1 / 28

Planning and Execution of Works

Planning and Execution of Works. Bar Charts. What Is a Project?. A project is ‘‘A temporary endeavor undertaken to create a unique product, service, or result’’. (PMI 2008) Key words Temporary Unique

norawhitman
Download Presentation

Planning and Execution of Works

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Planning and Execution of Works Bar Charts

  2. What Is a Project? • A project is ‘‘A temporary endeavor undertaken to create a unique product, service, or result’’. (PMI 2008) • Key words • Temporary • Unique • Any project must have a Starting Point and an Ending Point, and it must have a Deliverable Product or Service that is unique.

  3. Are Projects Unique? • Some people may think of two construction projects as identical just because they have the same design. • In project management, we may have similar projects, but every project is unique. • Differences may come from a difference in location (soil type, weather conditions, labor market, building codes, unforeseen conditions, etc.), in management type and experience, or in circumstances.

  4. Project planning • The process of choosing the one method and order of work to be adopted for a project from all the various ways and sequences in which it could be done’’ (AntillandWoodhead1990). • Those processes performed to establish the total scope of the effort, define and refine the objectives, and develop the course of action required to attain those objectives’’ (PMI). • Project planning serves as a foundation for several related functions, such as • cost estimating, scheduling, project control, quality control, safety management, and others.

  5. Scheduling • The determination of the timing and sequence of operations in the project and their assembly to give the overall completion time. • Project planning answers the questions What is going to be done? How? Where? By • whom? and When (in general terms, the project’s start and end)? • Scheduling deals with “when” on a detailed level.

  6. Planning and Scheduling

  7. WHY SCHEDULE PROJECTS? • There are several parties involved in any project (stakeholders). They all need and benefit from project scheduling but from different perspectives. • Contractors • Owners/Clients

  8. Contractors need project scheduling to • Calculate the project completion date (avoid penalties). • Calculate the start or end of a specific activity. • Coordinate among trades and subcontractors, and expose and adjust conflicts. • Predict and calculate the cash flow. • Improve work efficiency. • Serve as an effective project control tool. • Evaluate the effect of Variations. • Prove delay claims

  9. Owners need Project Scheduling to • Get an idea on project’s expected finish date. • Ensure contractor’s proper planning for timely finish. • Predict and calculate the cash flow. • Serve as an effective project monitoring tool. • Evaluate the effect of Variations. • Verify delay claims.

  10. THE SCHEDULER • A civil engineer, an architect, a computer whiz, a mathematician, a project manager, an artist, or a communicator? • Three types of knowledge that a scheduler must have: • Knowledge of computer software (and perhaps hardware as well) • Knowledge of the principles of scheduling and project control (as part of project management) • Knowledge of the specific technical field, such as service buildings, Railway Constructions, Bridge, Trackworks etc.

  11. What is Project • A project is a set of activities with • A well-defined objective(s) • A target completion date • An estimated budget

  12. Type of Schedule • Written Schedule • Gantt Chart (Bar Chart) • CPM Schedules (Critical Path Method) • Activity on Arrow • Activity on Node AB • PERT • LSM (Linear Schedule Method)

  13. BAR CHART • A graphic representation of project activities, shown in a time-scaled bar line with no links shown between activities. • The bar chart was originally developed by Henry L. Gantt in 1917 and is alternatively called a Gantt chart. • It is very popular in the construction industry—because of its ability to graphically represent a project’s activities on a time scale.

  14. ACTIVITY / TASK • Before a bar chart can be constructed for a project, the project must be broken into smaller, usually homogeneous components, each of which is called an ACTIVITY, or a TASK. • No absolutely correct or incorrect way to break down a project exists. • However, the scheduler should take a balanced approach and break it down into a reasonable number of activities that are easily measured and controlled without being overly detailed.

  15. Fixing False Sealing 3 men x 30 days Start time 3000 board type End time What is Activity • An activity or task is a given kind and amount of work which: • Consumes time • Consumes Resources • has a definable beginning and ending

  16. Activity to Bar Chart • The duration of each activity must be estimated. • Bars are then drawn to show, for each activity, the duration and the starting and ending points.

  17. Bar Chart • STEPS • Analyze the project and specify the basic approach to be used. • Break the project down into a reasonable number of activities to be scheduled. • Estimate the time required to perform each activity. • Place the activities in sequence of time, taking into account the requirements that certain activities must be performed sequentially. • Logical constrain • Resources constrain • If a completion date is specified, the diagram is adjusted until this constraint is satisfied.

  18. Items in Bar Chart • Name of work • Unit • Estimated quantity • Unit cost (optional) • Start date • Finish date • Predecessor • Successor • Calendar • Signatures: Client and Contractor

  19. Bar Chart • Example:

  20. Solution

  21. Alternative Solution

  22. Advantages Of Bar Charts • Simple and Easy to prepare and understand. • No ‘‘theory’’ or complicated calculations are involved. • Anyone can understand them. • They can be prepared anywhere with just a pencil and paper. • Bar charts are time-scaled; that is, the length of a bar representing certain activity is proportional to the duration of that activity. • So, Just by looking at the chart one can get an idea on the duration of each activity. • Bar charts particularly appeal to persons who do not have a technical background.

  23. Disadvantages • Lack of logical representation (relationships): • Why did this activity start on that date? Bar charts do not reveal the answer. It could be a logical relationship, a resource constraint, or a subjective decision by the project manager. • Bar charts do not allow the length of the bars to be subjectively changed or the bars to be moved around to make the chart look or read better. • Difficult to update. • Difficult to find Critical Path. • Bar charts may not be practical for projects with large numbers of activities.

  24. How to identify the Critical path in a Bar Chart • Types of a Project Activity • Critical Activity: if it is delayed, it will delay the project. • Noncritical Activity: it may not delay the project if it’s well managed.

  25. STEPS to identify the Critical Path • Start with the last Activity; Draw a vertical line from the i Node of late Activity. • The activities whose j nodes touch the vertical line, are Potential Critical Activity. • Draw a vertical line from the i node of the new critical activity. • Proceed in this manner until you reach Day 0.

  26. Identify the Critical Path

  27. Effective Use Of Bar Charts • Presentation to Field Staff • Presentation to Management • Identifying delays against base line. • Applying corrective action at site to maintain program and completion date.

  28. THANKS

More Related