An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project SMACC Sixteenth report[20 min]10/01/2014

  2. Activities since last LSC (06/12/2013) • Arc splices installation • By Activities • By sectors • SIT • DFBA • Dashboards • Specials • IFS repair update • Splices in 23 update • S45 He spill test • Dipole diodes (&quad diodes) • Activities for the next 2 weeks • Conclusions

  3. SMACC Main activities for the last 3(5) weeks From last LSC (06.12.2013) All is reclosed but the IC with DFBAK Insulation vacuum leak tested on >3/4 of S56 • Sector 56 : • Final leak test and surface work on DFBAK SHM • Sector 67 : Pressure test planned for 15.01.2014 • Sector 78 (No access in R7 in W51, neither in sector on 6-7.01.2014) • Complete the reconnection of Q5L8 • Final decision on DFBAO repair location • Progress on M leak tests and closure of interconnections • Sector 81 (No access in sector on 6-7.01.2014) • Continue the M linesrewelding • Start M leak tests • Sector 12 • Electricalinsulation • Sector 23 • Unsoldering/Resoldering of splices, • Cu machining • Installation of shunts • Sector 34 • Start Cu machining • Start installation of shunts • Sector 45 • M linesopening  Ready for pressure test next week  Completed  Will be repaired at the surface  90% leak tested, 60% reclosed  2/3 rewelded  > ¼ tested On-going, ≈ 1/2 of the sector done  Completed but few NCs   On-going, > 80% completed  On-going, > 70% completed >25% done   Starting, >10% done  On-going, L5 in priority (He spill test)

  4. SEQUENCE AND STATUS Install DN200 Completed 100 % Completed Completed Open M sleeves Open ICs OK to open > 7.1 sectors 8 sectors 8 sectors Undo / Redo splices ElQC(new splices) Cancelled ≈ 6 sectors Machine Cu ElQCafter Cu mach. ElQC(old splices) ≈6 sectors > 6.5 sectors > 5.8 sectors Consolidate Q diodes Restarted for 3 weeks more ≈ 4 sectors Weld M Leak test M Close IC Final LT Insulate splices ElQCafter shunt Install shunts ≈ 1.7 sector > 5.5 sectors ≈ 4.5 sectors > 5.75 sectors > 2.5 sectors > 3.5 sectors > 3 sectors

  5. SMACC Progress report by activity • Desoldering / Resoldering: Completed in about 6 sectorsequivalent 57 64 • Desoldering in 23 is almost completed • Heavy tooling to transfer around P3 (not a good access) • OK for a restart, time to restart the machines • A bit of margin wrt to Cu machining Courtesy H Prin

  6. Cu machining≈ 6 sect-eq SMACC Progress report by activity 58 Courtesy H Prin / M Dumas

  7. SMACC Progress report by activity • Shunts are installedin ≈ 5.8 sectors-eq (1243 ICs > 70%) • 38 ICs shunted in 4 days (↔≈ 48/week) • Work in sectors 23-34 (No infrastructure at P3) • A few (#7) days ahead of schedule (Mind the last X% effect)

  8. SMACC Progress report by activity • Insulation box: Installed in 4.5 sectorsequivalent • Injected only on Thursday this week : 20 IC (≈ 100/week) due to lack of ecobond (delivered on Wednesday 8.01.2014) • > 100 ICs are ready for injection • Only 5 ICs in 12 are not ready to be injected • Mounting of the boxes is starting in 23 Courtesy H Prin / G Maury

  9. SMACC Progress report by activity • M Welding : ≈ 763 ICswelded, > 3.5 sec-eq: • Machines have been maintained • 81 was not accessible on Monday/Tuesday • Only registered when inspected • 4 leakswerefound end of 2013 (2 in S78 and 2 in S81) • Investigation are on-going (2), requiringdisconnection of main and spool piecesbusbars As presented LSC 4.10.2013 18 weeks @ 51 14 ICS behind forecast 11 weeks @ 34

  10. SMACC Progress report by activity • Quadrupole diodes : On going, for 3 more weeks… • 4 sectors are consolidated (56,67,78 &81) • Delivery from company 2 received and conform • Order to company 3 launched, delivery in February • Not on the immediate critical path for the next weeks, otherwise, fall back solution exists to allow M welding and partial M leak testing • Team worked on dipole diodes in 56 (see later) • Still issues with company 1 Courtesy L Grand-Clement

  11. SMACC Progress report by activity • Reclosure of interconnections : > 2.5 sec equivalentisreclosed • All ICs are reclosed in 56 and in 67 except the DFBAK • Sector 78 was not accessible on Monday/Tuesday • Re-Opened 3 ICs in 56 (dipole diodes)

  12. SMACC Progress report by activity • Final leak test: ≈ 1.7 sec equivalentcompletelyvalidated • 67 is completed • Starting in 78

  13. SMACC Sector 67 • Followed by: • Leak test • ElQA • Flushing • ElQA •  Campaign to fixNCs (leaks, short circuits in diodes) in March 14

  14. SMACC Progress report by sector • Main activities are : • Welding of M lines • Leak test of M lines • Main activities are : • Leak test of M lines • Closure of interconnections • Leak test on insulation vacuum

  15. SMACC Progress report by sector • Main activities are : • Cu machining • Shunt installation • Installation of insulation boxes • Main activities are : • Injection of electrical insulation • Diodes consolidation to start

  16. SMACC Dashboards • Openingiscompleted • Shuntingisslightlyahead on schedule • Confident that the installation of insulation boxes willrecover • Welding rate willincrease, a buffer isavailable • Reclosure: Limited by release rate (and thisweek by access)

  17. SMACC Progress report SIT • SIT • All cryomagnets are reconnected • Team members are partiallyreinforcing the train and the DFBA activities • Intervention on triplet braids to start end of January Courtesy N Bourcey, S Le Naour

  18. DFBA: SMACC Progress report DFBA • Special DFBAs • DFBAK Interlayers leak has finally been localised,  NOT the one to insulation vacuum 10 bellows delivered last week of Dec-13 : 2 are needed per DFBA Leak tested successfully so far Radiographic analysis revealed the presence of porosity/small voids in the welds (acceptable) and of tungsten inclusions (NOT acceptable) Relevant inspection can be carried out at CERN with the required accuracy level Repair procedure of the welds is under definition/validation (EN-MME) •  Identify 4 [2] good units (or repair if needed) •  Impact on the reinstallation of the DFBAK, not (yet) on the S56 schedule • DFBAO Decided to repair it in the surface workshop (same procedure as for DFBAK) • Disconnection is startingTo avoid impacting the global schedule, CSCM has to be cancelled in S78 A Perin / S Atieh / D Lombard

  19. DFBA: SMACC Progress report DFBA Courtesy S Atieh

  20. DFBA: SMACC Progress report DFBA • Standard DFBAs • MSC shunt installation team has been reinforced with 4 additional persons, operational since 10 December. Effect is already visible on broaching/brazing operations. • 62 / 135 splices consolidated, work completed on 4 DFBAs. • Global schedule is being redefined following decision to repair DFBAO in the workshop DFBAA-AB (P1): To beinsulatednextweek, soready for reclosure DFBAC (P2): Pigtailsconsolidated  Progress ishigherthan nominal for standard operations Courtesy A Perin

  21.  Completed  Completed

  22. SMACC Dashboards Baseline: 66.8 % (62.5 %) Completed: 60.3 % (56.6 %) Delay 27 (25) days • Delay stable, Baseline: 62.4 % (55.7 %) Completed: 58.8 % (52.9 %) Delay 9 (9) days  Delay stable • New baseline for DFBA under implementation • Synthetic view is under development • Preliminary forecast done (To be validated) • Impact of bellows W inclusions not included yet • On the critical path, // arcs Preliminary

  23. SMACC Dashboards Progress: Baseline: 64.4% (58.3 %) Completed: 58.4% (53.8 %) Delay16 (15) days Stable ; Δbaseline ≈ Δcompleted

  24. SMACC IFS repair (Last LSC) From last LSC (06.12.2013) • Based on ElQA diagnostics fromoutside • Confirmed • Can befixed in-situ

  25. SMACC IFS repair: Update IFS werereplaced and checked OK Courtesy L Grand-Clement

  26. SMACC Overheated splice repair in 23 In QBBI.B34L3  Validated Seenextpresentation (R Ostojic) Courtesy S Le Naour / A Piguiet

  27. SMACC Sector 45 He Spill test Up to Mid W4: Opening of M lines Removal of electricalinsulation Installation of capture tools PerformElQC of existingsplices W4 (end) : Temporaryrelosure of W-bellows on ≈ 30 Ics Preparation of test W5 : Half of sector (L5) not accessible for AUG tests W6 : He spill test during the nights (Access restrictions)

  28. SMACC Dipole diodes Results from S56 – dipole diode lead R @ RT RHalf-moon < 2 µΩ 308 measurements RHS-BB < 2 µΩ RDiode-HS < 5µΩ Courtesy F Savary

  29. SMACC Dipole diodes : work plan • W51-2013: • Venting of the related vacuum subsectors (VSC) • Establishing cryogenics conditions to allow intervention (CRG) • CW2: • Mo-Tue: Opening of #3 interconnections [W bellows and thermal shields] (MSC-αω) • Wed-Thu: Opening of diode containers and access flange (MSC-Diode team) Then: • Local measurement of the contact resistances (MSC, L. Grand Clement and ElQA) and analysis (on-going) Courtesy F Savary

  30. SMACC Dipole diodes • Dipole diodes current leads willbemeasured in the 8 sectors at warm • Methodwillbe cross checkedwith the outliersidentified in 56 • Duration : ≈ 1 week per sector • Usuallydoneafter 17h • Extra workload for ElQA team • Planned in S81 nextweek • NB: This part of the circuit isalso «checked» by CSCM, presentlyplanned in 2-3 sectors • Tooearlytooconclude; it has to beanalysedwithin the diodes WG (MPE-MSC)

  31. SMACC Quadrupole diodes : on-going cases • @ QBQI.24L1, MQA needs to bereplaced, it has excessive diode to heatsink R: • 19 µΩ (EE025, cathode, heat sink A) • 6 µΩ (EE024, anode, heat sink B) • @ QBQI.8R3, removal to investigate on possible effects of radiations • @ QQBI.7R3, MDA removed to investigate on possible effects of radiations Courtesy F Savary / L Grand-Clement

  32. SMACC Summary on progress Main 13 kA Splices:  Delay stable at 9 days, despite the Christmas break Special Interventions:  Delay stable DFBA:  Good progress on standard consolidation  Special cases (AK/AO) will require extra work  Replacement bellows issue to be followed up SMACC:  About 2.5 weeks Delays are stable Very slightly more than nominal rate achieved these last 15 weeks !

  33. SMACC Main activities for the next 2 weeks • Sector 56 : • Final leak test and surface work on DFBAK SHM • Investigation on dipole diodes • Sector 67 : Pressure test planned for 15.01.2014 • Leak tests, ElQA • Sector 78 • Progress on M leak tests and closure of interconnections • Disconnect DFBAO SHM (Priority to bedefined) • Sector 81 • Complete the M linesrewelding • M leak tests • Sector 12 • Complete electricalinsulation • Progress on quad diodes consolidation • Sector 23 • Cu machining • Installation of shunts • Start electricalinsulation • Sector 34 • Cu machining • Installation of shunts • Sector 45 • M linesopening & ElQC in the zone of He spill test, temporaryreclosure of ICs

  34. Conclusions • Good restart – Accessingwent on smoothly : THANKS • Delays are stable, despite the end of yeareffect • Sector 67 isready for pressure test • Confident that consolidation of splices in the arc canrecover the baseline: Last X % effect… • Tightfollow-up of components for diodes consolidation • Tightfollow-up of standard DFBA splices consolidation • Issues: • Consolidation of specialDFBAs • Repair of NCs in parallelwith production work