This document summarizes the closing report of the AltPHY Task Group meeting held in January 2003. It includes information about the accomplishments, officer slate, technical review, approval of working documents, contribution presentations, and future plans.
E N D
Project: IEEE P802.15 Working Group for Wireless Personal Area Networks (WPANs) Submission Title: [AltPHY Task Group Closing Report Jan 03] Date Submitted: January, 2003 Source: [Chuck Brabenac] Company: [Intel] Address: [2111 NE 25th Ave, Hillsboro, OR 97124] Voice: [503-264-8575], FAX: [503-264-3483], E-Mail: [chuck.brabenac@intel.com] Re: [] Abstract:[] Purpose: [] Notice: This document has been prepared to assist the IEEE P802.15. It is offered as a basis for discussion and is not binding on the contributing individual(s) or organization(s). The material in this document is subject to change in form and content after further study. The contributor(s) reserve(s) the right to add, amend or withdraw material contained herein. Release: The contributor acknowledges and accepts that these viewgraphs becomes the property of IEEE and may be made publicly available by P802.15. Chuck Brabenac, Intel R&D
First meeting as a Task Group • Upshot: Great start -- accomplished all objectives! • Slate of officers confirmed • Chair: Bob Heile • Vice-chair: Chuck Brabenac • Technical editor: Rick Roberts • Secretary: Len Miller Chuck Brabenac, Intel R&D
Technical Review & Editing Work Accomplished • Selection Criteria (03/031) • Review of edits since last meeting -- Jason Ellis • Session & & subcommittee editing, led by Rick Roberts • 22 comments processed/editing • Selection Process (03/041), led by Ian Gifford • Review/history of process definition • Session & subcommittee editing Chuck Brabenac, Intel R&D
Motions to approve TG3a working documents • Approved ALL 3 key documents!!!(75% WG roll-call vote) • Technical requirements (03/030r0) • 40-Yes (87%) / 3-No / 3-Abstain • Selection Criteria (03/031r6) • 42-Yes (91.3%) / 0-No / 4-Abstain • Selection Process (03/041r7) • 27-Yes (93.1%) / 2-No / 0-Abstain • Sets the stage for initial proposals in March Chuck Brabenac, Intel R&D
Contribution Presentations • “Summary of 2001/2002 SG3a activities and UWB contributions” • Jason Ellis 03/029r0 • “Use of the SG3a UWB channel model for PHY proposal evaluations” • Matt Welborn 03/040r1 Chuck Brabenac, Intel R&D
Other related sessions • Joint meeting with 802.19 COEX • 15.4/UWB interest group Chuck Brabenac, Intel R&D
Looking ahead • Reviewed project timeline • March: First round of proposals • May: Second round • July: Down-selection begins, start drafting • Sept: Draft improvements • Work Plan between January and March • Proposal intent responses (due by 03Feb2003) • CFP responses (due by 03Mar2003) Chuck Brabenac, Intel R&D