RIC 2009 Human Factors DAC/ITAAC Reviews Michael Junge USNRC/NRO/DCIP March 11, 2009

RIC 2009 Human Factors DAC/ITAAC Reviews Michael Junge USNRC/NRO/DCIP March 11, 2009. Impacts on Fuel Load Schedule. Licensed operators are required to load fuel. Prior to fuel load, Industry estimates two licensed operator examinations will be required.

nansen
Download Presentation

RIC 2009 Human Factors DAC/ITAAC Reviews Michael Junge USNRC/NRO/DCIP March 11, 2009

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. RIC 2009Human Factors DAC/ITAAC ReviewsMichael JungeUSNRC/NRO/DCIPMarch 11, 2009

  2. Impacts on Fuel Load Schedule • Licensed operators are required to load fuel. • Prior to fuel load, Industry estimates two licensed operator examinations will be required. • Operator license exams require a plant-referenced simulator. (10 CFR 55.46) • Certification of the simulator requires a complete control room design. • A complete control room design requires an HFE program implementation.

  3. HFE Program Review • HFE program review approach • Program level review • Implementation Plan level review • Results review • Sequence of reviews

  4. NUREG 0711 chart

  5. Impact of Review Approach on DAC/ITAAC Inspection Resources Designs Approved To-Date Designs Under Review Applicants submitted high-level HFE program descriptions Applicants providing detailed HFE program Implementation Plans Staff conducted program-level reviews Staff is conducting implementation plan level reviews Implementation Plan deferred to DAC/ITAAC Completed Implementation Plans provide detailed acceptance criteria DAC/ITAAC inspection of Implementation Plan & results DAC/ITAAC inspection of results against detailed acceptance criteria Significant resources (staff & time) required for DAC/ITAAC inspection Fewer resources required for focused inspections

  6. Bottom Line • DAC/ITAAC inspection sequence must be managed to support fuel load schedules. • DAC/ITAAC closure resources for designs approved to-date must be budgeted appropriately.