STH 29 and CTH O Construction

STH 29 and CTH O Construction. Project Manager: Richard Simon Project Leader: Dave Julson. Overview. Cost - $24.5 M Schedule Let: June 2012 Construction: August 2012 – November 2013 Major Features Structures: 3 box culverts, 2 large culverts, 1 bridge 3.5 miles STH 29

nansen
Download Presentation

STH 29 and CTH O Construction

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. STH 29 and CTH O Construction Project Manager: Richard Simon Project Leader: Dave Julson

  2. Overview • Cost - $24.5 M • Schedule • Let: June 2012 • Construction: August 2012 – November 2013 • Major Features • Structures: 3 box culverts, 2 large culverts, 1 bridge • 3.5 miles STH 29 • 3 miles local roads • Wetland Mitigation Site • Excavation: 400,000 CY Rock, 400,000 CY Common, 100,000 CY Borrow • Staging • 4 stages • Counter directional traffic • ADT : 20,000

  3. Wetland Mitigation Site

  4. Wetland Mitigation Site

  5. Grading Challenges

  6. Erdman Creek

  7. B-37-439

  8. B-37-439

  9. B-37-439

  10. Stream Enhancements

  11. Grubbing Recycling

  12. Rock Excavation

  13. Rock Excavation

  14. Erosion Control

  15. Erosion Control

  16. B-37-408

  17. Barrier Wall