An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Thermosiphon project IV review-Overall cost estimation and planning Michele Battistin Elena Perez Rodriguez 19th November 2010

  2. ATLAS reviewing process

  3. EVM Project management This project will follow the Earned Value Management (EVM) technique Thermosiphon project

  4. Project Breakdown Structure (EDMS 1102716) Low temperature Chiller condenser liquid tank pneumatic valve Surface USA15 Heater From compressors To compressors

  5. Resource and responsibility matrix

  6. Planning

  7. Cost estimation

  8. Conclusions • The Mini-Thermosiphon has proved the working principle for the consolidation. • The 2 kW Thermosiphon will provide results for the control and detailed design. • The Full Scale Thermosiphon is already well advanced • Basic design is done • Planning and cost estimation have been presented • Purchase has started • Piping installation has been organized

  9. Thank you for your attention Any questions ?