Construction Analysis during theDesign Process www.ddss.arch.tue.nl Bauke de Vries
4D-CAD • Linking building components with construction activities • Manual task of the construction planner • Dedicated systems: NavisWorks, 4D Suite, … • Advantages: Simulation, Visualization
Challenge Automation of the planning process. Advantages: • Independency from the planner • Quick first concept plan
Construction algoritms Analysis by object name: Walls are bearing floors, colums are bearing beams, etc.
Construction algorithms Analysis by object elevation: Object with a lower elevation is bearing an object with a higher elevation
Construction algorithms Analysis by directed graph: Each object is a node in a connection graph.
Construction algorithms Analysis by object adjacency: Each object is a node in a topological graph
Construction analysis Object of anlysis
Construction analysis Move down – Inleiding – Oriëntatie – Doelstelling van het onderzoek – De algoritmen – Implementatie – – Case Study – Reactie uit het bedrijfsleven – Conclusie en Aanbevelingen – Einde –
Construction analysis The green objects have an intersection in the vertical direction with the red object – Inleiding – Oriëntatie – Doelstelling van het onderzoek – De algoritmen – Implementatie – – Case Study – Reactie uit het bedrijfsleven – Conclusie en Aanbevelingen – Einde –
Construction analysis The red object has in intersection with the green objects in the horizontal direction
Construction analysis Example: Objects adjacent to floor
Planning comparison Real planning Generated planning
Differences • Concurrency whenever possible • Unlimited resources • Construction method
Experiences • Model preperation through clash detection • Generated planning 2 months longer than real planning over a a period of 1 ½ year • Suitable for a quick first guess • Further development of: Construction method, Humen resources, Material resources