TEXAS GENERAL LAND OFFICE JERRY PATTERSON - COMMISSIONER. Coastal Erosion Planning and Response Act (CEPRA) Program. Cycle 5 Priorities and Dredging Needs Matthew Mahoney, P.G. Coastal Erosion Planning and Response Act (CEPRA) Program. Enacted by Texas Legislature in 1999.
E N D
TEXAS GENERAL LAND OFFICE JERRY PATTERSON - COMMISSIONER Coastal Erosion Planning and Response Act (CEPRA) Program Cycle 5 Priorities and Dredging Needs Matthew Mahoney, P.G.
Coastal Erosion Planning and Response Act (CEPRA) Program • Enacted by Texas Legislature in 1999. • State Funding: • - 80th Texas Legislature appropriated ~$17.2 million for Cycle 5 in FY08-09 – biggest funding cycle yet • Match requirements for Cycle 5: • - Beach Projects - 75% CEPRA, 25% Partner • - Marsh Projects - 60% CEPRA, 40% Partner
Coastal Impact Assistance Program (CIAP) The Energy Policy Act of 2005 amended the Outer Continental Shelf Lands Act (43 U.S.C. 1356a) to provide for the disbursement of $250 million each year from 2007 through 2010 to coastal states and their respective coastal political subdivisions as part of CIAP. State Funding: - $48,591,202 each year for four years
CEPRA Cycle 5 Projects • By combining CEPRA projects with CIAP will finally allow Texas to conduct large-scale beach nourishment projects on the Gulf Coast and large-scale marsh restoration projects in the Texas bay systems. • Projects requiring dredging: • West Galveston Island – 1 millon cyds • Town of South Padre – 500,000 cyds • Little Beach, Bolivar,Tx. – 200,000 cyds (TxDot) • Texas Point – 500,000 cyds (Corps) • Rollover Pass – 150,000 cyds (Corps) • Brazos Santiago – 400,000 cyds (Corps)
West Galveston Island Beach Nourishment • Project Description: • Nourish Gulf beach from west end of the seawall for three miles with up to 1 million cyds of beach quality sand dredged from a permitted sand source. • PROJECT BUDGET: $13.5 mil
West Galveston Island Beach Nourishment • 12 miles from source to placement area • 30 foot depth offshore is approximately 10,000 ft. from shore. • What I need from you today is input on dredging and transport methodologies so they can be included in permitting options.
THANK YOU TEXAS GENERAL LAND OFFICE MATTHEW MAHONEY, P.G. Coastal Geologist/Project Manager Coastal Erosion Planning and Response Act (CEPRA) Program JERRY PATTERSON – Commisssioner Texas General Land Office JODY HENNEKE – Deputy Commissioner Coastal Resources Program Area EDDIE FISHER – Director Coastal Protection Division