An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Black Falls Off-Grid Sanitation Construction Black Falls Water Project June-Aug, 2010 Rita Sebastian, Development Planner rita@brandeis.edu Ronald Tohannie, Project Director

  2. The Off-Grid Sanitation Construction was the continuation of the earlier Phase One project that was completed under an Environmental Justice grant from the US EPA. Phase One provided safe drinking water for families who were obtaining their drinking water from unsafe local water sources. The project installed temporary water storage systems in 10 homes in Black Falls and launched a community water hauling coop \ to deliver water from a new pipeline access point constructed by the US Indian Health Service.

  3. The Phase Two project was a collaboration between US Indian Health Service and the Black Falls Water Project, a coop of families in the Black Falls area of the Navajo Nation.

  4. The IHS installed solar-powered underground cisterns, septic systems, and provided the plumbing for the bathrooms. The families were responsible for the bathroom construction and were assisted by the coop.

  5. The project continued the Grassroots Driven Development approach where the local community manages the planning and implementation of development projects.

  6. Work on the project was a joint effort between the community coop and the families. Here, John Knight breaks ground for his foundation.

  7. The coop construction crew consisted of community members, young and old, men and women

  8. The homeowners participated at every step

  9. The families provided food for the workers

  10. Some of the families during construction of their bathrooms

  11. Volunteers from Home Depot assisted the community

  12. Home Depot received an award from Navajo Nation EPA for their work in phase one of the Black Falls project. The partnership continued in phase two.

  13. The extended families contributed expertise and assistance in all phases of construction - not just to the home of their immediate relations, but also to others in the community.

  14. Construction was done to the highest commerical standards: full R16 insulation; electric work conforming to building codes; highest quality materials and workmanship at every step

  15. The commitment to perfection continued to the finishing touches.

  16. Finished bathrooms included bathtup, toilet, sink, hot water, handicap accessibility, flooring, insulation, and electrical

  17. Bathroom construction was finished under budget and ahead of schedule, so some additional work was done: a porch at Katherine Peshlakai's

  18. and a new kitchen at Florabelle Paddock's

  19. The next phase of the project is replication, so that other communities can also have access to safe drinking water and sanitation.