Cost Effective Rodent Burrow Mitigation in Project Levees Using Grouting

Cost Effective Rodent Burrow Mitigation in Project Levees Using Grouting. California Department of Water Resources Levees Maintenance & Inspection Program November 2011. Genesis of Grouting Demonstration. DWR Maintenance Yards Programs (2000) Vegetation-on Levees (CLVRP) Research

moral
Download Presentation

Cost Effective Rodent Burrow Mitigation in Project Levees Using Grouting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Cost Effective Rodent Burrow Mitigation in Project Levees Using Grouting California Department of Water Resources Levees Maintenance & Inspection Program November 2011

  2. Genesis of Grouting Demonstration • DWR Maintenance Yards Programs (2000) • Vegetation-on Levees (CLVRP) Research • Methods Research by Allen Romero (DWR-retired)

  3. Demonstration Site Overview • RD 1500 – Robbins, CA • Sutter County • 16 miles NE of Woodland • Agricultural Levees • Borders Sacramento River • Unit 1 Levee • Sandy Soils • Grass Cover Only • Adjoins Active Corn Field • Squirrel Infestation (Pronounced)

  4. Typical RD 1500 Burrow Openings

  5. Goals of Grouting Study • Levee Risk Factor • Burrow Architecture • Engineering Quantification (LiDAR) • Seepage & Stability Effects • Grouting Methodology • Effectiveness of Cement-Bentonite • Low-Cost Fabricated Unit • Small Repairs vs. Large Repairs

  6. Fabricated Low-Cost Unit

  7. Grouting Test Site with Flagging

  8. Hand Mixing Cement-Bentonite

  9. Grouting Activities

  10. Grouting Logistics • Resources • 2 to 3 man crew • Mixer/Pump/Hoses/PVC • Cement-Bentonite, Garden Hoe • Water Tank • Burlap Bags, Stakes, Sledge Hammer

  11. Larger Repairs Require Batch Source

  12. Grouting Exposed (upper complex)

  13. Grouting Exposed (lower complex)

  14. Summary of Grouting Activities • 14 Significant Holes Grouted in 65-feet Reach • Average take approximately 1.5 cubic feet/hole • Largest take took over 3 cubic feet & 13 minutes • Urethane grout exposed air bubbles in C-B grout • Urethane grout showed voids still existed where levee slopes tractor rolled or dragged

  15. Cost of Fabricated Mixer/Pump* • Blah-Blah-Blah • Blah-Blah-Blah • Blah-Blah-Blah *Cost based upon 2011 U.S. dollar *Adjust yearly for inflation

  16. Cost of Cement-Bentonite Grout* • Blah-Blah-Blah • Blah-Blah-Blah • Blah-Blah-Blah *Cost based upon 2011 U.S. dollar *Adjust yearly for inflation

  17. Final Observations & Thoughts • Cement-Bentonite Grouting is Cost Effective • Resources to fabricate a mixer/pump readily available and relatively inexpensive • Labor resources no greater than other LMA activities • Grouting most effective when performed annually in conjunction with actively maintained rodent bait stations

  18. Questions?