1 / 17

Get Quality Preparation with Scrum.org Professional Scrum Product Owner (PSPO I) Certification

Click Here---> http://bit.ly/36T9KX3 <---Get complete detail on PSPO I exam guide to crack Professional Scrum Product Owner. You can collect all information on PSPO I tutorial, practice test, books, study material, exam questions, and syllabus. Firm your knowledge on Professional Scrum Product Owner and get ready to crack PSPO I certification. Explore all information on PSPO I exam with number of questions, passing percentage and time duration to complete test.

nidhisigzen
Download Presentation

Get Quality Preparation with Scrum.org Professional Scrum Product Owner (PSPO I) Certification

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. How to Prepare for Scrum.org PSPO I Certification? PSPO I Certification Made Easy with ProcessExam.com.

  2. Scrum.org PSPO I Exam Summary: Exam Name Professional Scrum Product Owner I Exam Code PSPO I No. of Questions 80 Passing Score 85% Time Limit 60 Minutes Recommended Practice Exam Professional Scrum Product Owner I (PSPO I) Practice Test Sample Questions Scrum.org PSPO I Exam Sample Questions and Answers Exam Fee USD $200 Enjoy success with ProcessExam.com

  3. Scrum.org PSPO I Syllabus Content: Syllabus Topics: Understanding and Applying the Scrum Framework Developing People and Teams Managing Products with Agility Enjoy success with ProcessExam.com

  4. Scrum.org PSPO I Training: Recommended Training: Professional Scrum Product Owner Enjoy success with ProcessExam.com

  5. Tips to Prepare for PSPO I: ● Perform enough practice with ProcessExam.com for Professional Scrum Product Owner I certification subjects. ● Understand the all Syllabus Topics. ● Perform online practice exams for Professional Scrum Product Owner I on ProcessExam.com. ● Identify your weak areas from practice test and do more practice with system. Enjoy success with ProcessExam.com

  6. Scrum.org PSPO I Sample Questions Enjoy success with ProcessExam.com

  7. Que.: 01. A Product Owner is entitled to postpone the start of a new Sprint after the conclusion of a previous Sprint for the following reason: (choose the best answer) Options: a) The Product Owner has not identified a Sprint Goal. b) The Quality Assurance department needs more time to make the previous Increment "Done". c) There is no acceptable reason. A new Sprint starts immediately after the conclusion of the previous Sprint. d) Not enough Product Backlog items are "Ready". e) The stakeholders are not happy with the value produced in the previous Sprint. Enjoy success with ProcessExam.com

  8. Answer: c) There is no acceptable reason. A new Sprint starts immediately after the conclusion of the previous Sprint. Enjoy success with ProcessExam.com

  9. Que.: 02. When should the Sprint Goal be formed? Options: a) During the Sprint Planning session b) A Sprint Goal is not required in Scrum c) At any time throughout the Sprint d) During the previous Sprint during the Product Backlog refinement session e) Before Sprint Planning so that the team can start planning Enjoy success with ProcessExam.com

  10. Answer: a) During the Sprint Planning session Enjoy success with ProcessExam.com

  11. Que.: 03. What pre-conditions must be fulfilled in order to allow Sprint Planning to begin? (choose the best answer) Options: a) A fully refined Product Backlog b) Formal budget approval to conduct another Sprint c) A clear and non-negotiable Sprint Goal d) A clear but negotiable business objective for the Sprint e) Enough "Ready" Product Backlog to fill the Sprint f) There are no such pre-conditions Enjoy success with ProcessExam.com

  12. Answer: f) There are no such pre-conditions Enjoy success with ProcessExam.com

  13. Que.: 04. The Development Team finds out during the Sprint that they aren't likely to build everything they forecast. What would you expect a Product Owner to do? (choose the best answer) Options: a) Re-negotiate the selected Product Backlog items with the Development Team to meet the Sprint Goal. b) Cancel the Sprint. c) Change the Sprint Goal. d) Inform management that more resources are needed. e) Skip Product Backlog refinement activities. Enjoy success with ProcessExam.com

  14. Answer: a) Re-negotiate the selected Product Backlog items with the Development Team to meet the Sprint Goal. Enjoy success with ProcessExam.com

  15. Que.: 05. When can the Product Backlog be updated? (choose the best answer) Options: a) Never, unless agreed to by the change request b) At any time when done by the Product Owner or at the Product Owner's discretion c) Only after a Sprint Review if agreed to by the stakeholders d) Only during Product Backlog refinement sessions if the Product Owner is present Enjoy success with ProcessExam.com

  16. Answer: b) At any time when done by the Product Owner or at the Product Owner's discretion Enjoy success with ProcessExam.com

  17. Follow Us on: Enjoy success with ProcessExam.com

More Related