An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Update on FCPS Construction/Renovation Projects July 2009

  2. Cassidy Elementary – Renovation • Architect: Tate.Hill.Jacobs: Architects • General Contractor: D.W. Wilburn, Inc. • Substantial Completion Date: August, 2010 • Contract Sum: $9,061,000 • Change Orders to Date (1): $3,152.42 • Current Phase: 1 (On Schedule) • Estimated Completion: 19%

  3. Cassidy Elementary – Renovation Rendering of Final Façade

  4. Cassidy Elementary – Renovation • Work Completed in Last 30 Days: • Asphalt removal at Stage Addition complete. • Primary electric installed and secondary conduits installed to transformer pad location. • Selective interior demolition continuing with removal of walls, ceilings and doors in Phase 1. Mechanical demolition on-going. • New Admin. Addition and Music Rm. Addition first floor slab in place. • Bearing CMU walls up to first floor height at New Admin. Addition. CMU begun on Music Rm. Addition. • Steel columns and beams begun for new Media Center at New Admin. Addition. • Door frames installed in new CMU walls at New Admin. Addition. • Under-slab plumbing and electrical rough-ins complete in New Admin. and Music Rm. Additions with wall rough-ins continuing with new CMU wall construction. New HVAC delivered to site.

  5. Cassidy Elementary – Renovation • Current Work Effort (July): • Storm sewer begun along front of building with new underground retention structures starting. • Gas main line to begin between Morton M.S. and Cassidy Elem. with completion prior to start of school. • Sanitary sewer work begun with completion prior to start of school. • Fire Protection/Water Main work started with completion prior to start of school. • Morton M.S. parking lot extension to start with completion prior to start of school. • Selective demolition of interior areas to continue as needed for Phase 1 work. • Concrete foundation and slab for Stage Addition to start with CMU walls following. • Coordination Meeting to be held on site 1½ week prior to start of school with contractors, local fire department officials and FCPS staff to review life safety and emergency egress compliance prior to staff/student occupancy.

  6. Cassidy Elementary – Renovation Existing Gym During Demo New Admin Addition New Stage & Music Room Addition New Media Center Addition

  7. Russell Cave Elementary – Renovation • Architect: Pearson & Peters Architects • General Contractor: Congleton-Hacker Construction • Substantial Completion Date: August, 2010 • Contract Sum: $5,001,150 • Change Orders to Date (1): $0 • Current Phase: 1 (On Schedule) • Estimated Completion: 16%

  8. Russell Cave Elementary – Renovation Rendering of Final Façade

  9. Russell Cave Elementary – Renovation • Work Completed in Last 30 Days: • Exterior concrete block walls are being installed. • Interior of Kitchen/Cafeteria has been demolished and renovation has begun. • Renovation of (4) classrooms on the south side has begun. • Concrete slab at the new addition has been poured. • Masonry restoration on the exterior of the original building in process. • Existing elevator has been upgraded. • Current Work Effort (July): • Roof trusses at the new additional will be set. • Kitchen/Cafeteria renovation will be completed. • Interior work on the new addition and the (4) classrooms on the south side will continue. They are scheduled to be completed in October. • Complete new electrical and mechanical systems in Kitchen/Cafeteria.

  10. Russell Cave Elementary – Renovation New Addition New Addition Interior of Cafeteria Masonry Restoration

  11. Arlington Elementary – Renovation • Architect: RossTarrant Architects • General Contractor: W/S Construction • Substantial Completion Date: August, 2010 • Contract Sum: $9,920,194 • Change Orders: $36,900 (#1--Demo) • Current Phase: 1 (On Schedule) • Estimated Completion: Demo – 100%

  12. Arlington Elementary – Renovation Rendering of Final Façade

  13. Arlington Elementary – Renovation • Work Completed in Last 30 Days: • Earthwork continues • Interior selective demolition continues • Foundation footers, stem walls and foundation drains are currently being installed • Site utilities being brought to the building • Interior plumbing being installed • Current Work Effort (July): • Structural shoring to begin ASAP and subsequent demolition of the remainder of that scope of work to existing to remain • Masonry scheduled to begin 7/20

  14. Arlington Elementary – Renovation Earthwork Continues Interior Selective Demo Foundation Footers Being Installed Site Utilities to Building

  15. Bryan Station Middle – Renovation • Architect: Clotfelter-Samokar Architects • General Contractor: Preston Construction Group • Substantial Completion Date: August, 2010 • Contract Sum: $10,769,400 • Change Orders to Date: $0 • Current Phase: 1A (On Schedule) • Estimated Completion: 14%

  16. Bryan Station Middle – Renovation Rendering of Final Façade

  17. Bryan Station Middle – Renovation • Work Completed in Last 30 Days: • Portable classrooms in place • Majority of demolition work in Phase 1 complete • Concrete sidewalk and stairs at rear of building complete • Current Work Effort (July): • Contractors preparing sub-grade for new addition and revised bus lane • Existing storm drains being replaced with new • New sanitary sewer line being installed to replace old, inadequate “pump-station” type sewer system • Kitchen/Cafeteria renovation work progressing rapidly to meet deadlines • Owner installing portable restroom units

  18. Bryan Station Middle – Renovation New Storm Sewer Drains New Sanitary Sewer Line Kitchen/Café Renovation Portable Restroom Units

  19. Leestown Middle – Renovation • Architect: Lucas/Schwering Architects • General Contractor: D.W. Wilburn, Inc. • Substantial Completion Date: August, 2010 • Contract Sum: $11,182,000 • Change Orders to Date: $0 • Current Phase: 1, 1a, 1b (On Schedule) • Estimated Completion: 12%

  20. Leestown Middle – Renovation Rendering of Final Façade

  21. Leestown Middle – Renovation • Work Completed in Last 30 Days: • Phase 1demolition and Asbestos abatement efforts on-going. • Phase 1 site demolition complete • Structural shoring at Cafeteria and in Corridor • Kitchen foundation walls poured • Demolition of existing kitchen, front entrance and administration suite are complete • Current Work Effort (July): • Interior and exterior demolition in Phases 1, 1a & 1b will continue • Plumbing, HVAC, electrical demolition on-going • Structural shoring will continue to be erected • Floor slab for the new Kitchen will be poured • Electrical and Plumbing rough-ins to begin • Masonry load bearing and erection of new fire walls to start • Masonry restoration has begun • Erection of structural steel to begin

  22. Leestown Middle – Renovation Front Entrance Demo Admin Suite Demo Admin Suite Demo Looking From Courtyard Existing Kitchen Demo

  23. Lafayette High Stadium – Replacement • Architect: Strand & Associates • General Contractor: Venture One Construction • Substantial Completion Date: June, 2010 • Contract Sum: $4,100,000 • Change Orders to Date: $0 • Current Phase: Phase 1 to begin August 1

  24. Lafayette High Stadium – Replacement Existing Campus

  25. Lafayette High Stadium – Replacement Existing Football Stadium

  26. Lafayette High Stadium – Replacement New Football Stadium

  27. Central Bus Garage – Adaptive Reuse • Architect: Lucas/Schwering Architects • General Contractor: James R. Leake & Sons, Inc. • Substantial Completion Date: August, 2009 • Contract Sum: $2,782,000 • Change Orders to Date (1): $4,346.17 • Current Phase: Construction • Estimated Completion: 27%

  28. Central Bus Garage – Adaptive Reuse Façade

  29. Central Bus Garage – Adaptive Reuse Proposed Floor Plan

  30. Central Bus Garage – Adaptive Reuse • Work Completed in Last 30 Days: • Rock removal continues • Exterior concrete continues to be placed, approximately 95% complete • Electric standards in parking lot being installed • Under-slab plumbing installed and being tested • Shoring in place for lift pits    • Bus exhaust evacuation system in place • Current Work Effort (July): • Steel erection for mezzanine to start 7/20 • Concrete placement at mezzanine to occur 7/24 • Electrical installation continues • Interior concrete slab placement to continue • Trench drain installation to commence • New parking lot water quality units to be installed • Parking lot curbs to be placed

  31. Central Bus Garage – Adaptive Reuse Under-slab Plumbing Install of Sanitary Sewer Line Foundation Wall for Bus Lift Under-slab Plumbing

  32. Tonight’s Agenda Items

  33. Tonight’s Agenda Items - continued