The Desk Jet Supply Chain

The Desk Jet Supply Chain. Vancouver PCAT - printed circuit card assembly and test FAT - final assembly and test 1 week cycle time no inventory Transport To San Jose, 1 day To EU 4-5 weeks To Asia 4-5 weeks. Stock vs Pull. DC’s - Target stock levels Forecasted sales

noma
Download Presentation

The Desk Jet Supply Chain

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Desk Jet Supply Chain • Vancouver • PCAT - printed circuit card assembly and test • FAT - final assembly and test • 1 week cycle time • no inventory • Transport • To San Jose, 1 day • To EU 4-5 weeks • To Asia 4-5 weeks

  2. Stock vs Pull • DC’s - Target stock levels • Forecasted sales • Safety stock to ensure availability • Vancouver - Pull • Replenish DCs to target levels just-in-time

  3. The Physical Supply Chain Supplier IC Mfg US DC Customer Supplier PCAT FAT EU DC Customer Supplier Mech Mfg Supplier AP DC Customer

  4. Variability • Material Availability • Process Yields and Downtime • Transport time to Asia and Europe • Demand

  5. DCs • Standard Process • Receive • Pick • Pack and Label • Ship • Some demand for “integration” • Little support for it

  6. Forecasts • Very bad in Europe • Overstock on some models • Shortages of others

  7. Proposals • New Plant in Europe • More Inventory • Air freight to Europe • More complex forecasting methods • ...

  8. Demand Data