1 / 23

FP420 Connection Cryostat Mechanical Design & Construction

FP420 Connection Cryostat Mechanical Design & Construction. Key capabilities of CERN TS/MME. CONTENT. Mechanical design & construction Key capabilities of CERN TS/MME. 1. DESIGN. 2. CONSTRUCTION. FP420 versus DFB ATM Pre-design Version # 1 Pre-design Version # 2 Mechanical analysis

niran
Download Presentation

FP420 Connection Cryostat Mechanical Design & Construction

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FP420 Connection Cryostat Mechanical Design & Construction Key capabilities of CERN TS/MME

  2. CONTENT Mechanical design & constructionKey capabilities of CERN TS/MME 1. DESIGN 2. CONSTRUCTION • FP420 versus DFB ATM • Pre-design Version #1 • Pre-design Version #2 • Mechanical analysis • Pre-design Version #3 • Open issues • Main processes involved • Schedule and possible lead times • Cost drivers • DFB ATM assembly experience 3. CONCLUSION • Advantages with CERN TS/MME • Required framework conditions FP420 Manchester Workshop - December 2006

  3. FP420 versus DFB ATM • Continuity of the X and C lines • Higher contraction of the busbar lines • Fixed point to be relocated • Longer interconnection bellow length • Detector constraints (accessibility, precision) • Radiation shielding Distribution Feed Box Arc Termination Module FP420 Cryostat FP420 Manchester Workshop - December 2006

  4. Pre-design Version #1 • Dipole cold foot to replace compensation system • Couple two DFB ATM • Allow contraction of the BB line FP420 Manchester Workshop - December 2006

  5. Pre-design Version #2 • Redesigned supporting beam • Double cold feet to free space for line X FP420 Manchester Workshop - December 2006

  6. Version #2 – Displacement analysis VACUUM CONDITION FP420 Manchester Workshop - December 2006

  7. Version #2 – Displacement analysis VACUUM CONDITION + INTERCONNECTION at cold (operation conditions) FP420 Manchester Workshop - December 2006

  8. Version #2 – Reaction analysis Cold condition (vacuum, bellow force) Bellow force - 10’000 N Reaction y 55’000 N Reaction z 70’000 N Reaction z - 32’500 N FP420 Manchester Workshop - December 2006

  9. Pre-design Version #3 • Two lowered supporting beams • One single piece FP420 Manchester Workshop - December 2006

  10. Version #3 – Open issues & next steps • Detector supported by the cryostat: need to deal with movements during cooling down and operation • Need of additional central fixed point and supporting jack • Use the transport buggies and the lifting beams of the DFBAs • Pre-design v#3 approval awaited FP420 Manchester Workshop - December 2006

  11. Construction – Processes involved • Machining (both heavy and accurate) • Sheet metal forming (vacuum tanks, piping) • MIG/TIG welding • Thermal treatments / Surface treatments • Mechanical fitting (Beam screen integration) • Metrology / Alignment • Vacuum test / x-Ray inspection • Thermal super-insulation • Electrical insulation assembly and test FP420 Manchester Workshop - December 2006

  12. Scheduleprojectionattempt Green light needed on time to allow the design work to start The production cannot start before the design is fully approved FP420 Manchester Workshop - December 2006

  13. Cost drivers – What helps cutting them • Re-use existent designed parts (cold feet, jacks, dished heads, etc) • Experienced and multi-skilled workforce • Avoid specific tooling • Optimize the logistics between operations FP420 Manchester Workshop - December 2006

  14. CERN TS/MME experience on DFB ATM • Design and mechanical analysis • Full production and assembly of 16 ATM • Budget and time constraints sealed in a interdepartmental workpackage agreement Results: Early deliveries and costs below expectations after the 3 first units Distribution Feed Box Arc Termination Module FP420 Manchester Workshop - December 2006

  15. Shuffling Box assembly FP420 Manchester Workshop - December 2006

  16. Welding of the dished heads FP420 Manchester Workshop - December 2006

  17. Cryostating of the Shuffling Module FP420 Manchester Workshop - December 2006

  18. Thermal Super-insulation FP420 Manchester Workshop - December 2006

  19. Final assembly FP420 Manchester Workshop - December 2006

  20. DFBA (ATM & HCM) Transport FP420 Manchester Workshop - December 2006

  21. Conclusions • Advantages with CERN/TS/MME • Design and construction synergy benefits • Shortened learning curve (skilled resources and appropriate equipment available) • Highly responsive multi-technological environment • Reduction of the logistics time and cost • Design and construction traceability (CDD/ EDMS / MTF) • Required framework conditions • Obtain the formal approval of the pre-design • Obtain the final version of the technical specification • Adopt a workpackage oriented approach combining the mechanical design and the construction FP420 Manchester Workshop - December 2006

  22. The CERN TS/MME Mechanical and Materials Engineering group received the Golden Hadron Award (LHC best suppliers) Fair and efficient partnership with CERN Member States (here: Bulgaria) FP420 Manchester Workshop - December 2006

  23. Thanks for their contribution … • Utilisation des ATM pour le projet FP420 - EDMS 771549 – Thierry Renaglia • Use of the ATM for the FP420 Project EDMS 743628 – Thierry Colombet • General information from the TS/MME ATM assembly team (Said Atieh, Laurent Préver-Loiri, Didier Lombard, and al.) …and thanks for your attention. FP420 Manchester Workshop - December 2006

More Related