KM 71.00. KM 72.00. Package7 EWE & FE of 38L to 77L of DBM-71 from km 40 to 72 main, minors & sub-minors & FCs. 162943 Ac. Works Completed Works under execution EPC works. 129450 Ac. KHAMMAM (68,914 Ac.).
E N D
KM 71.00 KM 72.00 Package7 EWE & FE of 38L to 77L of DBM-71 from km 40 to 72 main, minors & sub-minors & FCs 162943 Ac Works Completed Works under execution EPC works 129450 Ac KHAMMAM (68,914 Ac.) Package6 EWE & FE of 23R to 37L of DBM-71 from km 32 to 40 main, minors & sub-minors & FCs 56069 Ac KM 55.00 KM 39.00 Package 3 EWE & FE of minors & sub-minors & FCs from KM 45 to 71 of DBM-60 KM 40 Package5 EWE & FE of 1R to 22L of DBM-71 from km 0 to 32 main, minors & sub-minors & FCs DBM 60 Package 4 EWE & FE of dbm-69 FROM km 0 TO 39 including main, minors & sub-minors & FCs 15,000 Ac KM 34.4 10996 Ac 10249 Ac Package 2 EWE & FE of minors & sub-minors & FCs from KM 0 to 45 of DBM-60 KM 13.50 KM 16.00 DBM 69 KM 13.00 KM 9 7173 Ac DBM 71 KM 20 KM 20 773 Ac 808 Ac 3841 Ac. 4071 Ac. 1297 Ac 496 Ac DBM 54 KM 5 DBM 57 DBM 59 KM 5 618 Ac KM 4 KM 4 KM 3 KM 4 KM 2 DBM 70 Infall Regulator outfall Regulator DBM 61 DBM 62 DBM 67 DBM 68 DBM 55 DBM 56 DBM 63 BAYANNAVAGU B.R MYLARAM B. R KM 334.507 KM 284.000 KM 286.500 KM 291.760 KM 294.834 KM 295.000 KM 296.250 KM 300.400 KM 302.500 KM 306.882 KM 341.000 KM 310.630 KM 313.082 KM 317.782. KM 323.207 KM 328.717 KM 333.572 KM 334.000 KM 345.932 Km 296.50 to Km 297.96 Km 326.754 to Km 325.460 Tail end Br. canal WARANGAL (1,13,578 Ac.) NALGONDA (2,57,508 Ac.) Package 1 CC lining of Kakatiya canal from KM 284 to 346 SRI RAMA SAGAR PROJECT STAGE-II
SRI RAMA SAGAR PROJECT STAGE-II CATEGORY-II
SRSP - II Package No. 52/Cat-II : CC Lining in bed and sides of Kakatiya main canal from Km 284.00 to KM 346.00 Name of the Contractor : M/s K. Sudhrashan Reddy & M/s K. Venkateshwarlu & Co.(JV) Agreement Amount : Rs. 58.37Crs. Agreement Date : 11-03-2005 Period of Completion : 24 Months (8 milestones) Date of completion : 11-03-2007 • Investigation : KM 56 completed against 56 KM – Completed • Execution : Lining in good progress for entire length of 56 KM • Expenditure : Rs. 38.56 Crs. against Rs. 58.37 Crs. (including Mob.Adv. of Rs.2.92Crs.) • Mob. Adv. Recovered : Rs. 2.92 Crores.
SRSP - II Package No. 53/Cat-II : DBM-60 distributory from KM 0.00 to KM 45.00 earth work excavation and forming embankment, construction of CM & CD works of Major & Minor. Name of the Contractor : M/s R.M. Mohite & Bhooratnam & Co. Agreement Amount : Rs. 62.15 Crs. Agreement Date : 07-03-2005 Period of Completion : 30 Months (10 milestones) Date of completion : 07-09-2007 • Investigation : KM 48 completed against 322 KM length • Designs : KM 48 approved against 322 KM of length • Execution : In slow progress due to land acquisition • Expenditure : Rs. 3.70 Crs. against Rs. 62.15 Crs. • Land Acquisition : Required : 2127 Acres, Requisitioned : 149 Acres
SRSP - II Package No. 54/Cat-II : DBM-60 distributory from KM 45.00 to KM 71.00 Name of the Contractor : M/s Rani Constructions Agreement Amount : Rs. 60.90 Crs. Agreement Date : 09-03-2005 Period of Completion : 30 Months (10 milestones) Date of completion : 09-09-2007 • Investigation : KM 42 completed against 278 KM of length • Designs : KM 42 against 278 KM of length • Execution : Excavation in progress in 3 KM length against total length of 278 KM • Expenditure : Rs.3.84Crs. against Rs. 60.90 Crs. (in. MA of Rs.3.04Crores) • Land Acquisition : Required 1500 Acres, Requisitioned : 214Acres. • Bottlenecks : Land Acquisition
SRSP - II Package No. 55/Cat-II : DBM-69 Main and minors, sub minors & field channels Name of the Contractor : M/s AKR – COASTAL Agreement Amount : Rs. 72.99 Crs. Agreement Date : 11-3-2005 Period of Completion : 30 Months (10 milestones) Date of completion : 11-09-2007 • Investigation : KM 27 completed against 125 KM of length • Designs : KM 27 approved against 125 KM of length • Execution : In good progress in the entire length of 125 Km • Expenditure : Rs. 28.43 Crs. against Rs. 72.99 Crs. (inc. MA of Rs.7.30Crs.) • Mob. Adv. Recovered : Rs. 3.65 Crores. • Land Acquisition : Required 2880Acres, Requisitioned: 262 Acres
SRSP - II • Package No. 56/Cat-II : DBM-71 distributary from Km 0.00 to Km 32.00 • Earthwork excavation and forming embankment. • Construction of CM & CD works • Investigation, design and estimation of distributary system • Distributaries Majors, Minors, sub-minors and field channels of DBM-71 Branch canal Name of the Contractor : M/s Ramky Infra Structures & V. Satyamurthy Agreement Amount : Rs. 72.00 Crs. Agreement Date : 06-3-2005 Period of Completion : 30 Months (10 milestones) Date of completion : 06-09-2007 • Investigation : Completed • Designs : Approved • Execution : Excavation in progress in 16 KM length against total length of 96 Km • Expenditure : Rs. 15.00 Crs. against Rs. 72.00 Crs.(inc. Mob.Adv. of Rs.3.60Crs) • Mob. Advance recovered : Rs. 1.26 Crores. • Land Acquisition : Required 2065 Acres, Requisitioned : 1345 Acres.
SRSP - II • Package No. 57/Cat-II : DBM-71 distributary from Km 32.00 to Km 40.00 • Earthwork excavation and forming embankment. • Construction of CM & CD works • Investigation, design and estimation of distributary system • Distributaries Majors, Minors, sub-minors and field channels of DBM-71 Branch canal Name of the Contractor : M/s Ramky Infra Structures & V. Satyamurthy Agreement Amount : Rs. 55.35 Crs. Agreement Date : 06-3-2005 Period of Completion : 30 Months (10 milestones) Date of Completion : 06-09-2007 • Investigation : Completed • Designs : Approved • Execution : Excavation in good progress in total length of 99 KM • Expenditure : Rs. 16.00 Crs. against Rs. 55.35 Crs.(inc. MA of Rs.2.97Crs.) • Land Acquisition : Required 1264 Acs, Acquired : 378 Acs, Requisitioned:739Acs.
SRSP - II • Package No. 58/Cat-II : DBM-71 distributory from Km 40.00 to Km 72.00 • Earthwork excavation and forming embankment. • Construction of CM & CD works • Distributaries Majors, Minors, sub-minors and field channels of DBM-71 Branch canal Name of the Contractor : M/s Rani Constructions Agreement Amount : Rs. 45.60 Crs. Agreement Date : 09-03-2005 Period of Completion : 30 Months (10 milestones) Date of completion : 09-09-2007 • Investigation : KM 47 completed against 135 KMof length • Designs : KM 15 approved against 135 KM of length • Execution : Started Not in good progress • Expenditure : Rs. 3.67 Crs. against Rs. 45.60 Crs. • Land Acquisition : Required 1591 Acs, Acquired : 161 Acs, Requisitioned:360Acs
KARIMNAGAR 30,000 Acres Phase-II NIZAMABAD KARIMNAGAR 1,00,000 Acres Phase-I WARANGAL 60,000 Acres LEFT SIDE GRAVITY CANAL LEFT SIDE GRAVITY CANAL Mothe Reservoir FRL +318.00 M FRL +398.5 M 1.090 TMC 1.646 TMC FRL +318 M FRL +311 M MID MANAIR RESERVOIR 25.87 TMC 7.0 TMC 39 Kms 25 kms GOURAVELLI RESERVOIR THOTAPALLY RESERVOIR RIGHT SIDE GRAVITY CANAL KM (-) 0.85 KM 17.00 KM 43.000 KM 15.00 KM 28.400 KM 122.00 KM 103.00 KM 57.00 KM 70.00 KM 86.00 RIGHT SIDE GRAVITY CANAL NALGONDA 30,000 Acres TOTAL AYACUT : 2,20,000 Acres INDEX Works Completed EPC Works in Progress Reservoirs District Border Works under Investigation STATUS OF WORKS OF FLOOD FLOW CANAL PROJECT FROM SRSP
FLOOD FLOW CANAL FROM SRSP Package No.1/Cat-I : Earth work excavation and forming embankment including CM & CD works from KM 28.40 to KM 43.00 (14.60 KM length) Name of the Contractor : M/s PATEL – SOMA(JV) Agreement Amount : Rs. 165.57 Crores Agreement Date : 23-10-2004 Period of Completion : 30 Months (8milestones) Date of Completion : 23-04-2007 • Investigation : Completed • Designs (Structures) : Approved • Execution (canals) : Excavation in good progress for total length of 14.60 KM • Qty. of earth work done : 54.62 Lakh Cum against 125.6 Lakh Cum. • No. of Machinery : Deployed = 131 Nos (Excavators = 18 Nos., Dumpers = 56 Nos., Dozers = 13 Nos. etc) • Expenditure : Rs. 120.21Crs. (including Mob. Adv. of Rs.16.55Crs.) against Rs. 165.50 Crs. • Mob. Adv. Recovered : Rs. 16.55 Crores. • Land Acquisition : Required 859 Acres, Acquired 739 Acres, Requisition:120Acs.
FLOOD FLOW CANAL FROM SRSP Package No.2 / Cat-I : Earth work excavation and forming embankment including CM & CD works from KM 43.00 to KM 57.00 (14.00 KM length) Name of the Contractor : M/s JayaPrakash-Gayathri (JV) Agreement Amount : Rs. 187.00 Crores Agreement Date : 23-10-2004 Period of Completion : 30 Months (10milestones) Date of Completion : 23-04-2007 • Investigation : Completed • Designs (Structures) : Approved • Execution (main canal) : Excavation in progress for total length of 14 KM • Qty. of earth work done : 62.40 Lakh Cum against 97.99 Lakh Cum. • No. of Machinery : Deployed = 168 Nos (Excavators = 18 Nos., Dumpers = 56 Nos., Dozers = 13 Nos. etc) • Expenditure : Rs. 104.31 Crs (including Mob. Adv. Of Rs.18.70Crs.) against Rs. 187 Crs. • Mob. Adv. Recovered : Rs. 18.70 Crores. • Land Acquisition : Required 769Acres, Acquired 710Acres, Requisitioned:59Acs.
FLOOD FLOW CANAL FROM SRSP Package No. 3 / Cat-I : Earth work excavation and forming embankment including CM & CD works from KM 57.00 to KM 70.00 (13.00 KM length) Name of the Contractor : M/s IVRCL-SEW & Prasad (JV) Agreement Amount : Rs. 195.03 Crores Agreement Date : 20-10-2004 Period of Completion : 30 Months (10 milestones) Date of Completion : 20-10-2007 • Investigation : Completed • Designs : Approved • Execution : Excavation in good progress for a total length of 13 KM • Qty. of earth work done : 75.47Lakh Cum against 131.27 Lakh Cum. • No. of Machinery : Deployed = 232 Nos (Excavators = 34 Nos., Dumpers = … Nos., Dozers = 16 Nos. etc) • Expenditure : Rs. 136.35 Crs. (inc. Mob. Adv.Rs.9.75Crs.) against Rs.195.03 Crs. • Mob. Adv. Recovered : Rs.9.75 Crs. • Land Acquisition : Required 825Acres, Acquired – 825.33Acs, Balance Nil.
FLOOD FLOW CANAL FROM SRSP Package No. 15 / Cat-I : Earth work excavation and forming embankment including CM & CD works from KM 70.00 to KM 86 (16.00 KM length) Name of the Contractor : M/s Simplex – Subhash Agreement Amount : Rs. 218. 77 Crores Agreement Date : 19-03-2005 Period of Completion : 30 Months Date of Completion : 19-09-2007 • Investigation : Completed • Designs (structures) : Completed • Execution : Excavation in progress in total length of 16.645 KM • Qty. of earth work done : 50.61Lakh Cum against 176.63 Lakh Cum. • No. of Machinery : Deployed = 84 Nos (Excavators = 14 Nos., Dozers = 5 Nos. etc) • Expenditure : Rs. 74.10 Crs. (inc. Mob. Adv. of Rs.21.87Crs.) against Rs.218.77 Crs. • Mob. Advance recovered : Rs. 9.94 Crores • Land Acquisition : Required 1083Acs,Acquired 512.12Acs,Requisitioned 570.88 Acs
FLOOD FLOW CANAL FROM SRSP Package No. 16 / Cat-I : Earth work excavation and forming embankment including CM & CD works from KM 86.00 to KM 103.00 (17.00 KM length) Name of the Contractor : M/s Maytas – NCC (JV) Agreement Amount : Rs. 210.06 Crores Agreement Date : 23-03-2005 Period of Completion : 30 Months (10 milestones) Date of completion : 23-09-2007 • Investigation : Completed • Designs : Approved • Execution : Excavation in good progress in total length of 17 KM • Qty. of earth work done : 62.68 Lakh Cum against 142.14 Lakh Cum. • No. of Machinery : Deployed = 84 Nos (Excavators = 11 Nos., Dozers = 5 Nos. etc) • Expenditure : Rs. 63.80 Crs. (including Mob. Adv.) against Rs. 210.06 Crs. • Land Acquisition : Required 1098Acs,Acquired 778.33Acs, Requisition 319.67Acs
FLOOD FLOW CANAL FROM SRSP Package No. 17 / Cat-I : Earth work excavation and forming embankment including CM & CD works from KM 103.00 to KM 122.00 (19.00 KM length) Name of the Contractor : M/s Madhucon–Sinc–Hydro (JV) Agreement Amount : Rs. 19900 Lakhs Agreement Date : 19-3-2005 Period of Completion : 30 Months (10 milestones) Date of Completion : 19-09-2007 • Investigation : Completed • Designs (Structures) : 7Nos. Approved against 32Nos. Balance with CE/CDO. • Execution : Excavation in good progress in total length of 19.00 KM • Qty. of earth work done : 67.45 Lakh Cum against 141.3 Lakh Cum. • No. of Machinery : Deployed = 74 Nos (Excavators = 16 Nos., Dozers = 8 Nos. etc) • Expenditure : Rs. 94.90 Crs. (including Mob. Adv.Rs9.95Crs.) against Rs. 199.00 Crs. • Mob. Adv. Recovered : Rs. 9.95 Crores. • Land Acquisition : Required 1108.40Acs,Acquired 606.12Acs, Requisitioned:502.28Acs