1 / 5

LBT Q1 2009 Eng/SW Review

LBT Q1 2009 Eng/SW Review. ALPC – Primary Mirror Aluminum Shooting. Highlights (Q1/2009). Aluminization dates set for 20-24 July. Progress (Q1/2009). Planning From Q1 Review Next Aluminization Aug 09 on DX Late July. Open Issues. Technical

moeshe
Download Presentation

LBT Q1 2009 Eng/SW Review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LBT Q1 2009 Eng/SW Review ALPC – Primary Mirror Aluminum Shooting

  2. Highlights (Q1/2009) • Aluminization dates set for 20-24 July LBT Q1 2009 Engineering Review

  3. Progress (Q1/2009) • Planning From Q1 Review • Next Aluminization Aug 09 on DX • Late July LBT Q1 2009 Engineering Review

  4. Open Issues • Technical • Documentation for Aluminization System from OSU improved but needs more work • Continuous Upgrade of Aluminization System • Meisner trap for mirror cell • Schedule • Find James time to implement a Meisner trap for mirror cell • Financial • None • Resources • None LBT Q1 2009 Engineering Review

  5. Planning (Q2/2009) • Buy stuff for the next Aluminization LBT Q1 2009 Engineering Review