110 likes | 246 Views
Flexible Budgets. Overhead Cost Management. Chapter 17. Flexible overhead budgets. Basic formula. Flexible overhead budgets. Overhead cost variances. Used for control and evaluation of overhead costs Variable overhead variances Variable overhead spending variance
E N D
Flexible Budgets Overhead Cost Management Chapter 17
Flexible overhead budgets • Basic formula
Overhead cost variances • Used for control and evaluation of overhead costs • Variable overhead variances • Variable overhead spending variance • Variable overhead efficiency variance • Fixed overhead • Fixed overhead budget variance • Fixed overhead volume variance
Variable overhead variances Actual variable overhead Actual activity X variable OH rate Standard activity X variable OH rate Variable overhead spending variance Variable overhead efficiency variance
Fixed overhead variances Actual fixed overhead Budgeted fixed overhead Fixed overhead applied to WIP Fixed overhead budget variance Fixed overhead volume variance
Variable overhead variances $2,785.00 14,270 hours X $0.19 = $2,711.30 14,000 hours X $0.19 = $2,660.00 $73.70 unfavorable Variable overhead spending variance $51.30 unfavorable Variable overhead efficiency variance
Variable overhead variances • VOH spending variance • Total VOH cost is greater than the amount that should have been incurred at the actual hours worked • VOH efficiency variance • Number of hours worked is greater than the amount that should have been worked for the output achieved
Fixed overhead variances $2,840.00 $2,400.00 14,000 hours X $0.15 $2,100.00 $440.00 unfavorable Fixed overhead budget variance $300.00 unfavorable Fixed overhead volume variance
Fixed overhead variances • FOH budget variance • Actual FOH cost is greater than the amount budgeted • FOH volume variance • Volume of output was less than planned