STH 29 and CTH O Construction. Project Manager: Richard Simon Project Leader: Dave Julson. Overview. Cost - $24.5 M Schedule Let: June 2012 Construction: August 2012 – November 2013 Major Features Structures: 3 box culverts, 2 large culverts, 1 bridge 3.5 miles STH 29
E N D
STH 29 and CTH O Construction Project Manager: Richard Simon Project Leader: Dave Julson
Overview • Cost - $24.5 M • Schedule • Let: June 2012 • Construction: August 2012 – November 2013 • Major Features • Structures: 3 box culverts, 2 large culverts, 1 bridge • 3.5 miles STH 29 • 3 miles local roads • Wetland Mitigation Site • Excavation: 400,000 CY Rock, 400,000 CY Common, 100,000 CY Borrow • Staging • 4 stages • Counter directional traffic • ADT : 20,000