200 likes | 336 Views
WIS 23 Freeway Designation and Corridor Preservation Plan Stakeholder meeting #7 FALL, 2014 County P to WIS 32 Sheboygan County WisDOT Project ID 1440-19-00. Agenda. Introductions Review of study goals and objectives Final recommendations and interim improvements West Segment East Segment
E N D
WIS 23 Freeway Designationand Corridor Preservation PlanStakeholder meeting #7FALL, 2014County P to WIS 32Sheboygan CountyWisDOT Project ID 1440-19-00
Agenda • Introductions • Review of study goals and objectives • Final recommendations and interim improvements • West Segment • East Segment • Central Segment • Discussion of new central segment alternative • What’s Next?
Review of Study Goals and Objectives • WisDOT Goals and Objectives • Preserve the public investment in WIS 23 by planning for long-term mobility and safety • Map the right of way necessary for conversion of WIS 23 to a freeway • Avoid and minimize local and environmental impacts • Work in a collaborative manner with local officials, stakeholders and the public throughout the study process
Review of Study Goals and Objectives • Stakeholder Goals and Objectives • Protect Multi-Modal Investments • Maintain • Access for emergency response • Local road continuity • Consistency with existing plans • Agricultural access across WIS 23
Freeway Designation Segments West Segment Central Segment East Segment
Central Segment County E, O and Pleasant View Right-In / Right-Out Construct right-in/right-out intersection Constructed right-in/right-out intersection Construct right-in/right-out intersection Constructed in 2013
East Segment County M J-Turn Constructed J-Turn Intersection at CTH M Constructed Turn Around Location Constructed Turn Around Location Willow Road Hillside Road HillsideRoad Willow Road Constructed in 2013
West Segment Freeway DesignationRecommended Alternatives Close County P/Pioneer Road access County P connection to Valley Lane Construct connection to County C Close Inez Court access Close Branch Road access Connect Inez Court to Pioneer Road Construct dedicated left turns Connect Branch Road to Inez Court. Inez Court access to remain open. Scheduled for 2015 with WIS 23 Expansion project. Connect Branch Road to County C Phase 1 Phase 2 Phase 3 Phase 4
West Segment Freeway DesignationRecommended Alternatives Construct connection from County P to Valley Lane Construct Valley Lane connection to County C Close County P / Pioneer Road intersection BRANCH ROAD VALLEY LANE BRANCH ROAD PIONEER ROAD Construct connection between Branch Road and County C. Construct connection between Branch Road and Pioneer Road – Scheduled for 2015 Close Inez Court and Branch Road intersections Recommended Alternative - December 2011
East Segment Freeway DesignationRecommended Alternatives Hillside Road Willow Road Close Hillside Road intersection Construct Hillside connection to Sunset Road Construct overpass at Willow Road Construct J-Turn at County M – Completed 2013 Close connection to Sunset Road Construct overpass at County M Construct cul-de-sac on Bridgewood Road south of WIS 23 Construct cul-de-sac on Hillside Road south of WIS 23 HillsideRoad Willow Road Bridgewood Road Phase 1 - 2013 Phase 2 Phase 3
East Segment Freeway DesignationRecommended Alternatives Recommended Alternative - December 2011
East Segment Freeway DesignationRecommended Alternatives Recommended Alternative - December 2011
Central Segment Freeway DesignationPreviously Discussed Alternatives Construct connection between County O and County OJ Close County O/OJ intersection Construct overpass at County E Close Pleasant View Road intersection Pleasant View Road Construct bridge over the Mullett River Kiley Way Rustic Road Kiley Way Construct connection at Rustic Road Relocations Required Plymouth Alliance Church development Pleasant View Road
Central Segment Freeway DesignationPrevious Discussed Alternatives Woodland Road Woodland Road Construct Woodland Road connection from WIS 67 to County E. Pleasant View Road Close Pleasant View Road intersection Close County O/OJ intersection Construct overpass at County E Kiley Way Pleasant View Road Plymouth Alliance Church development
What’s Next? • Public involvement meeting • Preliminary engineering • Environmental analysis • Mapping of right of way • Public Hearing
Project Contacts / Information • Natasha Gwidt – WisDOT Project Manager Phone – (920) 492-4125 Email – Natasha.Gwidt@dot.wi.gov • Project Information Website http://www.dot.wisconsin.gov/projects/ne.htm Go to the WIS 23 Corridor Preservation Study button.