An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ATLAS Liquid ArgonCBT-EC2 “crack studies”Goals and Run Plan – Early version J. Rutherfoord & P. Schacht 17 May 2004

  2. CBT-EC2 Goals – SummaryLiquid Argon TDR - 1996 • Study transition at |h| = 3.2 for • ETmiss determination • rms of resolution function • Tails of resolution function • What is probability that jet ET of 300 GeV will be mis-measured with less than 150 GeV? < 1  10,000 ? • Jet tagging efficiency • How low in ET can we still identify jets? J. Rutherfoord

  3. CBT-EC2 Run Plan - Input • FCal community from conference calls • Peter Schacht representing MPI discussions • Everyone is invited to help iterate towards the next version • Further iterations, even during the run, are expected • Run coordinators will implement the plans J. Rutherfoord

  4. CBT-EC2 Run Plan - Overview • Technical run – All systems working • Tune, calibrate, and detect problems • Scan through the ‘crack’ region with electrons and hadrons ***** • Interleave stability checks • Special tests J. Rutherfoord

  5. CBT-EC2 Run Plan - Technical Run • Without beam, check out … • Modules, cold electronics, HV, and cabling  • Warm electronics, trigger, BPCs, etc. • DAQ. Write dummy data. • Exercise offline and monitoring software • Write diagnostics J. Rutherfoord

  6. CBT-EC2 Run Plan – Calibrate detector • Set up up beam line and tune beam • Calibrate separately in EMEC/HEC and FCal • High(?) statistics, all(?) energies • Full transverse acceptance in each of the two systems • Electrons, m’s, and pions (ID p’s or veto p’s?) • 16 time samples, dual gain or autogain (?) • Transverse scan – look for and correct problems J. Rutherfoord

  7. CBT-EC2 Run Plan– Scan the “crack” • Vertical scan (Primary goal of CBT-EC2) • 2 or 3 vertical lines, 2 energies, e’s, p’s, and m’s • ~1 Million triggers at each point on central scan line at one energy • 16 time samples, autogain • Narrow and wide beam • Horizontal scan • In crack region at |h| = 3.2 J. Rutherfoord

  8. CBT-EC2 Run Plan- Stability Checks • At subset of ‘standard grid’ • Every 24 to 48 hours • High energy electrons • Every 2nd check include pion run • Modest statistics J. Rutherfoord

  9. CBT-EC2 Run Plan– Special Tests • Timing studies • Narrow beam, high energy, e’s and p’s • Calibration data over full DAC range • Non-linearities? • 32 time samples to understand signal shapes • Dual gains to set autogain thresholds • Alignment with muons • Switch between + and – beam • Proton data J. Rutherfoord

  10. CBT-EC2 – Yet to do • Better specify each of the tasks • Flesh out details of each of the tasks • Better organize and time-order the tasks • Add to and subtract from the various tasks • Prioritize the tasks • Which are absolutely necessary at all costs? • Which can be dropped if we run out of time? J. Rutherfoord