1 / 17

CE 2710 Transportation Engineering

CE 2710 Transportation Engineering. Wesley Marshall, P.E. University of Connecticut March 2009. The Four-Step Model. The Basic Transportation Model…. Inputs. Study Area Zones Attributes of Zones Socioeconomic Data Land Use Data “Cost” of Travel btw. Zones The Road Network.

Download Presentation

CE 2710 Transportation Engineering

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CE 2710Transportation Engineering Wesley Marshall, P.E. University of ConnecticutMarch 2009 The Four-Step Model

  2. The Basic Transportation Model… Inputs • Study Area Zones • Attributes of Zones • Socioeconomic Data • Land Use Data • “Cost” of Travel btw. Zones • The Road Network • Traffic Volume by Road Link • Mode Splits • Emissions Outputs

  3. What’s in the Black Box? The Four-Step Model

  4. The Four-Step Modeling Process… • Trip Generation • Trip Distribution • Mode Choice • Trip Assignment

  5. Overview of the Four-Step Model

  6. TRIP GENERATION } Input: - No. of Housing Units - Office, Industrial SF - HH Size - Income - No. of Cars Land Use Data Household Socioeconomic Data Examples of HH socioeconomic data } Examples of land use data Iterative Process Output: - i.e. columns of trip productions and trip attractions Trip Ends by purpose TRIP DISTRIBUTION Input: Trip Ends by purpose Output: - a matrix of trips between each TAZ… also called a “trip table” Trip Interchanges MODE CHOICE Input: Trip Interchanges Output: Trip Table by Mode - a matrix of trips between each TAZ for each type of mode TRIP ASSIGNMENT Input: Trip Table by Mode Output: Daily Link Traffic Volumes - i.e. traffic flows on network, ridership on transit lines

  7. P/A versus O/D Trip Production Home end of the trip (where the need to make a trip is generated) Trip Attraction Non-home end of the trip (where the need to make a trip is satisfied) Trip Origin # of trips that begin in a zone Trip Destination # of trips the end in a zone

  8. Zone 1Residential Zone 2Non-Residential Zone 1 = Production & Origin Zone 1 = Production & Destination AM Peak Hour Trip PM Peak Hour Trip Zone 2 = Attraction & Destination Zone 2 = Attraction & Origin

  9. Some General Problems with the Conventional Methodology • Focus on vehicular traffic • Better models typically have a transit component • Typically forecasts huge increases in traffic • Leads to engineers building bigger roads to accommodate “forecast” traffic • Which leads to induced traffic and congestion… right back where we started when we needed the bigger roads in the first place

  10. Some General Problems with the Conventional Methodology • Pedestrians and bicyclists are rarely included • Level of geography is difficult for non-motorized modes • Network scale is insignificant • Input variables are too limited

  11. Four-Step ModelProblem

  12. 4-Step Model Problem Given the zone data above and the tables/charts on the following page, Find the vehicle flows on the road network to the left using “all-or-nothing” traffic assignment. This will require completing all four steps of the transportation planning process…

  13. 4-Step Model Problem

  14. Pi Aj Fij Tij = ΣAjFij (Productions)(Attractions)(Friction Factor) = Sum of the (Attractions x Friction Factors) of the Zones Basic Step-By-Step Process • Trip Generation • Using the socioeconomic & land use data along with the cross-classification tables, come up with the number of trip productions & attractions for each zone… • Trip Distribution • Create trip interchange table based upon “friction” between zones using the travel time matrix, the F-Factor graph, and the Gravity Model… Gravity Model • Mode Choice • Create a separate trip interchange table for each mode based upon, in this case, the relationship of land use household density the percentage of people walking & biking… • Trip Assignment • Distribute the vehicle trips to the street network using “all-or-nothing” traffic assignment by assuming that all trips are accommodated on the shortest possible path between zones…

  15. 2 1 Travel Time = 2 Travel Time = 6 Travel Time = 5 Travel Time = 2 3 4 Travel Time = 5

  16. 586 + 97 = 683 2 1 Travel Time = 2 787 + 159 + 40 = 986 159 + 658 = 817 40 + 66 = 106 Travel Time = 6 97 + 215 = 312 Travel Time = 5 0 95 Travel Time = 2 527 32 3 4 Travel Time = 5 131

  17. 2 1 3 4

More Related