AECI Generator Interconnection Procedure (GIP) and Generator Interconnection Agreement (GIA) Overview

AECI Generator Interconnection Procedure (GIP) and Generator Interconnection Agreement (GIA) Overview. February 2, 2009. AECI GENERATOR INTERCONNECTION PROCEDURE. Applicable Generator Interconnections (Section 1). Generating Facility (GF) >= 1 MW

nanette
Download Presentation

AECI Generator Interconnection Procedure (GIP) and Generator Interconnection Agreement (GIA) Overview

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. AECI Generator Interconnection Procedure (GIP)andGenerator Interconnection Agreement (GIA)Overview February 2, 2009

  2. AECI GENERATOR INTERCONNECTION PROCEDURE

  3. Applicable Generator Interconnections (Section 1) • Generating Facility (GF) >= 1 MW • GF requesting interconnection to transmission facilities >= 69 kV

  4. Types of Interconnection Service (Section 3.3) • Energy Resource Interconnection Service (ERIS) • Network Resource Interconnection Service (NRIS)

  5. GIP Processing • Pre-Queue Informational Meeting (Section 3.1) • Valid Interconnection Request (Section 3.4) • Non-refundable fee • Study deposit based on GF MW rating • 50% Site Control • Executed Study Agreement • Executed Confidentiality Agreement • Completed Application • Stability model

  6. GIP Processing (continued) 3. System Impact Study Phase (Section 6) 4. Milestones To Enter Into Facility Study Phase (Section 7.1) • Executed Study Agreement • 100% Site Control • Study deposit based on GF MW rating • Detailed Stability model • Detailed one-line • Declaration of GF capacity • For NRIS, executed PPA or equivalent 5. Facility Study Phase (Section 7)

  7. GIP Processing (continued) 6. Generator Interconnection Agreement (GIA) Negotiation (Section 9.2) 7. Milestones To Execute GIA (Section 9.3) A) Recertification of 100% Site Control B) Non-refundable cash deposit (capped at $500,000) applied to future material and construction costs C) Provide one or more of the following: • Fuel Supply Contract • Cooling water supply Contract • Engineering, procurement or construction contract for major equipment • PPA or equivalent evidence • Air, water or land use permit

  8. System Impact Study Phase (Section 6) • Study order is based on date of receipt of a valid interconnection request and studied in serial order • AECI Transmission Planning has 120 days to complete study

  9. Milestones to Enter Facility Study Phase • Interconnection Customer has 60 calendar days from the receipt of the completed SIS to achieve the milestones listed in Section 7.1 • Failure to meet the required milestones will result in withdraw of the interconnection request (Section 7.2)

  10. Facility Study Phase (Section 7) • Study order is based on date of receipt of all the required milestones and studied in sequential order • AECI Transmission Planning has 120 days to complete study • AECI will tender a draft Generator Interconnection Agreement (GIA) with final FS Report

  11. GIA Negotiation and Execution (Section 9.2 and Section 9.3) • Negotiations of GIA Appendices begin at request of Interconnection Customer (IC) after tendering draft GIA • Negotiations of GIA shall not be more than 90 days • IC may request termination of negotiations and initiate dispute resolution (arbitration) • If GIA is not executed or dispute resolution commenced within 90 days of tendering draft GIA, request will be withdrawn • Milestones to execute GIA (Section 9.3) must be completed within 90 days of receipt of final GIA

  12. Transition of Existing Interconnection Requests See Section 5 of GIP

  13. AECI Generation Interconnection Agreement

  14. GIA Highlights GIA Terms and Conditions • Bilateral agreement between AECI and IC • 10 year initial term with year to year evergreen clause • Terminate with 3 year notice • Terminate if IC fails to provide notice to proceed with design, procurement and design as specified (Section 2.3.2) • Governs operational responsibilities of AECI and Interconnection Customer

  15. GIA Highlights GIA Terms and Conditions • Establishes responsibilities for construction, ownership and maintenance of system upgrades (Appendix A) • Establishes cost allocation and payment schedule for system upgrades (Appendix A) • Establishes various milestone dates (Appendix B) • No suspension of GIA

  16. Questions Contact Mgr of Transmission Policy: 417-885-9397 Or Mgr of Transmission Planning: 417-885-9361