Update on FCPS Construction/Renovation Projects. July 2009. Cassidy Elementary – Renovation. Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date: August, 2010 Contract Sum: $9,061,000 Change Orders to Date (1): $3,152.42
E N D
Cassidy Elementary – Renovation • Architect: Tate.Hill.Jacobs: Architects • General Contractor: D.W. Wilburn, Inc. • Substantial Completion Date: August, 2010 • Contract Sum: $9,061,000 • Change Orders to Date (1): $3,152.42 • Current Phase: 1 (On Schedule) • Estimated Completion: 19%
Cassidy Elementary – Renovation Rendering of Final Façade
Cassidy Elementary – Renovation • Work Completed in Last 30 Days: • Asphalt removal at Stage Addition complete. • Primary electric installed and secondary conduits installed to transformer pad location. • Selective interior demolition continuing with removal of walls, ceilings and doors in Phase 1. Mechanical demolition on-going. • New Admin. Addition and Music Rm. Addition first floor slab in place. • Bearing CMU walls up to first floor height at New Admin. Addition. CMU begun on Music Rm. Addition. • Steel columns and beams begun for new Media Center at New Admin. Addition. • Door frames installed in new CMU walls at New Admin. Addition. • Under-slab plumbing and electrical rough-ins complete in New Admin. and Music Rm. Additions with wall rough-ins continuing with new CMU wall construction. New HVAC delivered to site.
Cassidy Elementary – Renovation • Current Work Effort (July): • Storm sewer begun along front of building with new underground retention structures starting. • Gas main line to begin between Morton M.S. and Cassidy Elem. with completion prior to start of school. • Sanitary sewer work begun with completion prior to start of school. • Fire Protection/Water Main work started with completion prior to start of school. • Morton M.S. parking lot extension to start with completion prior to start of school. • Selective demolition of interior areas to continue as needed for Phase 1 work. • Concrete foundation and slab for Stage Addition to start with CMU walls following. • Coordination Meeting to be held on site 1½ week prior to start of school with contractors, local fire department officials and FCPS staff to review life safety and emergency egress compliance prior to staff/student occupancy.
Cassidy Elementary – Renovation Existing Gym During Demo New Admin Addition New Stage & Music Room Addition New Media Center Addition
Russell Cave Elementary – Renovation • Architect: Pearson & Peters Architects • General Contractor: Congleton-Hacker Construction • Substantial Completion Date: August, 2010 • Contract Sum: $5,001,150 • Change Orders to Date (1): $0 • Current Phase: 1 (On Schedule) • Estimated Completion: 16%
Russell Cave Elementary – Renovation Rendering of Final Façade
Russell Cave Elementary – Renovation • Work Completed in Last 30 Days: • Exterior concrete block walls are being installed. • Interior of Kitchen/Cafeteria has been demolished and renovation has begun. • Renovation of (4) classrooms on the south side has begun. • Concrete slab at the new addition has been poured. • Masonry restoration on the exterior of the original building in process. • Existing elevator has been upgraded. • Current Work Effort (July): • Roof trusses at the new additional will be set. • Kitchen/Cafeteria renovation will be completed. • Interior work on the new addition and the (4) classrooms on the south side will continue. They are scheduled to be completed in October. • Complete new electrical and mechanical systems in Kitchen/Cafeteria.
Russell Cave Elementary – Renovation New Addition New Addition Interior of Cafeteria Masonry Restoration
Arlington Elementary – Renovation • Architect: RossTarrant Architects • General Contractor: W/S Construction • Substantial Completion Date: August, 2010 • Contract Sum: $9,920,194 • Change Orders: $36,900 (#1--Demo) • Current Phase: 1 (On Schedule) • Estimated Completion: Demo – 100%
Arlington Elementary – Renovation Rendering of Final Façade
Arlington Elementary – Renovation • Work Completed in Last 30 Days: • Earthwork continues • Interior selective demolition continues • Foundation footers, stem walls and foundation drains are currently being installed • Site utilities being brought to the building • Interior plumbing being installed • Current Work Effort (July): • Structural shoring to begin ASAP and subsequent demolition of the remainder of that scope of work to existing to remain • Masonry scheduled to begin 7/20
Arlington Elementary – Renovation Earthwork Continues Interior Selective Demo Foundation Footers Being Installed Site Utilities to Building
Bryan Station Middle – Renovation • Architect: Clotfelter-Samokar Architects • General Contractor: Preston Construction Group • Substantial Completion Date: August, 2010 • Contract Sum: $10,769,400 • Change Orders to Date: $0 • Current Phase: 1A (On Schedule) • Estimated Completion: 14%
Bryan Station Middle – Renovation Rendering of Final Façade
Bryan Station Middle – Renovation • Work Completed in Last 30 Days: • Portable classrooms in place • Majority of demolition work in Phase 1 complete • Concrete sidewalk and stairs at rear of building complete • Current Work Effort (July): • Contractors preparing sub-grade for new addition and revised bus lane • Existing storm drains being replaced with new • New sanitary sewer line being installed to replace old, inadequate “pump-station” type sewer system • Kitchen/Cafeteria renovation work progressing rapidly to meet deadlines • Owner installing portable restroom units
Bryan Station Middle – Renovation New Storm Sewer Drains New Sanitary Sewer Line Kitchen/Café Renovation Portable Restroom Units
Leestown Middle – Renovation • Architect: Lucas/Schwering Architects • General Contractor: D.W. Wilburn, Inc. • Substantial Completion Date: August, 2010 • Contract Sum: $11,182,000 • Change Orders to Date: $0 • Current Phase: 1, 1a, 1b (On Schedule) • Estimated Completion: 12%
Leestown Middle – Renovation Rendering of Final Façade
Leestown Middle – Renovation • Work Completed in Last 30 Days: • Phase 1demolition and Asbestos abatement efforts on-going. • Phase 1 site demolition complete • Structural shoring at Cafeteria and in Corridor • Kitchen foundation walls poured • Demolition of existing kitchen, front entrance and administration suite are complete • Current Work Effort (July): • Interior and exterior demolition in Phases 1, 1a & 1b will continue • Plumbing, HVAC, electrical demolition on-going • Structural shoring will continue to be erected • Floor slab for the new Kitchen will be poured • Electrical and Plumbing rough-ins to begin • Masonry load bearing and erection of new fire walls to start • Masonry restoration has begun • Erection of structural steel to begin
Leestown Middle – Renovation Front Entrance Demo Admin Suite Demo Admin Suite Demo Looking From Courtyard Existing Kitchen Demo
Lafayette High Stadium – Replacement • Architect: Strand & Associates • General Contractor: Venture One Construction • Substantial Completion Date: June, 2010 • Contract Sum: $4,100,000 • Change Orders to Date: $0 • Current Phase: Phase 1 to begin August 1
Lafayette High Stadium – Replacement Existing Campus
Lafayette High Stadium – Replacement Existing Football Stadium
Lafayette High Stadium – Replacement New Football Stadium
Central Bus Garage – Adaptive Reuse • Architect: Lucas/Schwering Architects • General Contractor: James R. Leake & Sons, Inc. • Substantial Completion Date: August, 2009 • Contract Sum: $2,782,000 • Change Orders to Date (1): $4,346.17 • Current Phase: Construction • Estimated Completion: 27%
Central Bus Garage – Adaptive Reuse Proposed Floor Plan
Central Bus Garage – Adaptive Reuse • Work Completed in Last 30 Days: • Rock removal continues • Exterior concrete continues to be placed, approximately 95% complete • Electric standards in parking lot being installed • Under-slab plumbing installed and being tested • Shoring in place for lift pits • Bus exhaust evacuation system in place • Current Work Effort (July): • Steel erection for mezzanine to start 7/20 • Concrete placement at mezzanine to occur 7/24 • Electrical installation continues • Interior concrete slab placement to continue • Trench drain installation to commence • New parking lot water quality units to be installed • Parking lot curbs to be placed
Central Bus Garage – Adaptive Reuse Under-slab Plumbing Install of Sanitary Sewer Line Foundation Wall for Bus Lift Under-slab Plumbing