An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Segment 3 • East of Conner to Chene • 2015 to 2021 • Cost = $928 million (year of expenditure)

  2. Segment 2 • Chene to Cass • 2020 to 2025 • Cost = $424 million (year of expenditure) • Includes I-94/I-75 interchange

  3. Segment 1 • Cass to east of I-96 (Grand River) • 2024 to 2029 • Cost = $1,217 million (year of expenditure) • Includes I-94/M-10 interchange

  4. Showtime • I-94 Roadway to Detroit’s Future • On You Tube – Search I-94 • On MDOT’s Website –michigan.gov/mdot/studies