100 likes | 203 Views
CapX 2020 Transmission Plan: Ensuring Reliable Electricity. Need for Reliable Electricity. Projected Population Growth: 1.3 million by 2050 www.demography.state.mn.us Projected Job Growth: 500,000 new jobs by 2012 www.deed.state.mn.us
E N D
CapX 2020 Transmission Plan: Ensuring Reliable Electricity CapX 2020 - 9/15/2014
Need for Reliable Electricity • Projected Population Growth: 1.3 million by 2050 • www.demography.state.mn.us • Projected Job Growth: 500,000 new jobs by 2012 • www.deed.state.mn.us • Projected Electric Demand Growth: 4,500-6,300 MW by 2020 • CapX 2020 projects will ensure the region has reliable electricity to power homes, businesses and farms for decades to come • Transmission will enable more wind and renewable energy to come on-line CapX 2020 - 9/15/2014
Project Groups CapX 2020 - 9/15/2014
Group I Projects • Four lines work together to ensure reliability for the region • Lines meet most urgent need • Lines will serve as outlet for whatever generation resources are built (These corridors are preliminary) CapX 2020 - 9/15/2014
Group 1 Project CapX Brookings, SD –SE Twin Cities • Improves reliability in West Central Minnesota, Minnesota River Valley and Twin Cities; access to new generation, including wind • Scope: approx. 250 miles, 345 kilovolt • Proposed in-service: 2012-2014 CapX 2020 - 9/15/2014
Lyon Cty CapX 2020 - 9/15/2014
Brookings-Twin Cities 345 kV Studies • Based on SW MN→Twin Cities EHV Development Electric Transmission Study • Completed November 2005 • Additional studies • Generation Alternative • System Adjustments: MISO Queue additions – Lake Marion Xfmr Overload • Combined CapX Group I Loss Analysis • Local Load Serving • Marshall, Franklin, Lake Marion, New Ethanol Loads • Underlying system study CapX 2020 - 9/15/2014
Additional CapX Efforts • Cost Allocation: MISO RECB Analysis • MISO: Baseline Reliability Study – MTEP • Communications Team has been presenting the projects at several county & township groups along the potential route. • CapX team filed Exemption Filing, Comments regarding the filing have been received from DOC, NAWO, Windustry, Overland Law Office & Prairie Island Indian Reservation. • Notice Plan filing before CON Filing. 30 Days before CON Filing. Permitting team will determine when to file Notification Plan when CON is nearing completion. CapX 2020 - 9/15/2014
Q3 2006 Q4 2006 Q1 2007 Q2 2007 Q3 2007 Q4 2007 Q1 2008 Minnesota PUC CON Timeline Implement NPs File Notice Plans Notice PlansApproved Opportunities for Public Involvement CON Issued Prepare CON File CON Hearings Briefs Reply Briefs CON Review Data Requests Environmental Review Project Communications Route Development for All Four Projects Agency/Gov’t Consultations Public Meetings Separate but coordinated efforts Oct 4, 2006 CapX 2020 - 9/15/2014
Contacts • Randy Fordice—763-241-2463; rfordice@grenergy.com • www.CapX2020.com CapX 2020 - 9/15/2014