridge. Alternatives Analyzed — Summary of Impacts 21

  22. Alternatives Analyzed — Summary of Impacts • Wetlands: (see handout) • Total wetlands impacted = less than 4 acres. • Total other waters impacted = less than 0.25 acre. • High quality wetlands impacted: Less than 0.01 acre. • Wetlands delineation report submitted to DSL for the Bear Creek Bridge replacement and received concurrence. • Waterways: • No adverse floodway impacts to any of the creeks in the project area • Bear Creek - Replacement of bridge - would result in similar or slightly improved hydraulic conveyance - remove bridge piers below the OHWM – benefit to the creek - no increase in stormwater pollutants due to treatment facilities • Coleman Creek – no impact with Build Alternative • Payne Creek – no impact with Build Alternative 22

  23. Water Quality: Total future impervious surface area: 28 acres (includes ODOT contributing area) Net new impervious surface area: 11 acres With mitigation, direct impacts to Bear Creek from changes in stormwater runoff would not be detectable. No substantial affects to temperature or bacteria levels in Bear Creek. No violations of in-stream water quality standards in Bear Creek. Build Alternative requires relocation of existing Home Depot stormwater treatment pond. Adequate right of way included to accommodate stormwater facilities. Alternatives Analyzed — Summary of Impacts 23

  24. Alternatives Analyzed — Summary of Impacts • Biology—Aquatic Species: • Presence of SONCC coho salmon in Bear Creek and tributaries (Coleman and Payne Creek) and designated critical habitat. • Biological Opinion (June 2010) issued by NMFS: proposed action is not likely to jeopardize the continued existence of SONCC coho salmon nor result in the destruction or adverse modification of critical habitat designated for this species. The BO also includes an incidental take of SONCC coho during construction. • Proposed action may temporarily impair the EFH for Pacific Salmon during construction. • Includes standard conservation and mitigation measures to avoid, minimize and mitigate potential impacts to aquatic species. • Fish Passage – Plan for Bear Creek Bridge 24

  25. Alternatives Analyzed — Summary of Impacts • Biology—Terrestrial Species: • No terrestrial wildlife species, plant species, or designated critical habitat for terrestrial species protected under the ESA have been identified within the project area. • Noxious weeds prevalent in project area: yellow starthistle, Medusahead rye, Himalayan blackberry) • No Effect Memo for USF&WS trust species was completed.

  26. Hazardous Materials: Build Alternative to impact or be close to 3 sites of high concern that may contain hazmat: residences (potential asbestos), truck stop, and orchard. 3 sites of moderate concern (gas station and farm buildings). Extensive mitigation to reduce potential exposure to hazmat. Air Quality: Build Alternative not expected to cause exceedances of NAAQS for CO, PM10 or PM2.5. Build Alternative meets regional conformity requirements and project-level conformity requirements. Project would adhere to ODOT construction specifications and best construction practices to reduce and minimize air quality impacts. Alternatives Analyzed — Summary of Impacts 26

  27. Visual Resources: Overall project area: Enhances visual cohesion by adding continuous sidewalks. Improved aesthetics of new bridges Constructs new and wider structure over I-5. West of I-5: New approach road to OR 99 from Coleman Creek Estates—affects views to and from residences. Removes trees and two houses on semi-residential E. Bolz Road, a transitional commercial area. Improved visual conditions to and from Greenway multi-use path. East of I-5: Moves major intersection away from neighborhoods east of I-5. New roadway through former orchard Alternatives Analyzed — Summary of Impacts 27

  28. Comments Submitted on Environmental Assessment CETAS – Regulatory Agency Comments No formal written comments submitted from CETAS agencies. 28

  29. Public Involvement Project Support • Build Alternative supported by PMT, PDT, CAC, City of Phoenix and Jackson County. • City of Phoenix adopted IAMP. • Phoenix East Side Traffic Study group supports project. 29

  30. Summary of Public Comments General Project would be very beneficial to Phoenix & other communities. Minimize the cost of water line relocation for the City of Phoenix. Need interchange or overcrossing at South Stage Road. Remove the previous [interim] project on Fern Valley Road. Bikes and pedestrians: Bicyclists and pedestrians will benefit. Provide access to bicyclists and pedestrians during construction. Traffic: Autos and trucks will benefit. Public Involvement 30

  31. Summary of Public Comments (cont.) Businesses: Too many impacts to businesses during tough economic times. Need easier accessibility to truck stop. Design: Realign Fern Valley Road to connect to OR 99 at Cheryl Lane rather than Ray’s Market due to pedestrian safety and traffic flow concerns. Important to repair Bear Creek Bridge and I-5 structure. Process and EA: ODOT executed comprehensive NEPA process with extensive public outreach and testimony. EIS is required for this project due to potential substantive damage to water quality, farmland and air quality. EA should include more build alternatives. EA should include additional quantitative cumulative impact analysis due to urbanization. Public Involvement 31

  32. Preferred Alternative Avoidance and Mitigation Measures: • Reduced typical section on OR 99 to avoid and minimize impacts to adjacent businesses. • Inclusion of additional access road to Coleman Creek Estates to help minimize impacts to residential area. • Traffic management, signage and coordination during construction to reduce impacts to emergency services and businesses. • Shape and placement of Bear Creek Bridge footings designed so Greenway path users have unobstructed of entire path under bridge. • Provide for continued bike and pedestrian connections to Greenway during construction. • Design bridge to be aesthetically compatible with Greenway. • Minimize vegetation removal during construction. 32

  33. Avoidance and Mitigation Measures: Selection of Diverging Diamond Interchange to reduce commercial ROW impacts. Alignment shifted to avoid impacts to historic resources. Section 6(f) replacement of about 0.07 acre for impacts to Bear Creek Greenway properties. During final design sound walls will be evaluated and considered for area adjacent to Bear Lake Estates (residential area located along I-5). Bear Creek Bridge designed to pass 100-year flood event. Stormwater pollutant loads (particularly sediment and dissolved copper) and runoff rates will be reduced through detention ponds, treatment swales, vegetated ditches. Stormwater pollutant loads (particularly sediment and dissolved copper) and runoff rates to be reduced through combination of detention ponds, treatment swales, vegetated ditches or other water quality treatment methods. Preferred Alternative 33

  34. Avoidance and Mitigation Measures: Stormwater pollutant loads (particularly sediment and dissolved copper) and runoff rates to be reduced through combination of detention ponds, treatment swales, vegetated ditches or other water quality treatment methods. Per ODOT stormwater standards, low impact development practices to be implemented first to reduce flows and volumes (e.g., minimizing impervious area and mimicking natural drainage patterns by allowing runoff to flow off side of road). Use of suitable vegetation or substrate filters to enhance stormwater treatment. Mitigate for loss of about 4 acres of wetland functions and area. Likely options include: Creating or enhancing wetlands on-site Creating or enhancing wetlands off-site (purchasing mitigation credits from ODOT’s vernal pool wetlands bank near White City). Use standard construction specifications and practices to minimize impacts to humans and environment. Preferred Alternative 34

  35. Preferred Alternative The Build Alternative meets the project’s Purpose and Need: - reduces congestion in and around the interchange area, Fern Valley Road and OR 99 - replaces the Bear Creek Bridge with a structure two times the width of existing structure increasing capacity along Fern Valley Road. The Build Alternative balances impacts with mitigation opportunities resulting in a net benefit to natural resources. 1. SONCC coho Salmon: new Bear Creek Bridge will remove existing bridge bents out of OHW resulting in better fish habitat 2. Improved Water Quality - treatment of existing stormwater runoff that was not previously treated. 3. Improved Bike and Pedestrian facilities throughout project area

  36. Probable Permits and Approvals Needed: Federal Agencies - NPS: Section 6(f) conversion - USACE: 404 permit State of Oregon Agencies - DEQ: Asbestos-containing building materials and Section 401 - ODFW: Fish Passage Plan - DSL: Removal/fill permit Jackson County - Section 6(f) conversion for impacts to the Bear Creek Greenway - Bridge and stream crossings: compliance with Jackson County Land Development Ordinance (Floodplain Overlay) - CUP for realignment of N. Phoenix Road outside the UGB. City of Phoenix -Comp plan amendment for change to Plan Map, road reclassification and adding project to TSP, Tier 1 project list - CUP for new bridge in Bear Creek Greenway Zoning District Preferred Alternative 36

  37. Schedule Anticipated Schedule • Conclude NEPA Process: June, 2011 • Right of Way acquisition: Under Way (state funds) • Permits/Approvals: June, 2012 • Construction Start: December, 2012 • Construction End: December, 2015 37

More Related