DOE-2 Overview and Basic Concepts

DOE-2 Overview and Basic Concepts. Background. US public domain programs from 1970s Post Office program; NECAP (NASA energy-cost analysis program); NBSLD (National Bureau of Standards Load Determination) Cal-ERDA (California + U.S. Energy Research & Development Administration) program

noam
Download Presentation

DOE-2 Overview and Basic Concepts

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. DOE-2 Overview and Basic Concepts

  2. Background • US public domain programs from 1970s • Post Office program; NECAP (NASA energy-cost analysis program); NBSLD (National Bureau of Standards Load Determination) • Cal-ERDA (California + U.S. Energy Research & Development Administration) program • Department of Energy (DOE) funding • First generation DOE-1.4 program (1978) • Later DOE-2.0A, 2.1A, B, C, D, E come out • Program description • http://gundog.lbl.gov/dirsoft/d2whatis.html

  3. Background • Current versions • DOE-2.1E (official), DOE-2.2 & PowerDOE • Maintained by the Simulation Research Group of Lawrence Berkeley National Laboratory (LBNL) • Funded by U.S. Department of Energy (DOE) • Several PC versions & interfaces, e.g. • ADM-DOE2, FTI-DOE, VisualDOE (at a cost) • eQUEST (freeware)

  4. Background • In the past, mainly used by researchers • DOE-2 is powerful but very complicated • Require much input time & detail • Need efforts to learn & to master • In recent years, also used by building designers & energy analysts • Consider as the reference program in USA • Becoming popular internationally (e.g. for developing building energy codes) • Often used for performance-based energy codes

  5. Background • Based on transfer function theory & weighting factor method; in FORTRAN language • Program structure • Building description language (BDL) processor • Error diagnosis & calculate response factors • Simulation subprograms • LOADS – building loads • SYSTEMS – secondary HVAC system • PLANT – primary HVAC system • ECONOMICS – economic analysis

  6. Main Features • Capabilities • Energy conservation studies • Building envelope design (materials, construction, etc.) • Internal loads (occupant, lighting, equipment) • HVAC systems & plant • Building design studies • Daylighting & ventilation design • Energy & environmental systems • Such as cogeneration, desiccant cooling & ice thermal storage • Economic & life cycle analysis

  7. Main Features • Limitations • Cannot model electrical & lift systems • Certain constraints on some building systems • Inflexible FORTRAN structure • Sequential calculation method (L-S-P-E) • Not able to consider heat balance

  8. Input 1 Output Input 2 Simulation Process • DOE-2 input file (BDL instructions) • Input files in ASCII text format • Commands, subcommands & keywords • Basic file structure: • LOADS section • SYSTEMS section • PLANT section • ECONOMICS section (optional) DOE-2 Simulation Engine

  9. Simulation Process • Run periods • Normally whole year (8,760 hours) • May run on shorter period (say, one month) • May carry out simulation for multiple years (if the weather files are available) • Control of simulation process • Base case design • Design alternatives (done with interface program) • Parametric runs & analysis (may be tailored made)

  10. Simulation Process • DOE-2 output reports • Standard reports • Verification reports + Summary reports • For loads, systems, plant & economics • Hourly reports • Very detailed; for checking by advanced users • Program-specific output • Summary graphs and tables • Customised reports • Errors & diagnostics

  11. Simulation Process • DOE-2 output files & reports • Commonly read summary reports: • LS-A (Space Peak Loads Summary) • SS-A & SS-B (System Monthly Loads Summary) • PS-A (Plant Energy Utilization Sumary) • PS-B (Monthly Peak and Total Energy Use) • PS-E (Monthly Energy End Use Summary) • BEPS (Building Energy Performance Summary)

  12. Design Typical Weather Weather Design Load Calculations Energy Calculations Peak Design Loads Equipment Sizes Building Energy and Plant Capacity Consumption

  13. Input Requirements • Input data • Site data • Building type, location, geometry, construction • Weather data: design weather, weather files • Building data • Surface areas, windows, zoning, room shapes • Building materials, mass, finishes, shades • Operating schedules & profiles • Internal loads, design conditions

  14. Input Requirements • Input data (cont’d) • Building systems • HVAC (air side) system type & performance • Lighting & electrical services • Building plant and equipment • Performance of refrigeration, boiler & other plants • Data for economic analysis • Electricity tariffs/rates, fuel prices • Equipment costs, interest rates

  15. Input Requirements • Model zoning (thermal, not geometric) • Should consider thermal loads (e.g. interior-perimeter), occupancy, lighting type and schedule • For existing buildings, refer to actual zoning • Need to simplify the model • Combine zones with similar load and usage • Intermediate typical floors are modelled as one floor • Combine HVAC systems • Sometimes, use ONE zone to quickly calculate the load

  16. Combine several rooms into one zone

  17. Input Requirements • General rules for zoning • One exterior zone per major orientation (4-5 m deep) • One internal zone per use schedule • One plenum zone (if plenum returns) for each air handler • One zone each for special uses • Separate ground and top floor zones