250 likes | 262 Views
Learn how to collaboratively develop plans, assign resources, establish commit dates, and monitor project health for successful outcomes. Discover strategies for sizing and configuring buffers tailored to project risks and task types. Ensure project success by utilizing top-down and bottom-up buffer sizing methods. Navigate through project milestones and track progress with Buffer Task settings, Milestone Pace Cars, and Buffer Charts. Monitor project health with detailed guidelines on changing buffers if needed.
E N D
Fundamentals of Buffers A revolution in how things get done!
Effective Planning • Plan Development collaboratively with team • Layout tasks and their dependencies • Assign resources (no unassigned tasks in near-term) • Review resource loading update plan as necessary • Assign project priority to major milestones • Move higher priority projects ahead of lower priority projects • Size buffers collaboratively with stakeholders • Establishes commit date between project team and the business • Monitor project health find ways to finish before commit date • Repeat #1, 2 & 4 frequently pivot as needed • Rolling Wave Planning
Variability Work (hours) • Duration (days) = Availability (hours/day) Work + X% • Duration (days) = Availability - Y% ∴ Duration will vary!
Buffer Unbuffered Date (low probability) Buffered Date (commit/due date)
Buffer Unbuffered Date (low probability) Buffered Date (commit/ due date)
Sizing the Buffer Remaining Work Today Unbuffered Duration
Sizing the Buffer • Top-Down Method • Low/Medium Project Risk Profile • Technical challenges are typical of other products (incremental advances in technology) • Critical resources are dedicated to the project (available when you need them) • Buffer size = 1/3*(Unbuffered Duration) • High Project Risk Profile • High technical risks (technology that’s new to the company and/or world) • Critical resources are not available when you need them (busy on other projects) • Buffer size = 1/2*(Unbuffered Duration) or more!
Sizing the BufferTop-Down = 13.5 weeks = 5 business days/week * 13.5 weeks = ~68 business days Unbuffered Duration Buffer = 1/3*(68) = ~23 business days
Sizing the Buffer • Bottom-Up Method • Separate tasks by type: Work vs. Monitor • Look at the critical path • Ask, is this critical task’s duration a 50/50-type or a 90/10-type estimate? • Buffer Size = sum of the critical path task variances (days)
Sizing the BufferWork Tasks 7 days 2 days Work tasks (50/50) = 9 days Buffer contribution = 50%*(9) = 4.5 days
Sizing the BufferMonitor Tasks 3 days 13 days Monitor tasks (90/10) = 16 days Buffer contribution = 10% * 16 = 1.6 days Buffer Size = 4.5 + 1.6 = ~6 days
Sizing the Buffer • Top-Down • Bottom-Up • Come to an agreement with stakeholders and commit Buffer = 8 business days Buffer = 6 business days Buffer = 7 business days
Configuring Buffers Buffer Task Tracking Milestone Pace Car Tracking Milestone Pace Car Buffer Task
Buffer Task • Overlap the buffer’s start date with the milestone • Buffer’s Duration = Buffer Size + 1 day • Make the title explicit • Suggested format: Buffer/(Milestone Name) • e.g. Buffer/OQ Complete 8 days 7 days
Buffer Task Settings Buffer Report: unique code Tracking Start Date: mm/dd/yy Tracking Start Date The day you start tracking the milestone’s movement
Tracking Milestone Settings • Buffer Track In: unique code • (Must) unique code = same value used in the buffer task • e.g. Buffer Track In: Project A-OQ Complete Buffer Track In:(unique code)
Pace Car Size Offset • Optional • Visualize the yellow region of the Buffer Chart in the Game Plan • It changes throughout the project (Offset) Pace Car Size = 5 days Pace Car Size = 5 days Offset = 13 days Offset = 5 days
Pace Car & Project Health If the Tracking Milestone… • Is left of the Buffer Task’s start date, the project is below the green region on the Buffer Chart – Ahead. • Is left of the Pace Car’s start date, the project is in the green region on the Buffer Chart – Low Risk. • Is above the Pace Car, the project is in the yellow region on the Buffer Chart – Some Risk. • Is right of the Pace Car’s end date, the project is in the red region on the Buffer Chart – At Risk. • Is right of the Buffer Task’s end date, the project is above the red region on the Buffer Chart - Behind.
Pace Car Settings • Duration =15% of the buffer’s duration • e.g. if buffer’s duration = 30 days, then… • Pace Car’s duration = 15%*30 = 4.5 5 days • Buffer Chart: unique code (PaceCar) • unique code = same value used in the buffer task • (PaceCar) = must follow unique code; used to define that this is a Pace Car and not a buffer or tracking milestone. • e.g. Buffer Chart: Project A-OQ Complete (PaceCar) 5 days Buffer Chart:unique code (PaceCar)
Buffer Chart Settings • unique code = same value used in the buffer task
Monitor Project Health Edit Title
Changing Buffers • Once projects are active and buffer size has been agreed to with the stakeholders, changes must be made using an approval process. • Playbook Process Owner Team to define & implement the process • If approved… • Do not change the original buffer • Rename it to show it was the original • Create and configure a new buffer task and pace car • Specify a new, unique Buffer Report code leaving the original intact
Learn and Improve • If buffer end dates are consistently missed… • Ask why and look for root causes • Challenge project risk profile assumptions
Buffer Task • Until the project starts, leave Buffer task’s lifecycle Planned • (Could) Make it a successor to the milestone • When the project starts, Schedule the Buffer Task • (Must) No predecessors, break link to the milestone Planned Scheduled Link No Link
Need a hand? • Contact Technical Support at support@accuer.com • We’re here to help!