E N D
1. St Lucie Pressurizer Examinations Phil Ashwin
EPRI
3rd International Workshop of
In-service Inspection Qualification Bodies
October 15-16, 2008
Vienna, Austria
2. Recap from 2007 Recommendations
Operational Experience (OE) Feedback is important and should be carefully analysed to see if and how it may influence the Qualification file.
It is recommended the there is a loop in the Qualification process to allow for Operational Experience Feedback.
3. October 10th 2007… How do the results of ISI get back to the qualification process? Summary
Qualified procedures provide reliable examinations when performed in the qualified manner
The component configuration must be appropriate
We need to do a better job of characterizing the surface condition and dealing with it properly
The search unit must be selected carefully
Data must be acquired and analyzed carefully
All available factors must be evaluated before reaching a conclusion
Putting too much weight on the details of the earliest information disseminated to the industry can be harmful
This often is not the plant’s official OE
4. Relevance Presentation provides an example and the consequence of
Putting too much weight on the details of the earliest information disseminated to the industry can be harmful
5. Overview of the St Lucie Pressurizer Examinations Florida Power & Light removed the pressurizer from St Lucie Unit 1 and donated it to Nuclear Regulatory Commission (NRC) Office of Research
In collaboration with NRC, EPRI Materials Reliability Program (MRP) and NDE examined the nozzle welds using manual UT
360° indications were reported
“Either SCC or multiple fabrication defects”
If SCC, the operating basis of eight PWRs was challenged
NRC Office of Regulation prepared to shut down the eight PWRs for inspection (Friday, March 7)
Intensive NDE data acquisition confirmed no major cracking was present (Friday, March 14)
NRC cancelled the shutdown activity
6. Topics Retirement of St Lucie pressurizer
Initial NDE of safety nozzle welds
NRC response to initial NDE
Industry mobilization
Enhanced NDE results
NRC decision
Destructive analysis
Industry self-assessment
Summary
7. Topics Retirement of St Lucie pressurizer
Initial NDE of safety nozzle welds
NRC response to initial NDE
Industry mobilization
Enhanced NDE results
NRC decision
Destructive analysis
Industry self-assessment
Summary
8. Retirement of St Lucie pressurizer Florida Power & Light (FPL) chose to replace its pressurizer
Faced high inspection and mitigation costs
Pressurizer design enabled removal
FPL donated the pressurizer to USNRC Office of Regulatory Research (RES)
Shipped to Studsvik hot storage facility in Memphis
RES planned an NDE round-robin followed by destructive analysis (DE)
First step: perform a UT survey of the nozzles, to learn whether there was any cracking to support the NDE research project
9. Topics Retirement of St Lucie pressurizer
Initial NDE of safety nozzle welds
NRC response to initial NDE
Industry mobilization
Enhanced NDE results
NRC decision
Destructive analysis
Industry self-assessment
Summary
10. Initial NDE of pressurizer nozzles NRC RES had no budget to examine the nozzles, and requested EPRI Materials Reliability Program (MRP) to collaborate
MRP funded EPRI NDE Program to engage an NDE vendor to examine the dissimilar metal welds
Structural Integrity Associates
Manual phased array UT
Dye penetrant (PT)
11. Initial NDE of pressurizer nozzles PT results
A few short, linear indications on the inside surface (ID) of the welds
A few rounded indications on the outside surface (OD)
12. Initial NDE of pressurizer nozzles UT results
Reflectors were numerous, present 360° around circumference
Depth about 80%
Detected in A, B, and C safety nozzles
13. Initial NDE of pressurizer nozzles Indication profile built from 19 measurement points
14. Topics Retirement of St Lucie pressurizer
Initial NDE of safety nozzle welds
NRC response to initial NDE
Industry mobilization
Enhanced NDE results
NRC decision
Destructive analysis
Industry self-assessment
Summary
15. NRC response to initial NDE The initial NDE was reported to NRC RES
There was interest and discussion of follow up work
RES communicated the data to NRC Office of Nuclear Reactor Regulation (NRR)
On May 7, senior NRR management indicated an intention to require eight PWR units to shut down for immediate inspection or mitigation
These eight units were operating until their next scheduled outage based on an EPRI MRP advanced finite element analysis (FEA) indicating that 360°, deep circumferential cracks cannot exist without leakage
If the St Lucie indications were SCC, it would challenge the FEA
16. Topics Retirement of St Lucie pressurizer
Initial NDE of safety nozzle welds
NRC response to initial NDE
Industry mobilization
Enhanced NDE results
NRC decision
Destructive analysis
Industry self-assessment
Summary
17. Industry mobilization NRR’s intention was communicated to industry at about noon on Friday, March 7
EPRI MRP and NDE coordinated a rapid response effort to obtain more advanced NDE data, to be followed by DE
DE required NRC RES permission (they own it)
Vendors onsite at Studsvik in Memphis, beginning Saturday noon:
LMT – encoded phased array UT
WesDyne – encoded ET scanned on the ID
IveyCooper – radiography
Four EPRI staff provided oversight and coordination
NRC RES staff member and consultant
Utility representative from MRP
18. Topics Retirement of St Lucie pressurizer
Initial NDE of safety nozzle welds
NRC response to initial NDE
Industry mobilization
Enhanced NDE results
NRC decision
Destructive analysis
Industry self-assessment
Summary
19. Enhanced NDE results Encoded phased array UT
Showed clear evidence that no significant SCC was present in any of the three safety nozzle welds
Evidence of extensive fabrication defects
Not surface-connected
Encoded ET on the inside surface
A few, short (~0.5” long) linear indications
No evidence of extensive surface-connected cracking
Radiography
No indications of cracking
Indications of fabrication defects
20. UT rollout showing embedded defects St Lucie Safety Nozzle A
21. Correlation of UT, PT, ET, RT
22. Correlation of UT, PT, ET, RT
23. Correlation of UT, PT, ET, RT
24. Topics Retirement of St Lucie pressurizer
Initial NDE of safety nozzle welds
NRC response to initial NDE
Industry mobilization
Enhanced NDE results
NRC decision
Destructive analysis
Industry self-assessment
Summary
25. NRC decision NRC RES and NRR were kept closely informed of all activities, from the beginning at Friday noon
Informed NRC on Monday (maybe Tuesday) that there was no evidence of significant SCC
By Wednesday night the picture was complete
On Thursday there was a public meeting with senior NRR and RES management
Senior utility representatives presented industry’s conclusion that there was no safety concern
EPRI provided discussion of the NDE methods and results
On Friday NRC notified the eight units that their operational basis was intact; no unscheduled shutdown would be required
26. Topics Retirement of St Lucie pressurizer
Initial NDE of safety nozzle welds
NRC response to initial NDE
Industry mobilization
Enhanced NDE results
NRC decision
Destructive analysis
Industry self-assessment
Summary
27. Destructive analysis With NRC RES permission, EPRI MRP has cut off one of the three safety nozzles and performed destructive examination
The results have not been published yet
The DE showed:
No service-induced cracking
Several fabrication defects in the body of the weld
28. Topics Retirement of St Lucie pressurizer
Initial NDE of safety nozzle welds
NRC response to initial NDE
Industry mobilization
Enhanced NDE results
NRC decision
Destructive analysis
Industry self-assessment
Summary
29. Industry self-assessment A self-assessment was performed to identify any lessons that could be learned from the St Lucie event, and applied to future emergent issues
Several recommendations resulted from the assessment
A key one: improvement and regularization of communications with NRC staff
Another: keeping senior utility management aware of any research activities that could impact operating plants
30. Topics Retirement of St Lucie pressurizer
Initial NDE of safety nozzle welds
NRC response to initial NDE
Industry mobilization
Enhanced NDE results
NRC decision
Destructive analysis
Industry self-assessment
Summary
31. Summary The retired St Lucie pressurizer was found to contain no service-induced cracking
Manual UT made a conservative interpretation, recognizing the possibility that the indications could be fabrication defects
Encoded UT showed clearly that there was no significant cracking
Destructive examination results will be published shortly
32. October 10th 2007… How do the results of ISI get back to the qualification process? Summary
Qualified procedures provide reliable examinations when performed in the qualified manner
The component configuration must be appropriate
We need to do a better job of characterizing the surface condition and dealing with it properly
The search unit must be selected carefully
Data must be acquired and analyzed carefully
All available factors must be evaluated before reaching a conclusion
Putting too much weight on the details of the earliest information disseminated to the industry can be harmful
This often is not the plant’s official OE
33. For discussion As qualification bodies,
How can we be more effective at sharing Operational Experience?
What are the IQB responsibilities following the qualification and application of the NDE system?
Does being proactive challenge being independent?
34. Questions