PO1C SIT1 Testing organisation and governancev. 0.127.04.2014
Content 1. Introduction 2. Test governance 2.1 Test scope definition - SIT1 test scenarios and blocks // artefact: RU_PO1C_Test scenario design.xlsx 2.2 SIT1 test estimation // artefact: this document - test preparation estimation // artifact: RU_PO1C_Scenario preparation progress.xlsx - test execution estimation 2.3 Test scenario preparation - SIT1 test blocks specification // artefact: RU_PO1C_Test scenario block template.xlsx + How to develop test scenarios.docx - SIT1 test scenarios assembly // artefact: RU_PO1C_Test scenario template.xlsx + How to develop test scenarios.docx - SIT1 test data definition // artefact: RU_PO1C_Test data template.xlsx + How to define test data for a test scenario.docx - SIT1 test scenario preparation progress monitoring // artifact: RU_PO1C_Scenario preparation progress.xlsx 2.4 Dependencies definition - SIT1 test execution pre-conditions // artefact: SIT1 prerequisites status.xlsx - SIT1 test environment // artefact: SIT1 prerequisites status.xlsx 2.5 Test execution management - SIT1 test execution planning and resource allocation // artefact: RU_PO1C_Test execution plan and status.xlsx + How to plan SIT1 test execution? - SIT1 test execution coordination // artefact: RU_PO1C_Test execution plan and staus.xlsx + How to execute SIT1 test ? 2.6 Defect reporting // artifact: this document - Defect reporting ECC // artefact: How to report defects for ECC and legacy systems.docx - Defect reporting legacy // artefact: How to report defects for ECC and legacy systems.docx - Defect fixing process // artefact: How defects are fixed.docx 2.7 Test results reporting // artefact: Project progress dashboard.xlsx 3. Test organization 3.1 Testing resources to be allocated - Consultants and business analysts // artefact: this document 3.2 Roles and responsibilities // artefact: this document 3.3 Communication plan - SIT1 coordination + Triage // artefact: this document 4. SIT1 test success criteria// artefact: this document 4.1 Test entry criteria 4.2 Test success criteria 4.3 Test exit criteria 5. Test tools // artefact: this document
1 Introduction (1/2) The purpose of this document is to describe the approach to PO1C SIT 1 Functional and Archiving test – planning activity:
1 Introduction (2/2) This document describes: • Test Governance = test processes to achieve test success criteria, metrics and artefacts • Test Organisation = test project actors, roles and responsibilities
2.1 SIT1 test scope definition • 99 scenarios in scope for SIT1 • 126 blocks from which the scenarios will be assembled • the test will be planned out of this scope • new scenarios and blocks will be treated as additional scope The list of test scenarios and the blocks they contain can be found in artefact: RU_PO1C_Test scenario design.xlsx Path:
2.2 Test preparation estimation (1/3) • 1 step in the block = 6 min. • 121 blocks with 10 steps on average = 121 hours • 3 hours to assemble 1 scenario incl. Test data x 102 scenarios = 362 hours • review and rework 102 scenarios x 30 min. = 51 hours • total 121+362+51 +10% = 587 hours • 587 hours / 17 consultants / 50% allocation = 8,6 weeks The progress of test preparation can be found in artefact: RU_PO1C_Scenario preparation progress.xlsx Path:
2.2 Test execution estimation (2/3) • 99 scenarios x 51 blocks (in average) x 10 steps (in average) = 50490 steps • 1 step = 10 min. to execute • 50490 steps x 10 min. = 8415 hours • 8415 hours / 17 consultants 50% allocation + 3 SKU teams 50% efficiency = 21 weeks
2.2 SIT 1 test estimation total (3/3) With current resources • 8,6 weeks (test prep.) + 21 weeks (test exe) =29,6 weeks (with 50% resource allocation) • we have 10 weeks from now (1/05/2014) in project plan • Mitigation?
2.3 SIT1 Test block specification process (1/4) • Test bocks are building blocks of test scenarios • Each block describes the test steps required to test a specific functional area • Each block is in essence a small test case with steps and expected results • Test scenarios are assembled from test blocks • Blocks are developed by functional consultants • Blocks are stored in e-room 80.11 – 02 Test Blocks Library artefact:RU_PO1C_Test scenario block template. xlsx artefact:RU_PO1C_How to develop test scenarios.docx Path:
2.3 SIT1 Test scenario assembly process (2/4) • Test scenarios are assembled from blocks • Blocks are copy/pasted from the blocks excel sheet into the scenario sheet. • Blocks may be modified to fit the test scenario • Manual steps or other extra steps my be added to the scenario • Test scenarios are stored in e-room 80.11 – 04 E2E Scenario Library artefact: RU_PO1C_Test scenario template. xlsx artefact: RU_PO1C_How to develop test scenarios.docx Path:
2.3 SIT1 Test data definition process (3/4) • Test data is defined in a separate excel sheet for each scenario • Test data is defined for each scenario for each step • Ensure that you specify only test data that will be available in SIT1! • Available test data for ECC can be found in XXX • Available test data for Legacy systems can be found in XXX • NB For each test run a separate test data sheet must be created!! • Test data sheets stored in e-room 80.11 – 04 E2E Scenario Library artefact:RU_PO1C_Test data template. xlsx artefact: RU_PO1C_How to develop test scenarios.docx Path:
2.3 Test scenario preparation monitoring (4/4) • Test scenario preparation is monitored by monitoring block development and scenario development • For each block and each scenario a deadline is assigned when it should be ready • We monitor progress per team on a week by week basis The plan and progress of test preparation can be found in artefact:RU_PO1C_Test scenario design.xlsx artefact:RU_PO1C_Scenario preparation progress.xlsx Path:
2.4 SIT1 Test environments and peripherals (1/2) • ECC Environment • Q21-500 SIT1 / DR • Legacy environments • Peripherals • Printers • 1 unit Zebra label printer • 1 unit FPrint-55 check-printer (Felix) • 1 unit OKI MX-1150 (high-speed dot matrix printer) • On 15th of May I’m waiting the delivery of (I got a confirmation from procurement department today): • 1 unit Epson DFX-9000 (low-speed dot matrix printer) • And last one, by the end of May: • 1 unit OKI MX-8150 (the new version of high-speed dot matrix) • Handhelds
2.4 SIT1 Test execution pre-conditions (2/2) • SIT 1 is scoped and scenarios are developed • ECC environment is ready • ECC data are agreed and loaded • Legacy environments are ready • Legacy environments are connected to ECC • Legacy data are agreed and loaded • All peripherals are available and connected to ECC • Adequate test execution resources incl. Legacy testing are secured • Ways of working for execution, co-ordination and defect handling are agreed • All test resources have logged in to ALM and have access • ECC and legacy environments and data are verified artefact:RU_PO1C_SIT prerequisutes status.xlsx Path:
2.5 SIT1 Test execution planning (1/4) • Test execution planning and resource allocation is based on the assumption that a scenario will be tested block by block, with one tester per block. • Scenarios are listed with blocks • Each block is assigned a name given test executor (1 block = 1h to execute) • PMO assigns for each person for each week the test allocation % • E2E leads or consultants mark each RICEF in scope as critical / non critical – where critical = no workaround • Each test executor is then assigned which blocks he/she can/should test – on a daily basis based on allocation % • Test scenario execution order is based on the RICEF delivery dates, taking account critical/non critical RICEFS The execution planning can be found in artefact: RU_PO1C_Test scenario design.xlsx – “SIT1 resource planning” tab RU_PO1C_How test execution is planned.docx Path:
2.5 SIT1 Test execution and co-ordination (2/4) • Test execution during SIT1 is co-ordinated dynamically based on actual situation using a Activity-board • Each tester is assigned a number of blocks within scenarios to test. The tester find his/her blocks to test in the “Test scenario design” file in tab “SIT1 resource planning” • An Activity-board is created on a wall using deck-tape. • Each scenario is printed as a number of blocks on business-card sized queue-cards, each block consisting of scenario name + block name + block sequence within scenario on each card • The cards are places in plastic pockets attached to the wall on the left hand side of the activity board • 5 columns are created: Tester; In progress; Blocked by defect; Done w. Workaround; DONE • Pockets are also placed on the right hand side of the Board to collect the DONE blocks.
2.5 SIT1 Test execution co-ordination (3/4) • Allocation of tasks during execution is done as follows: • Testers find “their” scenarios and blocks to test in the “Test scenario design” file. • The left hand pocket holds the backlog of all tasks. A tester takes a card i.e. Block that he/she is testing from the stack and places in column “In progress”. When the block has been tested the card is placed in column DONE (using sticky tape). • If block is tested with workaround or if it is tested with non-blocking defect – the next block can be taken and the queue card is placed in corresponding column. • This signals the next tester that the next block (which now is on top of the stack in the left hand side pocket) can be tested. • If a scenario is blocked by a defect the card is placed in column Blocked by defect. • When all the queue-cards from the left hand side are taken – the scenario is tested
2.5 SIT1 Test execution co-ordination (4/4) • Testers place their queue-cards in column “DONE” to see workload. • Cards are moved from columns to right hand side pockets by test manager • The topmost cards in each left hand side pocket, are the blocks ready to be executed. Each tester can take a block and put it on his/her “In progress” column. Thus “reserving” the block to him/her. • In this way – it is possible to manage workload dynamically on a running basis based on actual situation “on the ground”. Instructions for test execution are found here: artefact: RU_PO1C_Test scenario design.xlsx – “SIT1 resource planning” tab RU_PO1C_How to execute SIT1 test.docx RU_PO1C_How SIT1 execution is co-ordinated.docx Path:
2.6 Defect reporting SAP (1/3) • 1 step in the block = 6 min. The progress of test preparation can be found in artefact: RU_PO1C_Scenario preparation progress.xlsx Path:
2.6 Defect reporting Legacy (2/3) • 1 step in the block = 6 min. The progress of test preparation can be found in artefact: RU_PO1C_Scenario preparation progress.xlsx Path:
2.6 Defect fixing process (3/3) • 1 step in the block = 6 min. The progress of test preparation can be found in artefact: RU_PO1C_Scenario preparation progress.xlsx Path:
2.7 Test result reporting (1/1) • 1 step in the block = 6 min. The progress of test preparation can be found in artefact: RU_PO1C_Scenario preparation progress.xlsx Path:
3.1 Testing resources (1/1) • 1 step in the block = 6 min. The progress of test preparation can be found in artefact: RU_PO1C_Scenario preparation progress.xlsx Path:
3.2 Roles and responsibilities (1/1) • 1 step in the block = 6 min. The progress of test preparation can be found in artefact: RU_PO1C_Scenario preparation progress.xlsx Path:
3.3 Communication plan (1/1) • 1 step in the block = 6 min. The progress of test preparation can be found in artefact: RU_PO1C_Scenario preparation progress.xlsx Path:
4.1 SIT1 entry criteria (1/1) • 1 step in the block = 6 min. The progress of test preparation can be found in artefact: RU_PO1C_Scenario preparation progress.xlsx Path:
4.2 SIT1 success criteria (1/1) • 1 step in the block = 6 min. The progress of test preparation can be found in artefact: RU_PO1C_Scenario preparation progress.xlsx Path:
4.3 SIT1 exit criteria (1/1) • 1 step in the block = 6 min. The progress of test preparation can be found in artefact: RU_PO1C_Scenario preparation progress.xlsx Path: