1 / 18

Transmission and Distributed Resources; Dynamic Pricing and Advanced Metering

Transmission and Distributed Resources; Dynamic Pricing and Advanced Metering. J. Riley Allen Vermont Department of Public Service February 9, 2007. Is Transmission an Enabler of Distributed Resources or Competitor? Vermont Perspective.

mervyn
Download Presentation

Transmission and Distributed Resources; Dynamic Pricing and Advanced Metering

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Transmission and Distributed Resources; Dynamic Pricing and Advanced Metering J. Riley Allen Vermont Department of Public Service February 9, 2007

  2. Is Transmission an Enabler of Distributed Resources or Competitor? Vermont Perspective • Transmission is an enabler and a complement of distributed resources, however, • Goal is least cost service. • Vermont has taken explicit steps to ensure that distributed resources are also recognized as a complement or substitute for transmission resources

  3. In Docket No. 6860, the Board concluded that it had: • no viable option but to approve a transmission solution for a reliability problem that might have been either deferred or more cost-effectively addressed through demand-side measures or local generation, if there had been sufficient advance planning by VELCO and its owners. • Board Opened Docket 7081 to address this failure

  4. Vermont Context

  5. Vermont Situation • Vermont utilities remain vertically integrated; • Single provider of bulk transmission services (VELCO) • Vermont utilities depend on resources generally far from load • Vermont investments in transmission projects have been fairly inactive until recently. • Vermont Public Service Board approved the Northwest Reliability Project and the Lamoille Loop Project (together are now estimated to cost more than $250 million)

  6. Transmission Challenges

  7. Vermont load zone map Vermont split into five zones • Northern zone @15 MW (on 90 MW base in 2006) • Northwest zone @ 150 MW (on 535 MW base in 2006) • Eastern zone @ 10 MW (on 70 MW base in 2006) • Central zone @ 30 MW (on 280 MW base in 2006) • Southern zone @ 20 MW (on 140 MW base in 2006) Source: VELCO

  8. Challenge to all the key elements in a cohesive Transmission Planning Process • 20 Distribution Utilities (fully integrated owners of VELCO) • Single Efficiency Utility • Single Provider of Bulk Transmission Services (VELCO) • Department of Public Service (Responsible for Statewide Planning) • Competitive market place (energy efficiency, generation services)

  9. Proposed Planning Process and Coordinating Body

  10. Vermont System Planning Committee (VSPC) (Settlement Proposals Docket 7081) • Addresses the fundamental challenge of coordination • DUs, VELCO, VTDPS, Public Representatives, EEU • Addresses transparency through open meetings, notice of meetings, public participation, minutes of meetings posted; • Addresses integration through participation of efficiency utility, PSD and each solution is subject to a presumptive need for market test.

  11. VT System Planning Committee • Comprised of VELCO • 20 Distribution Utilities (4 with subtransmission facilities) • Energy Efficiency Utility • Vermont Department of Public Service • 3 Public Service Board appointments to represent environment concerns, business ratepayers, and residential ratepayers

  12. Vermont Proposed Planning Process

  13. Step 8 Perform Detailed NTA Analysis • Follows Step 3 (preliminary NTA analysis) that determines if full nontransmission alternatives might be viable • Evaluation is primarily centered on societal test • Nontransmission alternatives must meet “equivalence test” (eliminated violations of operating criteria to approximately same level as transmission) • Coordination with ISO-NE on NTA • Includes consultations with efficiency utility and renewable contract facilitator • Includes presumption of a market test.

  14. Key Features of the New Transmission Planning Process • Release to the public of transmission plan on 3 year cycle • Public engagement processes (transmission plan and choice of solutions) • Longer planning horizon (20 years versus 10 year current cycle) • Central coordinating entity (VSPC) • Increased transparency in planning process (VSPC has open records, open meetings, public representatives, web notice of meetings, regular reporting requirements)

  15. Key Features of the New Transmission Planning Process (cont’d) • Involvement of distributed resource providers (Energy Efficiency Utility; Market suppliers through RFPs and Open Door Policy)

  16. THE END

More Related