1 / 25

Fundamentals of Buffers

Learn how to collaboratively develop plans, assign resources, establish commit dates, and monitor project health for successful outcomes. Discover strategies for sizing and configuring buffers tailored to project risks and task types. Ensure project success by utilizing top-down and bottom-up buffer sizing methods. Navigate through project milestones and track progress with Buffer Task settings, Milestone Pace Cars, and Buffer Charts. Monitor project health with detailed guidelines on changing buffers if needed.

naomip
Download Presentation

Fundamentals of Buffers

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Fundamentals of Buffers A revolution in how things get done!

  2. Effective Planning • Plan Development  collaboratively with team • Layout tasks and their dependencies • Assign resources (no unassigned tasks in near-term) • Review resource loading  update plan as necessary • Assign project priority to major milestones • Move higher priority projects ahead of lower priority projects • Size buffers  collaboratively with stakeholders • Establishes commit date between project team and the business • Monitor project health  find ways to finish before commit date • Repeat #1, 2 & 4 frequently  pivot as needed • Rolling Wave Planning

  3. Variability Work (hours) • Duration (days) = Availability (hours/day) Work + X% • Duration (days) = Availability - Y% ∴ Duration will vary!

  4. Buffer Unbuffered Date (low probability) Buffered Date (commit/due date)

  5. Buffer Unbuffered Date (low probability) Buffered Date (commit/ due date)

  6. Sizing the Buffer Remaining Work Today Unbuffered Duration

  7. Sizing the Buffer • Top-Down Method • Low/Medium Project Risk Profile • Technical challenges are typical of other products (incremental advances in technology) • Critical resources are dedicated to the project (available when you need them) • Buffer size = 1/3*(Unbuffered Duration) • High Project Risk Profile • High technical risks (technology that’s new to the company and/or world) • Critical resources are not available when you need them (busy on other projects) • Buffer size = 1/2*(Unbuffered Duration) or more!

  8. Sizing the BufferTop-Down = 13.5 weeks = 5 business days/week * 13.5 weeks = ~68 business days Unbuffered Duration Buffer = 1/3*(68) = ~23 business days

  9. Sizing the Buffer • Bottom-Up Method • Separate tasks by type: Work vs. Monitor • Look at the critical path • Ask, is this critical task’s duration a 50/50-type or a 90/10-type estimate? • Buffer Size = sum of the critical path task variances (days)

  10. Sizing the BufferWork Tasks 7 days 2 days Work tasks (50/50) = 9 days  Buffer contribution = 50%*(9) = 4.5 days

  11. Sizing the BufferMonitor Tasks 3 days 13 days Monitor tasks (90/10) = 16 days  Buffer contribution = 10% * 16 = 1.6 days  Buffer Size = 4.5 + 1.6 = ~6 days

  12. Sizing the Buffer • Top-Down • Bottom-Up • Come to an agreement with stakeholders and commit Buffer = 8 business days Buffer = 6 business days Buffer = 7 business days

  13. Configuring Buffers Buffer Task Tracking Milestone Pace Car Tracking Milestone Pace Car Buffer Task

  14. Buffer Task • Overlap the buffer’s start date with the milestone • Buffer’s Duration = Buffer Size + 1 day • Make the title explicit • Suggested format: Buffer/(Milestone Name) • e.g. Buffer/OQ Complete 8 days 7 days

  15. Buffer Task Settings Buffer Report: unique code Tracking Start Date: mm/dd/yy Tracking Start Date The day you start tracking the milestone’s movement

  16. Tracking Milestone Settings • Buffer Track In: unique code • (Must) unique code = same value used in the buffer task • e.g. Buffer Track In: Project A-OQ Complete Buffer Track In:(unique code)

  17. Pace Car Size Offset • Optional • Visualize the yellow region of the Buffer Chart in the Game Plan • It changes throughout the project (Offset) Pace Car Size = 5 days Pace Car Size = 5 days Offset = 13 days Offset = 5 days

  18. Pace Car & Project Health If the Tracking Milestone… • Is left of the Buffer Task’s start date, the project is below the green region on the Buffer Chart – Ahead. • Is left of the Pace Car’s start date, the project is in the green region on the Buffer Chart – Low Risk. • Is above the Pace Car, the project is in the yellow region on the Buffer Chart – Some Risk. • Is right of the Pace Car’s end date, the project is in the red region on the Buffer Chart – At Risk. • Is right of the Buffer Task’s end date, the project is above the red region on the Buffer Chart - Behind.

  19. Pace Car Settings • Duration =15% of the buffer’s duration • e.g. if buffer’s duration = 30 days, then… • Pace Car’s duration = 15%*30 = 4.5  5 days • Buffer Chart: unique code (PaceCar) • unique code = same value used in the buffer task • (PaceCar) = must follow unique code; used to define that this is a Pace Car and not a buffer or tracking milestone. • e.g. Buffer Chart: Project A-OQ Complete (PaceCar) 5 days Buffer Chart:unique code (PaceCar)

  20. Buffer Chart Settings • unique code = same value used in the buffer task 

  21. Monitor Project Health Edit Title

  22. Changing Buffers • Once projects are active and buffer size has been agreed to with the stakeholders, changes must be made using an approval process. • Playbook Process Owner Team to define & implement the process • If approved… • Do not change the original buffer • Rename it to show it was the original • Create and configure a new buffer task and pace car • Specify a new, unique Buffer Report code leaving the original intact

  23. Learn and Improve • If buffer end dates are consistently missed… • Ask why and look for root causes • Challenge project risk profile assumptions

  24. Buffer Task • Until the project starts, leave Buffer task’s lifecycle Planned • (Could) Make it a successor to the milestone • When the project starts, Schedule the Buffer Task • (Must) No predecessors, break link to the milestone Planned Scheduled Link No Link

  25. Need a hand? • Contact Technical Support at support@accuer.com • We’re here to help!

More Related