10 likes | 130 Views
V0 electronics milestones. End 2004: electronics concept finalization (PMT, ‘shoebox’, FEE) CIU design prototype in test (charge, time, pre-process of triggers) January 2005: CCIU and TTCIU prototype design started (final trigger signal, collection of the data, …interface TTC/FEE)
E N D
V0 electronics milestones • End 2004: electronics concept finalization(PMT, ‘shoebox’, FEE) CIU design prototype in test(charge, time, pre-process of triggers) • January 2005: CCIU and TTCIU prototype design started (final trigger signal, collection of the data, …interface TTC/FEE) • July 2005: CCIU and TTCIU prototype realization • End 2005: CIU, CCIU, TTCIU protypes tested Design review • January 2006: CIU, CCIU, TTCIU final design starting • June 2006: electronics construction • End 2006: electronics test, calibration, connection to CTP electronics ready for installation in ALICE • Engineers: Y. Zoccarato, W. Tromeur, C. Combaret FEE meeting, 10 December 2004