Broadmeadow Way Greenway between Donabate and Malahide Linda Lally, A/Senior Executive Engineer Howth/Malahide Area Committee Meeting, 6th December 2017 Planning & Strategic Infrastructure Dept
Broadmeadow Way Project - Background • CDP Objective • Critical link in the overall Fingal Coastal Way • Broadmeadow Estuary Protected Status • Irish Rail viaduct collapse 2009
Broadmeadow Way – Project Objective • Trail of high amenity value • Connectivity • Construction feasibility • Environmental sensitivities • Safety • Sustainability
Broadmeadow Way – Route Planning & Strategic Infrastructure Dept.
Broadmeadow Way • Start/Finish points • Malahide Castle • Newbridge House • Linkages- Sutton to Malahide cycleway • Linkages –coastal route to Balbriggan
Broadmeadow Way – Malahide Planning & Strategic Infrastructure Dept.
Broadmeadow Way-Malahide Dept. Name
Broadmeadow Way-Bissets Strand Dept. Name
Broadmeadow Way-Haul Road Dept. Name
Broadmeadow Way-Viewing Platform Dept. Name
Broadmeadow Way- Pedestrian Bridge Dept. Name
Broadmeadow Way-Donabate Dept. Name
Broadmeadow Way-Donabate Dept. Name
Broadmeadow Way – DDR crossing Dept. Name
Broadmeadow Way – Key Issues • Engineering • Planning/ Environmental/ Legal • Stakeholder Consultation • Irish Rail • NPWS • Landowners
Broadmeadow Way –Next Steps • Finalise EIAR, NIS • Application for approval to An Bord Pleanála • Detailed design • Source funding • Tendering • Construction