80 likes | 232 Views
STEREO SWG #16 March 27-28, 2007 Hilton Garden Inn Greenbelt, MD. STEREO ‘Project’ Status March 27, 2007 M. Kaiser. Handover from Project very smooth (see next) In good financial shape CR not a problem Total through end of mission is fine Debbie Chipouras, Stephanie Gray, Valerie Lewnes
E N D
STEREO SWG #16 March 27-28, 2007 Hilton Garden Inn Greenbelt, MD
STEREO ‘Project’ StatusMarch 27, 2007M. Kaiser Handover from Project very smooth (see next) In good financial shape CR not a problem Total through end of mission is fine Debbie Chipouras, Stephanie Gray, Valerie Lewnes Press/PAO activities doing well Panorama and transit release in early March 3-D release April 23 Senior review next round! Guest investigator proposals due 5/11/2007 Please keep me informed!!
STEREO Organization During Phase B/C/D Project Manager Nick Chrissotimos Deputy Project Manager Jim Adams Deputy Project Manager/Instruments Mike Delmont Deputy Project Manager/Resources Rich Ryan GSFC Procurement Office Rex Elliot Contracting Officer / Julie Janus STP Program Support Office Configuration Management / D. Dusterwald-CSC, L. Hepler-CSC Planning / T. Parr-CSC, K. Milligan-CSC, D. Wicks-CSC, J. Rogers-CSC Business Support/ Mandy Tatum-SERV, Bobbie Power-SGT Business Support Financial Manager Elaine Blazosky Resource Analyst Tracy Felton, Linnette Morales, Beverly Thomas Mission Systems Engineering Systems Engineer/ Shane Hynes – Swales Instrument Systems Engineer/ Lisa Bartusek, Steve Wasserzug-Swales Systems Engineering / Joe Cerullo-ASRC S/W Systems Engineering / Jerry Hengemihle-MTEL General Business Support Jack Arrison-OSC Project Support Manager Leslie Cusick-SGT Project Scientist Michael Kaiser AETD Engineering Support Deputy Proj. Scientist Terry Kucera STEREO Science Center Bill Thompson-EITI System Assurance Systems Assurance Mgr. / Michael Haynes Quality Engineer / Pam Hopkins-HTSI, Larry Gibb-SRSTE Observatory Management Observatory Manager/ Larry Christensen Mark Jarosz Instrument Management IMPACT/ UCB Instrument Mgr. / Lil Reichenthal, Renan Borelli JHU/APL Ed Reynolds, Project Mgr. Parts Assurance Antonio Reyes-OSC Safety Richard Bolt SWAVES/ UMN Instrument Mgr./ Paul Buchanan Reliability Matt Samuel-MUNIZ SECCHI/ NRL Instrument Mgr./ Bernie Klein Software Quality Assurance Mike Garner-HTSI PLASTIC/ UNH Instrument Mgr./ Art Jacques-OSC 25 November 03
Science Teams STEREO Phase E (MO & DA) Management Structure Project Scientist – M. Kaiser Deputy – T. Kucera Resources– D. Chipouras Mission Director – S. Odendahl SSC Director – W. Thompson APL DSN FDF
Future Meetings • Scientific special sessions • Spring EGU, Vienna April 15-20, 2007 (13 abstracts) • Session ST5 “The 3D Heliosphere at Solar Minimum” • Spring AGU, Acapulco May 22-25, 2007 (25 abstracts) • Session SH-02 “STEREO: First Results” • Spring SPD, Honolulu May 27-31, 2007 (TBD abstracts) • Abstracts were due last Wednesday • IUGG, Perugia, Italy July 2-13, 2007 (49 total abstracts) • Session ASIV030 “New Results From Solar and Heliospheric Missions” • SWG • Full SWGs every ~ 6 months (Sept/Oct – volunteers needed) • Topical ‘workshops’ as they arise