1 / 11

LSS Review - RF System Installation: Status & Worries

This review provides an update on the installation progress, status, and concerns regarding the RF systems in the LSS4, including ACS, ADT, and APW equipment. The article highlights the main activities, worries, and potential impacts on the LSS installation if planning is not respected. Conclusions are drawn regarding the readiness of the ACS, ADT, and APW systems for installation.

michaelae
Download Presentation

LSS Review - RF System Installation: Status & Worries

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LSS Review - RF O. Brunner on behalf of the RF group

  2. Summary • UX45 – RUX45 Installation • Status & Worries  Interactions with LSS installation • ACS, ADT & APW Equipment Preparation Status • Conclusions

  3. 3 RF systems in LSS4: ACS - ADT - APW ACS APW APWL – RF APWT - BI APW APWL – RF APWT - BI ADT ADT

  4. UX45 – RUX45 Installation • Main activities: • Water cooling • Civil Engineering • Cabling • Wave guide installation • Ventilation  Might affect the LSS installation if planning not respected By e.g.: UX45-RUX45 cabling=> WG installation => SC modules installation

  5. Main worries – 1 (Civil Engineering) • Shielding wall in UX45 • Two passages used for QRL installation in the junction regions now being closed • Solution approved by SC/RP: Solid bricks • Problem: Non conform “bricks” used instead • “Solution” proposed by TS/CE: additional layer of bricks • Wall to be rebuilt? Waiting for SC/RP approval • Main worries: • Might affect LSS installation planning • Wall => Cabling => WG => SC modules • Personal protection during cavity commissioning • Equipment protection (cavity control system will be installed along the wall)

  6. Main worries – 2 • RUX45 Roof • Roof needs to be partially closed (on each side) prior to SC modules installation: Roof  RUX45 air cooling units Cryogenic distribution lines to SC modules  (WG)  SC modules • In order to follow up the LSS installation planning (H. Gaillard): • Roof parts must be ready by beginning of May • Roof installation: mid-May • Ventilation: 8 wks (?) • Cryogenic lines installation 4 wks • SC Modules installation mid-July

  7. ACS System Equipment • Equipment/Status: • 100kV/40A LEP Power Converters: • 3/4 already checked by AB/PO • 4 HV bunkers (UX45) + equipment (modulators, crowbars, ..): • equipment in preparation. Ready for installation this summer • 16 high RF power stations (UX45): • pre-installation in progress at CERN • wave guide system: • 60% already mounted. Waiting for end of cabling campaign • 4 SC modules (4 cavities each) + 1 spare module: • now being tested and prepared in SM18 • will be ready for installation mid-July (as planned) despite all tuning system problems UX45

  8. ADT System Equipment(CERN – JINR collaboration) • Equipment/Status: • All 20 vacuum tanks and supports delivered to CERN • 19 tanks & all electrodes cleaned and leak tested • 18 kickers assembled (bake out finished by mid-April) • Ready for installation as planned (16 kickers needed by mid-July)

  9. APWL – pick ups • Equipment/Status: • Prototype built & tested • One pick up installed in SPS (reference) • 6 LHC pick ups now being built: • Ready by mid-April • Calibration done by mid-May • Bake out finished by mid-June • Ready for installation: end of June • APWT? Built by BI. Late delivery might affect vacuum activities (bake out in particular)

  10. Bakeout in LSS4 • SC cavities • Absorbtion on cold surface from neighbouring sectors (cryo-pumping) => Increased dynamic losses, multipactoring => Difficult reconditioning after warm-up In test stands we need 10E-7/ 10E-8 to operate, limited volume (cavity & cut off tubes) Need better in machine due to larger volume (10E-9..?) • Electronics: • Single event upsets SEUs from beam gas collisions are a concern • Effect proportional to vacuum: => With 10E-8 mbar we would have between 10 and 100 SEUs per year in all LLRF systems in UX45(Rough estimate) Bakeout essential !

  11. Conclusions • UX45 & RUX45 Installation • Still many interdependent co-activities • RF Systems: • ACS modules should be ready on time despite many tuning problems discovered recently • ADT kickers: will be ready on time for installation • APW pick ups: will be ready on time for installation • APWT? If late will affect vacuum activities (bake out)

More Related