An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. IST plan Pieter Dieleman etc September 24, 2007

  2. Integration tests Expected steps for the different HIFI configurations FPU LOU test name TCL version 1 dummy dummyUFT 1.x 2 RT not connSFT-warm 2.x 3 RT dummy+harnesUFT- before LOU conn 1.x 4 RT RTSFT-warm 2.x 5 OT RT SFT-cold 3.x 6 OT RT IST/commissioning 3.x 7 OT RT SPT 3.x 8 OT RT TV scripts tests 3.x 9 OT RT RMS 3.x 10 OT OTTV 4.x

  3. IST Configuration • SVM (Service Module) • Panels closed; RT, 20-25º, MLI covered • LO at RT, 1 frequency per subband allowed • Cryostat • 2 or 4 K • ~25º tilt • Planned Dec 1 2007

  4. IST steps (1) • Chopper scan Chopper endstop check • Chopper steps Closed-loop parameter check • Per mixer band: • FT-unpumpedmixer I,V curves deflux IF noise • Diplexer calibration 1 LO frequency / subband for 5 VD2 or with (wide) LO tuning? • Duration 2 hours • Analysis step (1 day) FPU thermal test prime (20 h?) • CUS update with: • IF 2 settings (FPU IF power) • Course LO tuning • Diplexer optimum settings for LO coupling

  5. IST steps (2) • Per LO subband: • LO VD2 Vector scan Determine optimum LO VD2 • Diplexer scan with HC compare with diplexer setting for LO port Duration: 4 hours • Analysis step (1 day) FPU thermal test red (20 h?) • CUS update with: • Fine LO tuning • Diplexer optimum settings for Signal coupling

  6. IST steps (3) Commissioning • Per band: • FT-unpumpedmixer I,V curves deflux IF noise • IF stability test without LO • LO tune • Short stability test warm-up LO • Performance test Hot-cold • Chopper scan HBB-CBB position calibration (ripple) Duration 13 hours

  7. Summary • Allocated 10 hours, we take 20 (60 if thermal test included / 2 offline analysis days) • 3 days Short Performance Test were allocated, now removed • With LO warm, 1 freq/subband not representative anyway • 16 hours RMS (Reference Mission Scenario) = AOT’s • Scripts sufficiently up to date / debugged?