1 / 18

Capital Budgeting and Risk

10. Capital Budgeting and Risk. Introduction. This chapter looks at adjusting a project’s risk level when it has more or less than the firm’s average risk level. Risk. Project risk The risk that a project will perform below expectations Some of the risk can be diversified away. Beta risk

msprague
Download Presentation

Capital Budgeting and Risk

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 10 Capital Budgeting and Risk

  2. Introduction • This chapter looks at adjusting a project’s risk level when it has more or less than the firm’s average risk level.

  3. Risk • Project risk • The risk that a project will perform below expectations • Some of the risk can be diversified away. • Beta risk • Depends on the risk of the project relative to the market-portfolio • Beta risk cannot be diversified away. • Capital asset pricing model (CAPM) • Used to estimate risk-adjusted discount rates for capital budgeting

  4. Information on Risk • The Society for Risk Analysis (SRA) • http://www.sra.org/index.htm • Official journal of the SRA is Risk Analysis • http://www.sra.org/journal.htm

  5. All Equity Case • The project’s risk-adjusted discount rate is found with the SML equation:

  6. The Equity and Debt Case • Betas can be observed for firms in the same investment class as the proposed investment. • These betas can be used to estimate risk-adjusted discount rates. • A two-step process is used • Calculate an unleveraged beta • Calculate a new leveraged beta to reflect appropriate debt capacity

  7. Step 1: Calculate an Unleveraged Beta • Convert the observed, leveraged beta, l, into an unleveraged, or pure project beta, u.

  8. Step 2: Calculate a New Leveraged Beta • Calculate the new leveraged beta, l, for the proposed capital structure of the new line of business • Glossary of terms • http://www.contingencyanalysis.com/

  9. Step 2 Continued • Calculating the required rate of return, ke, based on the new leveraged beta, l: • Calculate the risk-adjusted required return, ka*, on the new line of business:

  10. Adjusting for Total Project Risk • NPV-Payback approach • Simulation approach • Sensitivity analysis • Scenario analysis • Risk-adjusted discount rate approach • Certainty equivalent approach

  11. NPV-Payback Approach • A project must have a positive NPV and a payback of less than a critical number of years to be acceptable.

  12. Simulation Approach • Estimate the probability distribution of each element which influences the CFs of a project. • ElementsNumber of units sold Market price Unit production costs NINVUnit selling cost Project life Cost of capital • Calculate the NPV using randomly chosen numerical values for the elements. • Repeat the process until a probability distribution of the NPV can be estimated.

  13. Sensitivity Analysis • Involves systematically changing relevant variables to identify which variables the NPV/IRR seems most sensitive to • Useful to make sensitivity curves to show the impact of changes in a variable on the project’s NPV • Electronic spreadsheets and financial modeling make sensitivity analysis easy to perform. • Examine the sensitivity of CF at this Web site: http://www.toolkit.cch.com/tools/tools.asp

  14. Scenario Analysis • Considers the impact of simultaneous changes in key variables on the desirability of an investment project • Estimate the expected NPV Optimistic Pessimistic Most likely • Estimate the Probability of each • Compute the expected NPV • Compute the standard deviation (SD) of the NPV

  15. Risk-Adjusted Discount Rate Approach • An individual project is discounted at a discount rate adjusted to the riskiness of the project instead of discounting all projects at one rate. • ka* = rf + risk premium • Calculate the NPV substituting ka* for k in the formula.

  16. certain return = t risky return Certainty Equivalent Approach • Involves converting expected risky CFs to their certainty equivalents and then computing the NPV • The risk-free rate (rf) is used as the discount rate not the cost of capital (k). • The certainty equivalent factor is the ratio of the certainty equivalent CF to the risky CF:

  17. The Certainty-Equivalent NPV • The certainty-equivalent NPV:

  18. Special Elements of Risk When Investing Abroad • Captive funds • Foreign government takes over assets • Exchange rate risk • Risk of inflation • Uncertain tax rates

More Related