270 likes | 279 Views
Diamond RF Status Morten Jensen. ESLS RF2004. Latest constructional Status. Photo. by Angelos Gonias, DLS, Aug. 30 th 2004. Buildings Status: Office Block. Contractual completion Dec. 12 th. Buildings Status: Synchrotron. Linac tunnel. Booster tunnel.
E N D
Diamond RF Status Morten Jensen ESLS RF2004
Latest constructional Status Photo. by Angelos Gonias, DLS, Aug. 30th 2004
Buildings Status: Office Block Contractual completion Dec. 12th
Buildings Status: Synchrotron Linac tunnel Booster tunnel Concrete works and painting complete, A/c ductwork and survey monuments in place DLS has taken over control of these areas.
Buildings Status: Synchrotron Storage ring tunnel Concrete work complete (apart from access zone to inner area) Painting of walls, floors and soffits in progress A/c ductwork and survey monuments being installed
Buildings Status: Synchrotron Experimental Hall Concrete slab complete (apart from access zone to inner area) 3 cranes installed and operational
General RF Plant Cryogenics Waveguide RF amplifiers Cavity location Rack mounted equipment Platform LLRF
Reminder of Key RF Requirement Operating Frequency 500 MHz Number of Cavities 2 (3 eventually) Superconducting Technology IOT based amplifiers 300 kW each WR 1800 waveguide 450 W Liquid Helium Refrigeration plant
Amplifier Update – 3 off amplifiers from Thales Air and water cooling calibrated Low power calibrated Combiner set up and low power balanced IOT switch-on next week Problems encountered Thales Switches in switching modules changed Poor match on reject loads Delayed delivery Typical calibration and wiring etc DLS Delay on drive amplifiers Delay to hand over of area Serious delay to water cooling supply
Amplifier Update Cont. Switchless combiner Reject load Hybrid combiners IOTs
Amplifier Update Cont. Hot off the Press!! Coax load return loss (40% glycol) 28 dB or better Combiner (IOT inputs) return loss 33 to 39 dB Isolation between IOTs 30 dB
Amplifier Update Cont. 300 kW load 300 kW Circulator
Amplifier Update Cont. PSU Delivery by end of Dec 2004 Installation to start in January 05 Testing with water End of Feb 05 Secondary water circuit
Cavity Update – 3 off cavities from ACCEL Cavity straight – based on Cornell type cavities Taper 5:1 or better Increased thickness of waveguide and stiffer grade of Niobium Multi-channel transfer lines for helium supply Space limited, hence mechanical modifications to inter cavity pieces and boot-box
ACCEL Update Rust on cavity cells
ACCEL Update cont. DLS Cavity components
ACCEL Update cont. Vertical test of CLS modules at Cornell
Drive Amplifiers – 9 off from Wessex Electronics 500 W IOT Drive Amplifier and Control Unit • Designed to deliver 500 W at 500 MHz CW • Control Unit φ & G control allow balancing of all four drive amps • Control unit provides remote control of φ & G settings and system monitoring
Drive Amplifiers cont Performance Data • Wessex Electronics manufacture test results:- • Nominal Gain 57 dB (ie 0dBm for 500 W O/P) • SS Gain Flatness 0.3 dB (over 4 MHz bandwidth) • LS Gain Flatness 0.15 dB (over 4 MHz bandwidth) • Max output power @ 500 MHz 509 - 540 W • Harmonic Content -50.8 dBc • Spurious @ 0 dBm input -75.6 dBc First completed unit is with Thales for IOT testing. No testing at DLS yet!
Waveguide • Order placed with Microwave Marketing (MEGA) for two waveguide runs • Each run includes • 3-stub tuner • Short circuit switch • Two flexible sections • Arc detector • Reflectometer (dual coupler) • Camera port • Delivery by end of December 2004
LLRF - Phase, Gain and frequency control Master Oscillator • Phase noise specification is being derived from allowable bunch jitter & SNR required for cavity regulation • Possible sources are: MA2040, SML01, PTS620 • Main parameters: • Amplitude regulation 0.5%, resolution 0.05% step • Phase stability 0.2°, resolution 0.5° step • Dynamic range 26 dB • Variable control of bandwidth • +/- 180° static phase control
LLRF • 5 Tender Returns received and under evaluation • Wide variety of implementations including: • IQ mod/demod, analog conditioning, VME control • Amp/Φ detection, possible IF, digital control (powerPC), IQ remod • Amp/Φ detect, VME DSP control • Cartesian loop (amps & IOT) + cavity loop: Amp/Φ detect, DSP Matlab model of cavity and RF plant is being developed to: • understand cavity drive requirements • optimise LLRF control loop dynamics • obtain transfer function from MO to cavity
Cryogenic Plant – Turn key contract with Air Liquide Refrigeration (Helial 2000) 450 W Sufficient for two (and possibly 3) cavity operation Design for cryostat pressure of 1.2 bar A Single compressor with variable frequency driver 2000 L liquid helium dewar 3 off 8 m buffer tanks (liquid equivalent ~ 2000 L) Multi-channel transfer line to ACCEL Valvebox Atmospheric heat exchanger for warm-up and cool-down Permanent gas analysis cabinet Additional entries on Dewar for superconducting Wiggler System being designed for possible upgrade for further coldbox
Cryogenic Plant Helial 2000 coldbox SRRC 1 (similar to Diamond installation) Buffer Tanks
Detailed RF Results and performance ESLS RF 2005!
Summary • Building – related to RF • Access to RF Hall on 29th October • Chilled raw water supply late (August 2005?) • Install temporary chiller with associated pipe work • Platform to be installed by end of Dec (Nov?) • RF Plant • AL to make first delivery of compressors by end of Dec • Thales to deliver by end of Dec • Full complement of drive amplifiers by end of Dec • Remaining cryo plant March/April 2005 • Cavity 1 delivery April 2005 • Key timescales • Thales Installation to start January 2005 • Amplifiers commissioned by 25th April – 12 July 2005 • LN2 commissioned by 25th March (from Dewars) • Cryo plant installation to start 13th April 2005, commissioned by 13th June • First cavity fully tested 1st August, 2nd by 20 August
Thanks to Alun Watkins Matt Maddock Adam Rankin Simon Rains