1 / 10

KSC Ground Operations Timeline

KSC Ground Operations Timeline. KSC CGSE TIM. A Technical Interchange Meeting regarding the Cryo Ground Support Equipment was held at KSC November 1 st through 3 rd , 2006 Numerous items were discussed and clarified including:

merlin
Download Presentation

KSC Ground Operations Timeline

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. KSC Ground Operations Timeline

  2. KSC CGSE TIM • A Technical Interchange Meeting regarding the Cryo Ground Support Equipment was held at KSC November 1st through 3rd, 2006 • Numerous items were discussed and clarified including: • Both Off-line and On-line activities will be performed in the SSPF • Generation of preliminary timeline for KSC Ground Operations

  3. Off-line Processing • Overview of Off-line processing: • Unpack, • Mate upper/lower USS • Install EVA Interface Panel • Attach grapple fixtures and EVA handrails • Install Umbilical Mechanism Assembly (UMA) • Install Remotely Operated Electrical Umbilical (ROEU) and foldable arm • Cryo top-off (Restricted access/no integration activities) • Magnet Checkout • Avionics Systems checkout • Perform EBCS alignment w/ Lower USS

  4. On-line Processing • Overview of On-line processing (ISS Interfaces): • Installation into Cargo Element Work Station (CEWS) with 12 degree tilt • Mate ACASS to Payload Attach System (PAS) UMA active half to passive UMA (verify alignment) • Validate interfaces (command, telemetry, power) with Payload Rack Checkout Unit (PRCU)

  5. STS Interfaces • Shuttle Interface verification will need to be performed during the End to End test on the Pad • Facilities for checkout in SSPF have been being disassembled for some time • This includes all verification through ROEU

  6. Initial Processing Off-line Processing On-line Processing On-Dock at SSPF (L-14 weeks) L-10 weeks L-7 weeks Canister loading Move to Canister w/ other Cargo Move to Vertical Processing Facility L-49 days L-32 days

  7. Processing Flow Vertical Processing Facility (VPF)

  8. Pre-launch Activity AMS in canister at VPF, Rotate Vertically, and Transfer to PCR AMS Power-down AMS Install Into PLB AMS Nominal Ground Ops (2000W via PDS, 500-1000W to Vent Pump 1553 (C&C) + RS422) AMS Power-up AMS Nominal Ground Ops STS Rollout to PAD and verification S0024 Hazardous Prop Load Weekend Weekend Weekend L-24 days L-9 days Ordinance Install (AMS powered) L-30 days L-27 days L-20 days L-13 days L-32 days AMS End to End Test AMS to minimum Power (Monitor SFHe Status only, Cryocoolers/ Vacuum Pump off) L-80 hrs Cryo GSE Disconnected And removed (Clear PCR for PLBD Close) AMS Power-off SFHe Top-off L/O Weekend AMS Nominal Ground Ops L-9 min L-88 hours L-30 min L-6 days SFHe Top-off Complete

  9. Scrub Turnaround AMS to minimum Power (Monitor SFHe Status only, Cryocoolers/ Vacuum Pump off) T0 Power On AMS Power-off AMS Nominal Ground Ops Vacuum Pump and Cryocoolers On L/O L1+24 hr Planned Launch (L1) L-9 min L-30 min L1 + 23.5 hr (estimated) L+1 hour (we may do Better) This scenario can be repeated up to 96 hours from first launch attempt (L1) Typically, a maximum of four launch attempts are made prior to re-servicing, so one day may be maintained At AMS Nominal Ops without attempting a launch.

  10. Scrub Turnaround (Recycle) De-Tank the Shuttle PLBD Open L-88 hours AMS Power Cryocoolers and Vacuum Pump on PCR Access, Attach Cryo GSE And perform Top-off Return to Pre-launch Activity Timeline TS TS + 2 days 8 hr TS + 1 hr TS + 9 days TS + 2 days

More Related