An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Chemical Grouting of Sanitary Sewers Illinois Section CSWEA Collection System Seminar June 11, 2009 Derek J. Wold, P.E. Baxter & Woodman, Inc.

  2. Chemical Grouting of Sanitary Sewers Introduction • Rehabilitation Alternatives • Why use Chemical Grout • Chemical Grout Overview • Specifications • Costs • Case Studies

  3. Chemical Grouting of Sanitary Sewers Introduction • Purpose of Rehabilitation • Structural Repair • Infiltration / Inflow (I/I) Removal • Extend Service Life

  4. Chemical Grouting of Sanitary Sewers Introduction • Rehabilitation Alternatives • Lining (CIPP, Slip Lining) • Pipe Bursting • Open Cut Replacement • Chemical Grouting

  5. Chemical Grouting of Sanitary Sewers Overview • Why utilize chemical grout • Less expensive than other rehabilitation methods • Extends service life • Remove I/I • When to use chemical grout • No structural defects • Joint leaks or root intrusion • No sags

  6. Chemical Grouting of Sanitary Sewers Mainline Sewer Grouting • Equipment • Packer • TV Camera • Gauges • Winch • Types of grout

  7. Chemical Grouting of Sanitary Sewers Service Connection and Lateral Grouting • Equipment used • Access

  8. Chemical Grouting of Sanitary Sewers Specifications • Standards • Rehabilitation of Sewers ASTM 2304. • Sealing Sewer Manholes ASTM 2414. • Specifications • Preparatory Cleaning and Televising • Grout Material • Joint Testing • 3 psi greater than groundwater pressure, or • ½ psi per foot • Maximum of 10 psi • Maximum pressure loss = 1 psi per 15 sec.

  9. Chemical Grouting of Sanitary Sewers Specifications • Joint Sealing • ½ gallon per inch diameter • Pump to “refusal” • Documentation • Joint Sealing Verification • Repeat Joint Testing • Warranty • Retest after 3 year

  10. Chemical Grouting of Sanitary Sewers Specifications • Service Connection Grouting • Test and Seal Specifications • 3 gal per connection • Lateral grouting

  11. Chemical Grouting of Sanitary Sewers Costs • Mainline • Service Tee • Lateral • Manholes

  12. Chemical Grouting of Sanitary Sewers Case Studies • Downers Grove Sanitary District • E1-014 Flow Basin • IM-12A Flow Basin • Village of Lisle

  13. Downers Grove Sanitary District Background • Special unit of local government • Responsible for wastewater collection and treatment • Operates 237 miles of public sewers • Operates 9 pumping stations • Operates one WWTF rated at 11 MGD • 20 square mile service area • Western suburbs of Chicago, Illinois • 21,062 building connections • Serves approximately 62,000 people

  14. Downers Grove Sanitary District35 miles west of Chicago map

  15. Downers Grove Sanitary DistrictSewer Rehab Policy – I/I Reduction • Select Target Rehabilitation Basin • Develop Criteria / Scoring System based on: • Frequency of SSOs • Frequency of Basement Backups • Flow Monitoring Data • System Age

  16. Downers Grove Sanitary DistrictTarget I/I Rehabilitation Basin • Select I-H-9 Flow Basin as first target basin • 188 Building connections • Approx. 8,300 LF of sewer and 32 manholes • Flow Data • 60 gpm ADF to 1,200 gpm peak flow • Preliminary SSES work and results • Flood testing • Smoke testing • Small amount of I/I identified • Inadequate storm drainage

  17. Downers Grove Sanitary DistrictIH-9 Flow Basin • Total Cost – Approx $1,500,000 • Line 100% of mains - $418,000 • Grout or Replace 100% Manholes - $47,000 • Line or replace 96% Services - $1,013,000 • Results • I/I reduced by 60-80 percent • No overflows in I-H-9 flow basin • Unable to produce air tight system • Impact of I/I Removal on inadequate storm drainage

  18. Downers Grove Sanitary DistrictE-1-014 Flow Basin • Basin Characteristics • 8,021 LF of 8-inch VCP sewer • 165 services • 28 manholes • Flow data • ADF = 25 gpm • Peak Flow = 750 gpm • Wetlands

  19. Downers Grove Sanitary DistrictE-1-014 Flow Basin • Grout 100% of mains and manholes • Results • Peak flow reduction of 45% • Costs • $300,000

  20. Downers Grove Sanitary DistrictI-M-012A Flow Basin • Basin Characteristics • 9,442 LF of sewer • 211 services • 34 manholes • Flow data • 50 gpm to 1200 gpm • Compliance Commitment Agreement with IEPA

  21. Village of LisleBeau Bien Area • Project Area • 6,314 LF of 8-inch sewer • 97 services • Rehabilitation • 3,314 LF of grouting • 3,080 LF of CIPP • 88 services grouted • 9 laterals lined • Costs

  22. Questions? • Derek J. Wold, P.E. • Baxter & Woodman, Inc. • 708-478-2090 • dwold@baxterwoodman.com