1 / 28

It’s All About the Risk: Planning for Trunk Sewers Using the RAMCAP J100 Risk Standards

Learn about the importance of risk planning in managing trunk sewer systems using the RAMCAPJ100 risk standards.

michellel
Download Presentation

It’s All About the Risk: Planning for Trunk Sewers Using the RAMCAP J100 Risk Standards

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. David J. Kerr | GHD It’s All About the Risk: Planning for Trunk Sewers Using the RAMCAPJ100 Risk Standards

  2. Introduction • Risk taking is part of everyday life both work and personal: • When we make decisions we consider the possibility of what could happen and the potential consequences • Sometimes we do robust evaluations of both, but • Most of the time we just wing it!

  3. Background: Trunk Sewer System • Peel’s Infrastructure Challenges • 2.5 Million residential and commercial customers • Major airport • 286 KM (178 miles) Trunk Sewers (>750 mm or 30 inches) • 12.5 KM (7.8 miles) Force Mains • Growth • Limited redundancy in the system • Limited funds for rehabilitation/maintenance Image placeholder

  4. Corporate Asset Management Planning • Initiative supported by CAO and Regional Council • Conducted a risk assessment of all Regional assets and defined Level of Service to customers • Provide recommendations for funding for asset management at a department level • Goal: Improve planning and prioritization of infrastructure across the organization Image placeholder

  5. AWWAJ100-10 Risk Management Approach • Project Objectives: • Characterize risk associated with trunk sewers and force mains • Develop risk management plans for high risk/critical assets • Develop a long-term capital plan to reduce overall risk • Develop a risk tool to repeat and update risk assessment 1 2 3 4 • AWWAJ100-10 Standard • Risk Analysis and Management for Critical Asset Protection (RAMCAP) • For Risk and Resilience Management of Water and Wastewater Systems

  6. Risk Management – AWWAJ100-10

  7. Risk Management – ISO 31000

  8. Asset Characterization • Simplify system in to segments • Assign identifiers to each segment • Maps of segmentation and identifiers by sewer shed • Rationale • Appropriate size to create meaningful risk profile • Commensurate with Budgets and Capital Programs • Existing data and information platforms • Hydraulic model • CMMS • GIS • How the Region may use risk profiles • Planning • Capital budgets and delivery • Operations and Maintenance

  9. Threat Characterization • Threat events considered based on: • Events identified by the Region – RFP • GHD Supplemented (Design, Construction, Operations, Geotechnical, Structural) Risk = Likelihood (or Probability) xConsequence or Risk= (Likelihood x Vulnerability) x (Consequence x Resilience)

  10. Threat Categories Threat Events • Natural Disasters • Third Party Damage • Proximity to Dangerous Sites • Operational • Pipe Breakage / Physical • Design / Construction

  11. Threat Category & Events

  12. Likelihood Threat Matrix

  13. Threat Likelihood Ratings

  14. Threat Vulnerability

  15. Consequence Matrix

  16. Consequence Financial

  17. Modeling Methodology • InfoWorks • Utilized model previously developed • Simulated 25 year return storm • Current System • Used model output to asessprobability of failure • d/D • Velocity • Flow Rate • Froude Number • Capacity • Number of customers upstream

  18. Total Risk Results

  19. Total Risk Results • Why? • Installed prior to 1996 • Shallow cover • Under a stream (no protection) • Low velocity • Reduced conveyance capacity • Hard to maintain (no CCTV) • Subject to root intrusion • Surcharged • HGL at surface during 25 year storm.

  20. Risk Assessment – 2017 Risk Results

  21. Mitigation Strategies – Network Level Programs • Replace / extend life (Twinning) • Close Monitoring • Select Contingency Planning • Run to failure – gear up for quick response • Select emergency plans in place • Update SOPs (as required) • Design / Construct • Operational (cross / inter zone connections) • Maintenance (inspections, signage, CA) • Select contingency planning • Select emergency planning (Stakeholder Communications) • Status Quo • Select emergency plans in place • Review maintenance plans

  22. Mitigation Options and CBA Master Plan

  23. Risk Assessment – Overview • Resilience • Operational • Maintenance • D & C $

  24. Program Planning Capital Works Team Approach for the Application of RAMCAP Benefits Challenges • Endorsement from Senior Management • Knowledge sharing between Program Planning, Operations and Capital Works • Understanding and buy-in with the scope and the deliverables • Clarity on process • Different priorities needed to be focused to a common goal • Understanding that high consequences does not necessarily mean high risk. Operations

  25. Data Approach: Top Down and Bottom Up Benefits Challenges • Calibrated hydraulic model to evaluate hydraulic consequences of failure • GIS database with system characteristics to feed into vulnerability analysis • A lot of unknowns in terms of condition • Data gaps and inconsistencies

  26. Next Steps 1 Risk mitigation planning 2 Incorporate outputs into the asset management planning and budget process 3 Ongoing QA/QC of data in GIS 4 Regular updates of risk assessment using risk tool 5 Risk assessment of other asset classes

  27. Take-Aways • Analysis is scalable to small and large utilities • Can be done incrementally over time • Risk without modeling • Hydraulic modeling • With & without GIS • Key step towards a full asset management plan • Defendable and repeatable • Emphasizes the need for good data • Can help unify different groups within your organization

  28. David J. Kerr | david.kerr@ghd.com Q&A

More Related