1 / 13

St. Louis Airport Authority (SLAA) Airport Experience Project

St. Louis Airport Authority (SLAA) Airport Experience Project. Kwame Building Group Program Manager. Yaphett El-Amin MWBE Program Manager. SLAA Airport Experience Minority Goals-25% Women Goals-5% for Design and Construction Projects. Work Completed within Two Phases Phase 1

nickolas
Download Presentation

St. Louis Airport Authority (SLAA) Airport Experience Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. St. Louis Airport Authority (SLAA)Airport Experience Project Kwame Building Group Program Manager Yaphett El-Amin MWBE Program Manager

  2. SLAA Airport ExperienceMinority Goals-25%Women Goals-5%for Design and Construction Projects • Work Completed within Two Phases • Phase 1 • Gateway Monuments and Wayfinding • Terminal Renovation • Concourse Renovations • Phase 2 • Arrivals Drive • Canopy

  3. Airport Experience Project Phase 1 • Seven Design Elements • Ticketing Dome Ceilings* • Entry Monuments and Access Roadway Signs* • Bag Claim Carrousels and In-Feed Conveyors • Terminal Architectural Renovations* • Terminal MEPSS Renovations and Improvements* • Concourse Architectural Renovations • Concourse MEPSS Renovations and Improvements • Design continuing through 2008 with Construction packages in 2008-2010 * represents packages with selected design firms

  4. Ticketing Dome Ceilings • Re-surface interior of four (4) domes • Smooth surface painted in a bright white • Repair skylight frames (as necessary) • Alternate to replace skylights with more transparent material • Teng and Associates Design Firm

  5. Entry Monuments & Access Roadway Signs • Install three (3) monuments on Interstate-70 at Cypress, Airflight and East Entry • Coordinate regional wayfinding with MoDot • Provide new roadway signage scheme along Lambert Blvd. and Airflight Drive • Apple Designs Design Firm

  6. In-Bound Bag Claim Devices and Conveyor Feeds-Design Build • Demo and replace six existing in-bound passenger bag claim devices and two (2) oversize claim devices • Demo and replace conveyor feeds from ramp • Install air curtains to reduce drafts and odors • Re-do existing architecture above bag claim devices to visually open hall • Electrical infrastructure upgrades to support new conveyors and carousels

  7. Terminal Architectural Renovations • Ticketing Hall, Mid-Level Departures Hall and Baggage Claim-Arrivals Hall • Floor, wall and ceiling coverings and finishes • Renovated restrooms + two new Mid-Level restrooms • Relocated C/D Security Checkpoint • Post-security food and retail node • New ticketing case work, back walls and video monitors • New baggage service offices • Wayfinding signage • Teng & Associates Design Firm

  8. Terminal Mechanical, Electrical, Plumbing and Special Systems Renovations • Ticketing Hall, Mid-Level Departures Hall and Baggage Claim-Arrivals Hall • MEPSS benchmarking, renovations and enhancements • Lighting, HVAC, plumbing, electrical systems • Fire, security, CCTV, paging special systems • Burns & McDonnell Design Firm

  9. Concourse Architectural Renovations Concourse A,B,C Public Circulation Areas and Holdroom Ceilings • New floor, wall and ceiling finishes • Renovated restrooms • New signage

  10. Concourse Mechanical, Electrical, Plumbing and Special Systems • Concourses A,B,C, Public Circulation Areas • MEPSS benchmarking, renovations and enhancements • Rework Lighting, HVAC, plumbing, electrical systems • Rework fire, security, CCTV, paging

  11. Seizing the opportunity for Success Airport Experience Project • Start Early • Reach out to others, do not wait until the last minute to show interest in the project • Be knowledgeable of St. Louis City requirements on SLAA Projects • Research other firms • Know who the players are in your industry • Establish relationships with potential Primes “Success is where preparation meets opportunity.”

  12. Meeting and ExceedingMWBE Goals • Prime Companies • Familiarize yourself with SLAA requirements for counting participation, ex. Only Certified MWBE companies located in the city of St. Louis will be counted toward goals. • Seek to create meaningful partnerships with MWBEs consider Joint Ventures or Mentor Protégé relationships as creative ways to meet and exceed the MWBE goals. • View goals as a HELP, not a hindrance. • MWBE Companies • Pursue a long term relationship with Prime. Deliver quality work with competitive pricing. • MWBE Program is not a set aside. Goals assist you to the door. You must open it.

  13. For Additional Information St. Louis Airport Authority (314) 551-5000 www.mwdbe.org Board of Public Service (314) 622-3535 www.stlbps.org Airport Experience MWBE Program Manager Yaphett El-Amin (314) 551-5041 ysel-amin@lambert-stl.org