An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Overview Fairfax Infrastructure Upgrades, Phase 2 John Hanks

  2. Project Goals • Increase size of uplink pipes • Finish upgrade of residence halls to switched 10Mbs to per pillow (‘dorm’) • Upgrade office and classroom ports to switched 10/100 (‘office’) • Add more ports in public areas

  3. Description • Actually 4 independent projects • Dorm upgrades • Enterprise Hall upgrades • Johnson Center/Fenwick • Robinson Hall Upgrades FOR MORE INFO... For updated project plan information, see http://netinfo.gmu.edu/FairfaxUpgrade

  4. ‘Dorm’ Upgrades • Upgrade software on existing units • Load 4.0 boot and run code • Reconfigure management network • Equipment replacement in 3 areas • Patriots Village - 3 & 9 • Commonwealth and Dominion • Student Apartments • Each independent ‘mini project’

  5. ‘Office’ Upgrades • Common ‘Master’ Plan for All Three • Announce Upgrades starting • Meet with technical contacts • Open meeting with all building occupants • Define schedule for implementation • Install equipment • Management would prefer upgrading during normal working hours

  6. ‘Office’ Upgrades – By building: • Announce Upgrades • Now you know… • Meet with technical contacts • Define all users in building • Identify any special needs • Review building upgrade plan • Set tentative dates for installation

  7. ‘Office’ Upgrades – By building: • Open meeting with all occupants • Confirm all users in building • Review identified special needs • Review building upgrade plan • Select dates for installation • Define Schedule for Implementation • Define and post final Implementation Schedule • Install Equipment • Post reminders week before • Install equipment

  8. Building Overview - Enterprise • Enterprise Hall • Total of three networks • Backbone • SOM • Classroom • Each network already properly defined • No IP changes • Available rack space in TSE • Can do floor by floor

  9. Building Overview – JC/Fenwick • Johnson Center & Fenwick Library • Total of six networks Backbone Admissions Library AIL Johnson Labs S&T I Labs • Each network already properly defined • No IP changes • Available rack space in TSE • Can do floor by floor (or closet by closet)

  10. Building Overview - Robinson • Robinson Hall • Total of three networks • Backbone • Robinson Labs • DoIIIT • Backbone network ‘a real mess’ • Almost all IPs must change (‘.12-.15) • Netmask and router must change (‘.12.1) • No rack space available in TSEs • Robinson A - must do entire building at once • Robinson B - Slightly more flexible • Harris Theatre - equipment change can wait

  11. Building Specifics - Robinson • Three Phase Backbone Transition • Sweep through building changing IPs • Convert as many devices as possible to DHCP • Move all statics to ‘.14 (B) and ‘.15(A) networks • UCIS & department keep static lists • Change Backbone Address • Change address on router and DHCP server • Change netmask and router on static list • Upgrade closet equipment • Robinson A – all floors out until upgraded • Robinson B – each floor will work until upgraded • Harris Theatre – will work until upgraded

  12. Robinson Upgrade Plan – tentative • Change address on router • Change DHCP server • Start changing netmask & router on static addresses from list Robinson B, Harris, Robinson A • At same time, start upgrading equipment by closet • 1A, 2A, 3A, 4A • 3B, 4B, 2B, 1B • Harris

  13. Phase 2 ‘Office’ Summary • Happening this Summer • Schedule to be determined by users • Enterprise, Johnson, Fenwick • No address changes required • Schedule flexible to closet level • Robinson Hall • IP information must change • Must complete all once started • Order of upgrades pretty much fixed