An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Overview Thorium Cycle project Project FIKI-CT-2000-00042 ADOPT FUETRA - Meeting March 13 2002

  2. Outline • Why Thorium? • Goal of Thorium Cycle project • General project Info • Working Packages: • WP2 HFR irradiation (Schram, Conrad, Somers) • WP3 KWO irradiation (Sommer, Somers) • WP4 Full core PWR behaviour (Phlippen) ADOPT FUETRA - Meeting March 13 2002

  3. Why Thorium ? • 232Th + 1n - > 233Pa - > 233U • Relatively low waste production • Possibility for enhanced Pu burning • Low leaching rate of thorium oxide • Potential use as an “inert” matrix • Follow-up of 4th FWP on Thorium, see also the report Thorium as a waste management option, EUR 191142 EN, ed. Gruppelaar and Schapira ADOPT FUETRA - Meeting March 13 2002

  4. Goal of Thorium Cycle project To supply key data for application of Th-cycle • Behaviour of Th-based fuel at extended burnup • irradiation experiment of 4 targets to 55 MWd/kgHM • irradiation experiment of 1 target to 35 MWd/kg HM in PWR • Core calculations for Th-based fuel: • code-to-code validation • sensitivity check for significant isotopes 232Th and 233U • to gain accurate results for 80-100 MWd/kgHM for Pu/Th fuel ADOPT FUETRA - Meeting March 13 2002

  5. WP1: Co-ordination WP3: KWO Irradiation WP4: Full core PWR behaviour WP2: HFR Irradiation General Project Info • Budget : 2.7 MEURO • Duration : 48 months • Participants : BNFL, CEA, FZK, JRC-IE, JRC-ITU, KWO-Obrigheim, NRG • Time frame : 1/10/2000 - 1/10/2004 To 6th Framework program ADOPT FUETRA - Meeting March 13 2002

  6. Status of Thorium cycle project • Project is now running for 1.5 years • Irradiation in HFR ongoing • Irradiation in KWO ongoing First 13 deliverables are issued ADOPT FUETRA - Meeting March 13 2002

  7. Time Schedule 2001 2002 2003 2004 ADOPT FUETRA - Meeting March 13 2002

  8. Test matrix irradiations HFR irradiation KWO irradiation ADOPT FUETRA - Meeting March 13 2002