CFS / Global – 29 September, 2010 PM Report:. SB2009: 4 two-day workshops form the core of ‘TOP LEVEL CHANGE CONTROL’ as advised by AAP, PAC and etc Written Workshop ‘Proposal’ for BAW # 1 sent to the GDE Project Director 28 September. Follows posted summary; to be posted (BAW Indico)
E N D
CFS / Global – 29 September, 2010PM Report: • SB2009: • 4 two-day workshops form the core of ‘TOP LEVEL CHANGE CONTROL’ • as advised by AAP, PAC and etc • Written Workshop ‘Proposal’ for BAW # 1 sent to the GDE Project Director 28 September. • Follows posted summary; to be posted (BAW Indico) • Reviews: • AAP? (Panel to receive BAW Proposal??) • PAC: November 11-12 • Focus on SRF industrialization and positron RD • Detector / Accelerator sessions more closely inter-twined Marc Ross, Fermilab
TLCC Process Physics and detector input / representation mandatory • Baseline Assessment Workshops • Face to face meetings • Open to all stakeholders • Plenary Marc Ross, Fermilab
Physics and Detector Group Participation (starting point: Joint ‘Scope and Parameters’ Plenary session at LCWS10) Similar session at IWLC10 enhance interactions and facilitate joint work 2010 - Workshop Connections: 5 contact persons identified: Brau, Buesser, Fujii, Markiewicz, Thomson 3 / 5 attended BAW 1. Marc Ross, Fermilab
IWLC10 Tuesday AM Plenary Session Marc Ross, Fermilab
Interim Report Marc Ross, Fermilab
be a significant milestone for the GDE. comprehensively summarize the significant progress be a 'half-way' point in the TD Phase be a snapshot of the R&D be forward looking content is encouraged, emphasize what has been achieved. be positive and upbeat, capture the significant progress Use of graphics, photographs etc. are strongly encouraged emphasize the international nature of our work. (Only R&D that is in the TDR R&D Plan should be included). Interim Report will : Marc Ross, Fermilab
We understand that much of the R&D is still on-going, - timing of such status reports is never optimal. Technical Editorial Board (TEB) has been formed one or two members of this editorial board have been assigned as key contacts TEB members are your primary points of contact the report material will be sent to our Communicators, will be working with a professional layout firm to produce the finished document. We look forward to working with you on this exciting project. Please help us as best you can to show what we have achieved in the last years, working together in a true international environment. Marc Ross, Fermilab
Wednesday ‘Technical Area’ Webex meetings, 06-11.2010 To be used to prepare for Baseline Workshops – as needed
2010 / 2011 – Schedule • LOwLBT (FLASH): 4-7 Oct. DESY – postponed to 14-18 Feb • ECloud ’10: 8-12 Oct. Ithaca • IWLC 2010: 18-22 Oct. Geneva • (DESY / XFEL – PM+Peter G., 25-26 Oct.) • ILC PAC: 11-12 Nov. Eugene • SiD collaboration meeting 15-17 Nov. Eugene • Second Baseline Workshop: 18-21 Jan. SLAC • ALCPG11: 19-23 March, Eugene • (US PAC: 28 March – 1 April, New York) • ILC PAC: 19-20 May, Taipei • Next LCWS – September or October, 2011, Spain(?) Marc Ross, Fermilab