Glenview Estate Subdivision

AustStab Awards of Excellence 2014. Glenview Estate Subdivision. Mid Coast Road Services Innovation or Excellence in Sustainability. Sponsored by. Objectives.

molly
Download Presentation

Glenview Estate Subdivision

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. AustStab Awards of Excellence 2014 Glenview Estate Subdivision Mid Coast Road Services Innovation or Excellence in Sustainability Sponsored by

  2. Objectives • Investigate options to reduce the cost of pavement construction through subgrade improvement, on a medium sized residential subdivision • King and Campbell were consulted regarding subgrade improvement initiatives available

  3. Existing design • Previous testing had subgrade CBRs of 3 • Original design was • 300mm select layer above • 100 DGS20 • 100 DGB20 • Existing subgrade exhibited swelling –indicated a low wet strength

  4. New Design New testing undertaken including lime demand testing at 2% and 4% HL Trials indicated soaked CBRS of 17-40 Resulting pavement design required stabilizing at 300mm of Hydrated Lime at 2%. Post testing achieved CBRS of over 25.

  5. Existing subgrade CBR 3

  6. Existing subgrade Road 2

  7. Dry Mix Road 1

  8. New Pavement Design • Pavement redesigned at CBR 15 • Select layer was removed • Pavement reduced to • 150mm DGS • 130mm DGB • 40mm AC14

  9. Benefits • Reduced duration of project by 2 weeks • Minimised impact to local residents • Cost savings of $10/m2 over 4,000m2 • Eliminated requirement to import fill • Eliminated requirement to remove 1200m3 of material to the tip site

  10. Outcomes • Sustainability • Reduced the volume of imported fill • Reduction in vehicle movements • Used existing subgrade material

  11. Timeframe Reduction in project duration from 22 weeks to 20 weeks

  12. Economical Cost savings delivered back to client Savings of $10/m2 in first stage

  13. Environmental Elimination of select layer approx 3,000t Reduced traffic movements on existing road network Reduced noise impact to residents near site